GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

COMMERCIAL  COURT CASES

IN THE HIGH COURT OF JUSTICE (COMMERCIAL DIVISION) HELD IN ACCRA ON  14TH JANUARY 2010 BEFORE HER LADYSHIP BARBARA ACKAH-YENSU (J)

 

SUIT NO.RPC/233/08

 

 BODYSHAPERS LIMITED                                               ===  PLAINTIFF

 

                                                          VRS.

 

GHANA TELECOMMUNICATIONS LIMITED                  ===  DEFENDANT

 

 

=======================================================

 

 

 

I

 

JUDGMENT:

 

Bodyshapers Limited (Plaintiff) has sued Ghana Telecommunications Limited (Defendant) for the following:

 

1.       An order for the payment of special damages of GH¢72,381.60 by the Defendant to the Plaintiff being the amount paid to the contractor as mobilization for the construction for a Bill Printing facility for Defendant at Abelenkpe in Accra.

 

2.       General damages for breach of contract.

 

3.       Interest on the said amount from 15th December 2004 up to the date of final payment.

 

4.       Costs.

 

By the pleadings, it is Plaintiff’s case that following discussions between its Managing Director and the Chief Executive of Defendant, it wrote to the Defendant making a formal offer for the construction of a Bill Printing facility, which was to be rented out to Defendant.  The Defendant accepted the offer and requested that Plaintiff start the mobilization since time was of the essence.  According to Plaintiff, Defendant requested Plaintiff to start the work whilst they worked on the lease covering the land on which the facility was to be put on.  It is Plaintiff’s case that Defendant has breached the agreement between them and has caused huge financial loss to Plaintiff.

 

Defendant on the other hand contends that Plaintiff made representations to the Defendant that Plaintiff had a leasehold interest in a parcel of land at Abelenkpe.  It was based on these representations that Defendant entered into discussions with Plaintiff to construct the building in question to house the Defendant’s Bill Printing machines.  In the process of conducting due diligence, Defendant discovered that Plaintiff had no interest in the said land, and further that Defendant was only incorporated to undertake health related activities

 

From the reliefs being sought Plaintiff’s have to first prove that there was a contract, which contract was breached by the Defendant.  The general position of the law is that it is the duty of a Plaintiff to prove his case; i.e. he must prove what he alleges.  The burden only shifts to the Defendant to lead sufficient evidence to tip the scale when on a particular issue the plaintiff leads some evidence to prove his claim.  See Ababio v. Akwasi III [1994-95] Ghana Bar Report, Part 2, 774.

 

To prove Plaintiff’s assertions, the General Manager of Plaintiff Company, Henry Darko (P.W.1) tendered in evidence Plaintiff’s offer letter (exhibit “A”) in which Plaintiff proposed a rental fee of US$8,000 per month to be paid two (2) years in advance.  P.W.1 also tendered in evidence Defendant’s letter of acceptance (exhibit “B”). 

 

P.W.1 also led evidence with regard to mobilization funds paid to the contractor who undertook the project.  He tendered in evidence a statement of details of the said payments together with the payment vouchers – exhibit “C” series;  the total amount was ¢723,816,000.00.  P.W.3 (John Lomotey Tei) is the contractor who undertook the project and he confirmed that exhibit “C” series were the payment vouchers issued in relation to the job he did.  Exhibit “D” is the “Agreement to enter into a lease for constructing an office and a Bill Printing facility at S.C.C. yard, Abelemkpe, Accra.” Exhibit “D” is however not signed.

 

Ghassan Laba (P.W.2), Managing Director of Moon Beam Limited testified that it was his company that was known to Defendant.  Since Plaintiff company was a sister company and unknown to Defendant, Defendant asked Moon Beam Limited to guarantee Plaintiff, which they did.  P.W.2 tendered in evidence, the said guarantee as exhibit “E”.  Moon Beam also provided an indemnity (exhibit “F”) to Defendant.

 

There may be said to be three basic essentials to the creation of a contract; agreement, contractual intention and consideration.  From the evidence I have examined so far, I will find that the main elements of a contract were satisfied.   Exhibit “A” referred to discussions between the parties and Plaintiff stated that it was formally submitting its proposals to Defendant.  After listing the facilities to be provided in the building, Plaintiff then stated that “our offer for the above facility is US$18,000 per month, payment to be made 2 years in advance”.  The Defendant in exhibit “B” referred to exhibit ‘A’ and stated categorically that; “we are pleased to confirm that we accept your offer as stated in the letter and kindly ask you to draw up a lease agreement accordingly”.  This is an unequivocal acceptance of the offer made by the Plaintiff to Defendant regarding the construction of the building; and it is binding on the parties.  The Defendant did not make a counter offer nor did it make a conditional acceptance of Plaintiff’s offer.

 

So, did Defendant breach the said agreement as Plaintiff is alleging?  Plaintiff is contending that it refused to sign the agreement because Defendant had unilaterally changed the term of the agreement that Defendant would pay two years’ rent advance to one year’s rent advance. On the other hand, Defendant is contending that Plaintiff represented certain facts to it which were untrue. And that it was based on these representations that they accepted Plaintiff’s offer.  The position of the law is that where a person, by his act or statement causes another to believe a thing to be true and to act on that belief to his detriment, the truth of such a thing will be conclusively presumed to be true in law against the party making the representation; Section 26 of the Evidence Decree, 1975 (NRCD 323). 

 

A representation is a statement of fact that is made by one party to another intended to induce and that induces the other to enter into a contract.  A misrepresentation is a false statement of fact that is intended to induce and in fact induces another to enter into the contract.  If, therefore the statement is one of opinion only, and not a statement of fact, even if false, there is no misrepresentation.  Secondly, if the statement relates to law or legal effects, rather than it being a statement of fact, there is no contract.  Thirdly, if even the statement was false, but the one alleging misrepresentation was not aware of the statement or did not rely on it, then there is no representation because there was no inducement.

 

The burden of proving that the claimant had actual knowledge of the truth, and therefore was not deceived by the misrepresentation, lies on the defendant; if established, knowledge on the part of the representee is of course a complete defence, because he is then unable to show that he was misled by the misrepresentation. 

 

So, what evidence did the Defendant lead to support this assertion? Kafui Agomeda Tetteh’s (D.W.1) evidence was that, firstly, Defendant realised that Plaintiff was registered as a gym. There is no evidence placed before the Court to indicate that the Plaintiff presented to the Defendant that it was registered as a construction firm only for the Defendant to find out that it was registered as a gym.  It is possible that the purpose for which a company is registered may change but may not be amended in its Regulations.  More importantly, under cross-examination, it was suggested to D.W.1 that Plaintiff got its regulations amended pursuant to the query raised by Defendant.  D.W.1 did not deny this.  Secondly, Defendant asserts that it had received a letter from the Divestiture Implementation Committee (DIC) in reply to their inquiries in which DIC stated that Plaintiff had no right to develop the land which formed part of the erstwhile State Construction Company (S.C.C.) which was under divestiture.

 

With regard to this alleged misrepresentation, it is the Plaintiff’s case that when these matters were brought to the attention of Plaintiff, they took concrete steps to address these concerns, which included, securing a letter from DIC giving them the right to develop the land, subject to the submission of drawings and payment of ground rent to be determined by the Land Valuation Board (LVB).

 

P.W.1 tendered in evidence, exhibits “K” and “L”. Exhibit “K” was a letter dated 18th June 1986, addressed to the Managing Director of Plaintiff Company.  The said letter was from the S.C.C who owned the land.  It was titled “Re:  Application for development of plot at Abelemkpe.  “It stated that the proposal to develop the land at Abelemkpe had been recommended to the Board of S.C.C. for approval.  Exhibit “L” was a follow up letter from S.C.C dated 25th June 2009, in which they referred to exhibit “K”, and informed Plaintiff that the Board of S.C.C had given approval for the development of the land at Abelemkpe.  Subsequently, when S.C.C. was placed under divestiture, Plaintiff again applied and obtained approval to develop the land, from D.I.C.  This is captured in exhibit “M”, addressed to L.V.B, and requesting them to assess the value of the land for ground rent.   Obviously, if Plaintiff had no interest in the said land DIC would not have requested LVB to value the land to determine the ground rent, and copy same to the solicitor for Plaintiff. 

 

P.W.2 also led evidence to show that Plaintiff had good title to the land as he tendered in evidence, exhibit “J”, being a copy of the Lease Agreement, executed between Plaintiff and DIC.   Paragraph 4 of Exhibit “J” reads that; “S.C.C. in July, 1996, granted the Lessee a leasehold interest for fifteen (15) years certain from 10th December, 1996, with an option for a further term of fifteen (15) years”.  Plaintiff also furnished Defendant with exhibits “E” and “F”, which were the guarantee from its affiliated company, and the Indemnity, respectively, to give Defendant the required assurances.

 

It is the Plaintiff’s further case that notwithstanding all the assurances and the steps taken by Plaintiff to perfect its title, the Defendant unilaterally decided to change the terms of the agreement by reducing the rent advance payable, from two (2) years to one (1) year.  Counsel for Plaintiff submits that this amounts to a fundamental breach of the terms of the contract and this is what compelled Plaintiff not to sign the revised agreement.  This is the basis for the reliefs being sought by the Plaintiff.    

The position of the law is that generally, barring fraud, parties to a contract cannot lead oral evidence to contradict, vary, add or subtract from the terms of their written contract.  Oral evidence is admissible to explain (but not to contradict) the circumstances and terms of a document.  In my opinion, Defendant has not adduced sufficient evidence to discharge the burden on it to prove that there were misrepresentations made by Plaintiff to Defendant that warranted the unilateral decision by Defendant to vary the terms of the contract; and I will so find.

 

So, is Defendant in breach of the contract in question? In my view, it is.  And why do I say so? The offer letter (exhibit “A”) contained a provision that; “payment to be made 2 years in advance”.  Defendant accepted this offer and asked Plaintiff to “start the mobilization as soon as possible”, which Plaintiff did.  The subsequent unilateral change in the term to pay the 2 years’ advance therefore constituted a breach which entitled Plaintiff to be discharged of all the remaining obligations created by the contract.  I will therefore find that Defendant did indeed breach the contract in question.

 

Now, one would ask whether Plaintiff itself was in breach of the contract by refusing to sign the agreement and also by not completing the project.  Because, the one seeking to rely on the other’s breach must himself not be guilty of breach in any material way.  In Comet Construction Co. Ltd v. Tema Development Corporation [1965] GLR 66, the respondent sought to rely on a forfeiture clause to terminate the building contract with the appellant on the ground that the appellant had taken unreasonable time to complete the construction of a number of buildings.  But the respondent had itself taken 22 months to make the site available!  The arbitration award in favour of the respondent was therefore set aside.

 

The Plaintiff’s case is that there was an agreement that Plaintiff would start the mobilization, which it did.  It was however the breach of the Defendant that resulted in the agreement not being signed, thus Plaintiff was not able to complete the project because it was cash-strapped.  In the Defendant’s letter of acceptance (exhibit “B”), the last paragraph read as follows:

 

As time is of the essence we would appreciate if you could start the mobilization as soon as possible.  We expect the lease agreement to be executed on or before 15th October, 2004”.

 

The effect of declaring time to be of the essence is to elevate the term to the status of a “condition” with the consequences that a failure to perform by the stipulated time will entitle the innocent party to (a) terminate performance of the contract and thereby put an end to all primary obligations of both parties remaining unperformed; and (b) claim damages from the contract-breaker on the basis that he has committed a fundamental breach of the contract.

 

Is Plaintiff therefore entitled to the special damages of GH¢72,381.60 being claimed? It is trite learning that damages are the normal remedy for a contracting party who suffers a loss not too remote, as a result of a breach of contract by the other party.  Special damages is that precise amount of pecuniary loss which the claimant can prove to have followed from the particular facts set out in his pleadings.  Special damages must be specifically pleaded and evidence relevant to it adduced.

 

In the case of Delmas Agency Ghana Ltd. v. Food Distributor International Ltd [2007-2008] SCGLR 748, the general principle relating to damages was expatiated on.  It was held that general damages are as the law will presume to be the natural or probable consequence of the Defendant’s act.  It arises by inference of the law and therefore need not be proved by evidence.  The law implies general damages in every infringement of an absolute right.  The catch, it was further stated, is that only nominal damages are awarded; where the Plaintiff has suffered a properly quantifiable loss; he must plead specifically his loss and prove it strictly.  If he does, he is not entitled to anything unless general damages are also appropriate.

 

P.W.1 tendered in evidence vouchers for various payments for mobilization, made to the contractor who worked on the project totalling ¢723,816,000.00 (GH¢72,381,600).  The said contractor, P.W.3 testified and corroborated P.W.1’s evidence.  Defendant did not challenge these pieces of evidence.  Indeed, D.W.2, an employee of Defendant Company, confirmed that Plaintiff used its own money to start the project when she testified that the project stalled at some time and Plaintiff was demanding money from Defendant because they had run out of funds.

 

In my opinion, Plaintiff has proved the specific loss it has suffered as a result of the Defendant’s breach and is entitled to an award of GH¢72,381.60 as special damages, and I will so hold.  If money is due, an award of damages can take the rates of interest and inflation into account, for as Taylor JSC said in Sowah v. Bank for Housing and Construction [1982-3] GLR 1324 at p. 1359:

 

“I propose to be guided by my initial inclination, for I am persuaded by the apparent modern approach of the English courts to the view that since money was due at one point in time and it is now being paid at a subsequent point in time, the interest which the money attracts during the period assuming that it is a loan, is, inter alia, a fair yardstick by which to measure to some extent the damages so suffered by the appellant, i.e. the contractor.”

 

I will therefore award interest as prayed, on the said amount.

 

Plaintiff is also claiming general damages.  As stated above, general damages are awarded in respect of such damages as the law presumes to result from the infringement of a legal right or duty; damage must be proved but the claimant cannot quantify exactly any particular items in it.  I will find that Plaintiff is entitled to an award of general damages, and award an amount of GH¢5,000.00.

 

To recapitulate, I will award special damages to Plaintiff in the sum of GH¢72,381.60.  I will also award interest on the said amount at the prevailing bank rate from 15th December, 2004 up to the date of final payment.  General damages of GH¢5,000.00 is also awarded to Plaintiff.

 

Costs assessed at GH¢3,000.00

 

 

 

                                                                        (SGD)

BARBARA ACKAH-YENSU(J)

JUSTICE OF THE HIGH COURT

 

COUNSELS

J. OPOKU BOATENG                   -        PLAINTIFF

FESTUS KAYI                      -        DEFENDANT

 

 

 
 

Legal Library Services        Copyright - 2003 All Rights Reserved.