GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

COMMERCIAL  COURT CASES

IN THE HIGH COURT OF JUSTICE (COMMERCIAL DIVISION) HELD ON 16TH DAY  OF FEBRUARY 2010 BEFORE HER LADYSHIP BARBARA ACKAH-YENSU (J)

 

                                                                             SUIT NO. RPC/331/09

 

 

ALHAJI ALI NAPARI ABUBAKARI      ===             PLAINTIFF

 

VRS

 

DAVIES WINSTON THOMPSON             ===                   DEFENDANT

====================================================

 

 

 

 

JUDGMENT

 

The Plaintiff sued the Defendant for the following reliefs:

 

“  a.  Damages for breach of contract

b.    Payment of 5% of the total cost of bills of quantity as at the time of the abrogation of contract between Plaintiff and Defendant on the Kokrobite site.

c.    An order directed at Defendant to pay all outstanding cost of materials bought by Plaintiff.

d.    An appointment of Quantity Surveyor to assess other related jobs executed by Plaintiff and for the Court to adjudge Plaintiff as entitled 30% thereof at Kaneshie.

e.    In the alternative an order directed that Plaintiff be paid on the basis of quantum merit of other jobs executed.

f.      Immediate payment of the total sum of ¢441,676,000.00 (Four Hundred and Forty One Million Six Hundred and Seventy Six Thousand Cedis) being expenses incurred for all on behalf of Defendant.”

 

From the pleadings and evidence of the Plaintiff, the Plaintiff, a Businessman and Contractor trading under the name and style of Napari Construction Works was introduced to the Defendant by a friend sometime in July, 2006.  The Defendant subsequently offered Plaintiff a construction job at Kokrobite.  Plaintiff stated that he went with the Defendant to Kokrobite and Defendant showed him an uncompleted building which was to be turned into a hotel.  He agreed to do the construction work required and sat down with Defendant’s lawyer to set down the conditions for the work.  The work at Krokobite was thus governed by an agreement which was signed at the Defendant’s lawyer’s office (exhibit “A”). 

 

The conditions for the work included Plaintiff using his surveyor and workers as well as redesigning the house to suit the purpose for which the Defendant wanted to use the property. The agreed total contract sum was GH¢80,000.00 and Plaintiff was to be paid an amount of GH5, 000 per month, in addition to 5% of the contract sum. 

 

It is also Plaintiff’s case that apart from the Kokrobite project, Defendant offered him another job at Orgle Road, North Kaneshie, Accra where he was asked to change the original design of the building and put up a storey building for use as a hotel amongst other things; this was not governed by any formal contract. According to Plaintiff, Defendant was not prepared to sit down and draw up an agreement in spite of all the efforts he made. Defendant, according to Plaintiff, subsequently engaged a new contractor to do the work, without the knowledge of the Plaintiff.  It is Plaintiff’s further case that the Defendant owes him for items he purchased on credit for use on the project, and which Defendant has not paid for.  It is also Plaintiff’s case that he had spent all the money that Defendant advanced to him on the project.

 

Plaintiff called four (4) witnesses who collaborated most of his story.  P.W.1, Clement Amaglo the Quantity Surveyor who did the valuation of the work done at North Kaneshie tendered in evidence his Valuation Report (exhibit “F”).  P.W.2, Haruna Omar Farouk’s evidence was that he was engaged by Plaintiff as a security guard in Defendant’s house at North Kaneshie  for a fee of GH¢200.00 per  month. He also led evidence on the work that he saw Plaintiff do.  He said that apart from doing security work he sometimes carried out mechanical repairs as well as acting as a driver, but he was not paid for four (4) months even though Plaintiff occasionally gave him GH¢10.00 or GH¢20.00 for food.

 

P.W.3, Frederick Kwabena Nyarko, testified that he was a plumber and that Plaintiff gave him a job as a plumber.  He said that after he had submitted estimates to Plaintiff, Plaintiff called him to accompany him to go and purchase some of the items contained in the estimates he submitted.  He also said that he heard Plaintiff asking the shop owner to sell the items to him on credit since he did not have money at the time.  P.W.3 tendered in evidence some receipts as exhibit “G”. He testified that because Plaintiff did not pay for the items he had to return those that had not been used to the owners.  He said he charged GH¢600.00 but the Plaintiff paid him an initial amount of GH¢200 and paid a total amount of GH¢300 in bits and pieces leaving an outstanding balance of GH¢100.00 to be paid to him.

 

Worlanyo Akoto, a refrigerator and air condition mechanic, testified as P.W.4.  He said he first met Plaintiff in 2006, when Plaintiff gave him a job at Kokrobite.  He identified exhibits “C3” and “C4” as the receipts which he gave to Plaintiff after the purchase of materials.  He subsequently moved to North Kaneshie where he carried out the same type of job for Plaintiff.  He stated that he charged ¢17,500,000.00 (GH¢1,750.00) for all the work carried out but had been given part payment of only ¢7,500,000.00(GH¢750.00).

 

Daniel Kofi Akorley, P.W.5, an electrician, testified that he did some work for Plaintiff at Kokrobite in 2006.  He said that they had to partition the rooms and re-position electrical points.  His evidence was that he told Plaintiff that he needed underground cable from the main pole to the meter.  He identified exhibit “C2” as a receipt he gave to Plaintiff.  P.W.5 also stated that he did another job for Plaintiff at North Kaneshie which involved chiseling and running cables.  He said he charged ¢23,400,000.00(GH¢2,340.00) but received only ¢10,000,000.00(GH¢1,000.00) as part payment, leaving an outstanding balance of ¢13,000,000.00 (GH¢1,300.00).

 

The Defendant on the other hand averred that he engaged Plaintiff to undertake some construction work at Kokrobite which was previously being executed by another contractor.  He stated further that five (5) sets of structural designs and drawings were handed over to Plaintiff who advised that a new structural design/drawing ought to be produced to conform to the modeling of the building to include more rooms.  As requested by Plaintiff, Defendant paid ¢3,000,000.00 (GH¢3,000.00) to Plaintiff who acknowledged receipt of same.

 

Defendant averred further that he informed Plaintiff that he and his neighbor, Dr. Seth Oninku, intended to extend electricity to their respective houses at Kokrobite and that they would share the cost equally.  Plaintiff however advised that Defendant should get electricity connected through underground cables because that was cheaper.  He stated that on 26th July 2006, Defendant’s Accountant, Nash Sam, paid to William Dodd, a representative of his neighbour Dr. Oninku, the sum of ¢15,320,000.00 (GH¢1,532.00) which represented Defendant’s initial electricity to the two neigbouring houses; Plaintiff witnessed the acknowledgement.

 

Due to the need to pay additional amount to cover the cost of extending electricity to the two houses, Defendant on 28th July 2006 gave to and authorized Plaintiff to pay to William Dodd aforesaid the sum of ¢3,400,000.00 (GH¢340.00).  Defendant averred further that the entire extension of electricity to the two neigbouring houses was carried out by the Electricity Company of Ghana (ECG).  Defendant also averred that Plaintiff received an amount of ¢190,000,000 (GH¢19,000) for the purchase of the needed materials but failed and/or was unable to render an account of same.

 

With regard to the North Kaneshie property, Defendant averred that he engaged Plaintiff to furnish a room for Defendant to live in; to build a supermarket; and renovate the main house, but Plaintiff did none.  Defendant averred further that he asked Plaintiff to construct a store in place of the demolished boys quarters so that Defendant could put some personal effects he had imported into the country in there, but Plaintiff failed to construct same. Defendant’s further case is that he saw a security man named Farrouk at the site but did not know the conditions under which he was employed. 

 

Defendant has counter-claimed for the following:

 

(i)           An account of all sums received and paid by Defendant, whether by himself, Nash Sam or Yaw.

(ii)          An order for payment by the Plaintiff to the Defendant of all sums found unaccounted for on taking such account.

(iii)        A return of the structural designs and drawings of the Kokrobite house which are in the possession of Plaintiff.

(iv)        Damages for their detention.

(v)         Further or other relief, including all further necessary or appropriate accounts, inquiries and directions.

(vi)        Costs.

 

The Defendant adduced evidence through his Attorney, Daniel Holomah (D.W.1).  His evidence was that he got to know Plaintiff when he was working on the North Kaneshie Project.  He was however aware that Plaintiff worked on a site purchased by Defendant at Kokrobite.  D.W.1’s further evidence was that Plaintiff was to receive GH¢5,000 every month and received a total amount of GH¢20,000.00 covering a period of four (4) months.  He tendered in evidence receipts to cover the amount of GH¢20,000.00 (exhibits “2” series).

 

It was D.W.1’s further evidence that Defendant could not provide structural designs to Plaintiff because they were with the previous contractor.  Defendant therefore gave GH¢3,000.00 to Plaintiff, which payment, Plaintiff acknowledged (exhibit “4”).  With regard to the connection of electricity, it was D.W.1’s evidence that Plaintiff was given money to extend electricity to the site but officers from ECG  came to remove the underground cable because it was allegedly illegally connected.  D.W.1 tendered in evidence a receipt for GH¢1,532 (exhibit “5”) given to Plaintiff for the electricity connection.  Furthermore, an amount of GH¢340 was paid to Plaintiff to be refunded to Defendant’s next door neighbour, Dr. Oniku, D.W.1 tendered in evidence a receipt from Plaintiff acknowledging the said payment – exhibit “6”. 

 

According to D.W.1, it was Plaintiff who advised Defendant to buy the North Kaneshie property.  He stated that unlike the Kokrobite project, there was no written agreement for the North Kaneshie project.  The oral agreement nonetheless was that Plaintiff was to turn some of the rooms into self-contained rooms; he was to replace the boys’ quarters with a storey building as storage facility; a supermarket and a restaurant. Plaintiff however only “broke down the boys’ quarters, did the concrete and mounted pillars”. Plaintiff was to receive GH¢5,000 every month through Defendant’s Accountant, Nash Sam, and received a total of GH¢30,000 for the North Kaneshie project.  Plaintiff however submitted receipts for only GH¢150,000 (exhibits “3”, “3A’ and “3B”).  And when Defendant returned from the U.K., Plaintiff could not account for the GH¢30,000.00 paid to him.

 

D.W.1 stated that the items that were allegedly purchased on credit by Plaintiff were not brought to Defendant’s attention.  He also stated that when the Defendant was coming to Ghana, he wanted two (2) rooms to be made ready for him and his nephew, so he gave the equivalent of GH¢5,000.00 in pounds sterling to be used to buy items like bed sheets and to furnish the rooms.  Plaintiff however submitted receipts for the purchase of one king size bed bought for GH¢180, and domestic carpets bought for GH¢355 (exhibits “7” and “8”). D.W.1 also testified that Defendant lodged in a hotel when he came from the UK because the rooms he was expecting to be ready for his use were not.  He stated further that it was when Defendant visited the site that he saw a gentleman living in a room on the 2nd floor and he was introduced as keeping watch over the materials Plaintiff had bought.

 

Defendant’s 2nd witness was Nash Sam (D.W.2).  He stated that he was employed as an Accounts Officer at the Defendant’s company Lion Star Limited.  He corroborated most of D.W.1’s evidence.  He said he paid to Plaintiff an amount of GH¢5,000 a month between August and December, 2006.  He also said that Plaintiff did not do the work at Kokrobite as agreed to in Exhibit “A”; he did not complete the work.  While the work at Kokrobite was ongoing, Plaintiff advised Defendant to buy the North Kaneshie property and without any authority from Defendant, Plaintiff stopped working on the Kokrobite project and started working on the North Kaneshie project.

 

Defendant also subpoenaed Kwaku Owusu Sekyere (D.W.3), a Quantity Surveyor, to come and give evidence.  Mr. Owusu  Sekyere was appointed as a Referee at the Pre-Trial stage to value the works done by Plaintiff.  He however was not able to present a report on the due date and the Pre-Trial was closed.

 

D.W.3’s evidence was that at a meeting held between him and the parties herein, he drew up a schedule of the works done by Plaintiff which the parties were in agreement, and the works being disputed.  These documents were tendered in evidence as exhibits “9” and “10” respectively.  These documents were given to the parties for their perusal and signature but only Defendant signed it; Plaintiff refused to sign it.  D.W.3’s further evidence was that his next line of action if the document had been signed would have been to go to the site, take physical measurements and to come up with “quantities representing the items of work”. D.W.3 said that he, together with the parties, nonetheless decided to go ahead with the measurements pending the Plaintiff signing the documents. Despite the fact that both parties had agreed on the date to meet at the site, Plaintiff did not turn up.  D.W.3 stated that as a result of this he had not quantified the work done up till now.

 

A cardinal rule in civil cases is that he who asserts must prove; this is trite learning.  By virtue of the Evidence Decree, 1975 (NRCD 323) parties assume the burden to discharge the burden of persuasion (or legal burden) as well as the evidential burden to discharge the burden of proof on them.  Thus certain issues must be proved by a party if he is to succeed in an action.  The legal burden of proof will generally be on the party asserting the affirmative of such an issue. A party bearing the legal burden on a particular issue will also bear the evidential burden on that issue. 

 

The general principle as stated by Aikins  JSC in Ababio v. Akwasi III [1994-1995] Ghana Bar Report Part 2, 774 is that it is the party who raises in his pleadings an issue essential to the success of his case who assumes the burden of proving it.  The burden only shifts to the defence to lead sufficient evidence to tip the scale in his favour when on a particular issue the Plaintiff leads some evidence to prove his case.  If the Defendant succeeds in doing this, he wins, if not he loses on that particular issue.

 

In this instant case Plaintiff is alleging that Defendant is in breach of the two (2) contracts between the parties herein, and that Defendant owes him monies for the work he has done. Plaintiff claims he expended an amount of GH¢22,050.40 on the Kokrobite project whereas Defendant only paid him GH¢19,000. He is also claiming that he is entitled to be paid 5% of the total cost of the project. With regard to the North Kaneshie project, it is Plaintiff’s claim that the work done was valued at GH¢41,704.10, but Defendant only paid him GH¢30,000.  Defendant on the other hand is alleging that Plaintiff did not do the works as agreed. These are the main issues on which the parties have burdens to discharge.

 

From the evidence, the undisputed facts are that the parties signed an agreement (exhibit “A”) with regard to the Kokrobite project.  The North Kaneshie project was however not covered by any written agreement.  Both parties agree that Plaintiff did not complete either job. Plaintiff however alleges that Defendant abrogated the contract covering the Kokrobite project whereas Defendant alleges that it was Plaintiff who did. With regard to the North Kaneshie project Plaintiff alleges that it was Defendant who abrogated the contract, which allegation Defendant denies.

 

I will start with the Kokrobite project. Plaintiff’s evidence as to why he stopped the work was as follows:

 

“My Lord, we agreed that I was going to put up this building within a period of 2 years.  But in total the Defendant gave me one Hundred and Ninety Million Cedis; that was for 4 months.  My Lord after giving me ¢190,000,000 for 4 months, he stopped paying me and he did not tell me anything”.

 

Defendant has however refuted this.  The effect of the evidence of both D.W.1 and D.W.2 was that after advising Defendant to purchase the North Kaneshie property, Plaintiff himself stopped working on the Kokrobite property and started working on the North Kaneshie property.  D.W.1 tendered in evidence exhibits “2”, “2A”, “2C”, “2E” and “2F”, as receipts issued by Plaintiff in acknowledgement of payments made on behalf of Defendant to Plaintiff.  The receipts total GH¢20,000. Plaintiff however explained that one of the payments made to him was for GH¢4,000 instead of GH¢5,000. He said that exhibit “C16”, a receipt for GH¢1,000, was paid for interior doors which were obtained by the previous contractor. The Defendant however asked Plaintiff to issue a receipt for this amount which he obliged. This piece of evidence was not rebutted by Defendant. I will therefore find that Plaintiff was paid a total of GH¢19,000 for the Kokrobite project.

 

Plaintiff is nonetheless claiming that he spent more than GH¢19,000; he is claiming that he spent GH¢22,000 plus; these are covered by receipts which he tendered in evidence as exhibit “C” series. He conceded under cross-examination that Defendant paid to him an amount of GH¢3,000 for the structural designs, but stated that it was only part-payment; he said he spent an additional GH¢1,000. He also said he paid for electricity to be connected to the site, and paid GH¢2,500 for a building permit.  According to him these additional items/works were however not captured in exhibit “A”, but the Defendant authorized him to do the said works.

 

The evidence of D.W.1 and D.W.2 was that Plaintiff was given money for the preparation of the structural designs.  Exhibit “4” is the receipt for the said amount of ¢3,000,000.00 (GH¢3,000).  It was their further evidence that Plaintiff was also given money for electricity to be extended to the site but subsequently officers from the ECG came to remove the wires from the underground cable claiming that it was illegally connected.  Exhibit “5” is a receipt for an amount of ¢1,532,000.00 (GH¢1,532.00) allegedly paid to Plaintiff for extending electricity to the said two (2) houses.  A further amount of ¢3,400,000.00 (GH¢340.00) was paid to Plaintiff to be refunded to Defendant’s neighbour as part of his contribution (exhibit “6”). All these pieces of evidence were not refuted by Plaintiff.

 

D.W.1’s evidence was that the mode of payment as agreed between the parties herein was that Plaintiff was to receive GH¢5,000.00 per month for the work, and he received this amount monthly for four (4) months. He also testified that it was agreed that anytime Plaintiff needed money over and above the amount of GH¢5,000 he was being paid per month, more money would be made available to him. Indeed, clause 4 of the agreement, exhibit “A” states that monies would be advanced to Plaintiff by Defendant at the request of Plaintiff.  D.W.1’s further evidence was that even though all the monies being claimed by Plaintiff were allegedly expended during the period he was still working on the Kokrobite project, he never brought this to the Defendant’s attention. Plaintiff himself had testified that one Yaw was introduced to him in August of 2006 as the person responsible for financing the project during Defendant’s absence from Ghana. So, what prevented Plaintiff from requesting for additional money if he indeed had expended more than he had been given?

 

In the circumstances I will find that Plaintiff has not established that he spent over and above the GH¢19,000.00 paid to him.  I will also find that he did not make any request for additional monies to be paid to him.

 

The agreement signed by the parties, exhibit “A”, indicated in clause “4” that

 

“The Employer shall at the request of the Contractor on monthly basis advance to him for the purpose of enabling him to carry out the works described above Fifty Million Cedis (¢50,000,000.00) per month but not exceeding the whole together with the amount for the time being due to the Employer in respect of building materials the sum of Eight Hundred Million Cedis (¢800,000,000.00)”

 

Plaintiff’s evidence was that the above stated amount was to cover the cost of building materials and hired labour.  And that Defendant was also required to pay him a further 5% of the contract sum for his workmanship.  Clause “5” of exhibit “A” reads as follows:

 

“In consideration of the works to be carried out the Contractor shall be paid an amount not exceeding 5% of the total cost of the works”

 

Defendant’s case as supported by the evidence of D.W.1 and D.W.2 is that the 5% payment being claimed by Plaintiff formed part of the monies paid to Plaintiff.  So, what is the interpretation to be given to the said clause “5”?

 

In the case of BCCI v. Ali [2002] 1 AC 251, Lord Bingham of Cornhill summarized the principles of interpretation as follows:

 

“To ascertain the intention of the parties the Court reads the terms of the contract as a whole, giving the words used their natural and ordinary meaning in the context of the agreement, the parties relationship and all the relevant facts surrounding the transaction so far as known to the parties.  To ascertain the partners’ intentions the court does not of course inquire into the parties’ subjective states of mind but makes an objective judgment based on the materials already identified.”

 

In my opinion, clause 5 refers to the payment of 5% of the total contract sum; that is had he completed the work.  This is because clause “4” specifically refers to the cost in respect of building materials and no one can expect that Plaintiff would work for free simply because he received monies for materials. I will therefore find that Plaintiff is entitled to be paid 5% of the total sum paid to him i.e. GH¢19,000.00.

 

Plaintiff gave his reason for not completing the job as follows:

 

Q:      On the Kokrobite project were you able to complete it?

 

A:      No my lord

 

Q:      What happened?

 

A:      My lord I worked for Defendant on the Kokrobite project between 3 to 4 months.  In the 4th month Defendant did not pay any money to me he didn’t tell me anything, but I went on to do the work.

 

Q:      What happened before you could not complete the Job?

 

A:      My lord according to the Defendant because of the serene atmosphere between him and I in the course of doing the work, at a point in time he wanted to purchase a house and he wanted me to supervise the purchase or see to how he was going to purchase the house and then if there was something to be done on that new house he was going to entrust it on my hand.

 

Q:      I am saying that you had a contract for 2 years on the Kokrobite project, you did the project at a certain point then the man was not paying you and you had to stop the construction and I am saying what happened before you cannot complete the job?

 

A:      My lord because the Defendant did not go according to the agreement that is in respect of monies he was to pay me at the end of every month in order for me to be able to do the work.  He did not go according to the agreement for that matter he put me in tight corner financially.  My lord because he did not comply with the agreement I had even borrow money somewhere to buy some materials to do the work up to a point.

 

Q:      What point did you get to in contract terms if you can give us the percentage of the work, whether 10%, 20%, 30%?

 

A:      My lord I did the work between 30% to 35%.

 

Q:      As at the moment, are you still working at the site?

 

A:      The Defendant did not comply with the agreement and he did not tell me anything and the work had to come to a stand still over a year now.

 

I must state that I do not find Plaintiff’s explanation convincing enough.  D.W.1’s evidence, which I believe, is that Plaintiff virtually walked out of the Kokrobite contract.  This, together with my finding that Plaintiff ought to have requested for additional funds but did not, have made me come to the conclusion that it was Plaintiff who abrogated the said contract.  With regard to the Kokrobite project therefore, I am of the view that it is Plaintiff who is in breach of the contract and therefore cannot be entitled to any award of damages, and I will so find.

 

I shall now move to the North Kaneshie project. Again, it is Plaintiff’s case that Defendant is in breach of the contract between them and that he spent in excess of the amount of GH¢30,000.00 which he received from the Defendant and is therefore claiming 30% of whatever amount is assessed by a Quantity Surveyor to be the cost of the work.  In the alternative, Plaintiff is asking to be paid on the basis of quantum meruit

 

It is an undisputed fact that the North Kaneshie project was not covered by any written agreement/contract.  According to Plaintiff, Defendant did not go according to the promise he made; Defendant refused to formalize the agreement between them.  Plaintiff’s evidence was that the property was originally used as a factory for the processing of wood.  He therefore had to clear all the debris.  He also broke down the boys’ quarters and put up a storey building to be used as a guest house.  Subsequently Defendant requested that the downstairs be converted into a restaurant, and a supermarket.

 

It was Plaintiff’s further evidence that he had the building plan prepared which he tendered in evidence as exhibits “D”, “D1” and “D2”.  Plaintiff stated that Defendant subsequently changed the original plan and so Plaintiff had to pull down some of the structures he had built.  Plaintiff also had to prepare a room for Defendant to stay in and therefore fitted the room with a carpet, fan, bed, mattress; bed spread etc. He stated that he gave the receipt to the Defendant and tendered in evidence a list of works he did as exhibits “E” and “E1”.  Plaintiff also stated that Defendant paid him a total amount of ¢300,000,000.00 (GH¢30,000).  It is Plaintiff’s case that in the course of the work, Defendant engaged another contractor to continue with the work, the reason being that he did not have patience for Plaintiff and could no longer work with him. This has not been refuted by the Defendant.

 

According to D.W.1 however, Plaintiff cannot claim that he spent monies in excess of the GH¢30,000 paid to him because Plaintiff was told that he would be provided with money anytime he needed it and therefore Plaintiff did not have that authority to buy items on credit, and Plaintiff did not bring this to the attention of Defendant.   The further evidence of D.W.1 was that it was agreed between the parties that Plaintiff would be paid GH¢5,000.00 every month by Defendants’ Accountant, D.W.2.  Plaintiff was paid a total of GH¢30,000.  D.W.1 tendered in evidence receipts received from Plaintiff in acknowledgment of monies received by him totaling GH¢15,000.00 (Exhibit “3”, “3A”, and “3B”)

 

It is trite learning that an agreement need not be written.  It cannot be disputed that there was an oral agreement between the parties herein for Plaintiff to do some work on the North Kaneshie property.  From the totality of the evidence adduced, it is my opinion that it was the Defendant who abrogated the said contract.  In my opinion however, Plaintiff has not established that he spent in excess of the GH¢30,000 paid to him.  The Quantity Surveyor’s report, exhibit “F”, indicates that Plaintiff spent a total of ¢417,041,100 (GH¢41,704) thus leaving a balance of ¢117,041,100 (GH¢11,704) to be paid by Defendant to Plaintiff.  In my view however, the Quantity Surveyor relied on figures given to him by Plaintiff but which figures have been successfully disputed by Defendant at the trial. I will consequently not attach any weight to the said report. I will therefore find that Plaintiff has not established that he is entitled to be paid the said amount of GH¢11,704 for materials and hired labour. 

 

Plaintiff is seeking, in the alternative, payment on the basis of quantum meruitQuantum Meruit, as is well known, means “how much is worth”; it is an equitable remedy.  It is a remedy available for quasi contract.  When there are no express contractual terms on remuneration for goods supplied or services rendered, the court will assess an amount which is fair and reasonable on the basis of quantum meruit.

 

As Abban J (as he then was) said in Hammond v. Ainooson [1974] 1 GLR 176 at P.183:

 

“In any case, even if I had found that there had been no concluded and enforceable agreement between the parties as to the amount of allowance the Plaintiff was to receive for her services during the time the boat was under repairs, or for the other consideration supplied by her, I would still have held that the plaintiff could recover on quantum meruit basis for the value of the benefit she conferred on the Defendant and the Defendant accepted.  The principle is that where a person rendered services in pursuance of a transaction, supposed by him to be a contract, but which in truth, is without legal validity, he can recover for the value of his services in quantum meruit.

This implied obligation to pay reasonable remuneration is an obligation imposed by law and not in inference of fact arising from the performance and acceptance of the services.”           

 

In his dissenting judgment in the case of Addison v A/S Norway Cement Export Limited [1973] 2 GLR 151 at 163, Anin J.S. said:

 

“Before I am done, I would wish to observe, purely in an obiter manner, that on the facts of this case and in view of the findings made, that the Plaintiff did perform services for the Defendants and at their request, and that the parties intended that these services should be paid for, an alternative claim for quantum meruit would not be out of order.  Once such a claim is instituted, appropriate evidence may then be led on what is the customary or reasonable commission in the circumstances of the case.  In this connection, some help may be derived from the reported case of Mabsout v. Fara Brothers (Ghana) Ltd and from the decision, and in particular the dictum of Greer LJ in Craven-Ellis v. Canons, Ltd, where he stated:  ‘the obligation to pay reasonable remuneration for the work done when there is no binding contract between the parties is imposed by a rule of law, and not by an inference of fact arising from the acceptance of service or goods.”

                   

The evidence adduced by the Plaintiff and Defendant’s witnesses is that the monies received by Plaintiff in respect of the North Kaneshie property were for materials. I will find that in the circumstances of the instant case it will be equitable or in conformity with natural justice for the Plaintiff to be paid some amount as workmanship on a quantum meruit basis since there is no figure to be relied on in arriving at how much Plaintiff should be paid. 

 

Plaintiff however did not lead any evidence as to what is customary or reasonable amount in the circumstances of this case.  Plaintiff also did not cooperate with the Court appointed referee to do a valuation of the work done. The evidence placed before the court is that another contractor has taken over the job and therefore I cannot even order that a valuation of the work done by the Plaintiff be done.  I will therefore award what I think is reasonable, i.e. GH¢5,000 for the work done on the North Kaneshie property.

 

Is Plaintiff entitled to an award of damages for Defendant’s breach of the contract for the North Kaneshie project? In the case of Adae v. Eyiah [1972] 2GLR, 358 Abban J (as he then was) held that in building contracts, the contractor is entitled to an uninterrupted possession of the site for the purpose of carrying out the works in the contract.  Thus the driving away of the workmen of the Defendant therein from the building site amounted to repudiation and the Defendant in those circumstances was entitled to treat the contract as discharged by the said breach. His Lordship held further that the failure to complete the building was not due to the default of the Defendant.  It was rather the Plaintiff who made it impossible for the Defendant to complete the work; and the Defendant was therefore excused from the consequences of not completing the building.

 

I agree with his Lordship and have already made a finding that the failure of Plaintiff herein to complete the North Kaneshie project was not due to the default of Plaintiff; he was prevented from doing so.  Defendant was therefore, in my opinion, in breach.

 

In the case of Delmas Agency Ghana Limited v. Food Distributors International Limited [2007-2008] SCGLR, 748, it was held that general damages is such as the law will presume to be the natural or probable consequence of the Defendant’s act.  It arises by inference of the law and therefore need not be proved by evidence.  The law implies general damage in every infringement of an absolute right.  The catch however is that only nominal damages are awarded.  Where the Plaintiff has suffered a properly quantifiable loss, he must plead specifically his loss and prove it strictly.  If he does not, he is not entitled to anything unless general damages are also appropriate. I will award Plaintiff general damages of GH¢3,000.00

 

In conclusion, I will hold that Plaintiff is not entitled to the reliefs being sought except an order for Plaintiff to be paid GH¢3,000 on the basis of quantum meruit; and GH¢5,000 as general damages for the North Kaneshie project.

 

As stated earlier, Defendant has counter-claimed. In my opinion, however Defendant has not established his counter-claim for an account and payment by Plaintiff because Defendant has not proved that Plaintiff is under any obligation to account for monies paid to Plaintiff under the agreements between the parties. There should be a reason for asking Plaintiff to account for monies paid to him; for instance if Defendant claims that Plaintiff received more than was agreed under the said agreements. Defendant has not made any such claim. In the circumstances I will find that Defendant is not entitled to these reliefs and accordingly dismiss the said counter-claim.  I will however order the return to the Defendant of the structural designs and drawings of the Kokrobite house which are in the possession of Plaintiff.  Since Defendant has established that he paid for the designs/drawings,  I will nonetheless hold that Defendant is not entitled to damages for the detention of the said drawings.

 

I will not make any award as to costs. Since I have found that both parties have breached one contract or the other, and both parties have succeeded in some of their respective claims, I think it is just fair that both parties should bear their own costs.    

 

 

 

                                                                   (SGD)       

                                                BARBARA ACKAH-YENSU (J)

JUSTICE OF THE HIGH COURT

  

COUNSEL

ADJEI LARTEY                    -        PLAINTIFF

J.H. SENOO                          -        DEFENDANT

 

 
 

Legal Library Services        Copyright - 2003 All Rights Reserved.