GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME  JUDGEMENT OF THE COURT OF APPEAL

 

BUSHIE ENTERPRISE v. THE PROJECT MANAGER, NORELEC GHANA & NORLEC GHANA [26/03/2004] CA NO. H1/44/2004.

IN THE SUPERIOR COURT OF JUDICATURE

IN THE COURT OF APPEAL

ACCRA-GHANA

__________________________________

CORAM:   ARYEETEY, J.A. (PRESIDING)

AKOTO-BAMFOR, J.A.

ASARE-KORANG, J.A.

CIVIL APPEAL NO. H1/44/2004

26TH MARCH 2004

BUSHIE ENTERPRISE       ....                                         PLAINTIFF/RESPONDENT

VERSUS

1. THE PROJECT MANAGER, NORELEC GHANA }

2. NORLEC GHANA       ....                                          } DEFENDANTS/APPELLANTS

_____________________________________________________________________

 

ARYEETEY, J.A.

A background to this appeal is as follows: The plaintiff/respondent, as Sub-Contractor, entered into an agreement, exhibit A, with the second defendant/appellant-company, as Contractor, on 15th June 1998 for the excavation of foundations and erection of 221 steel towers for electricity transmission of 34.5 KV line between Kumbungu and Daboya in the Northern Region. The contract price payable to the respondent is stated in the agreement. It is the case of the respondent that the appellants unilaterally reduced the number of towers to be erected to 42 without any justification, which was in violation of clause 1.7 of exhibit A. The respondent contends further that while he was making excavations in respect of Towers Numbers 1-42 the appellants stopped him without giving him the notice required under Clause 1.7 of exhibit A. According to the respondent the termination of the contract by the appellants was also contrary to Clauses 2.1, 3.1. and 3.2. of exhibit in that when the appellants terminated the contract they failed to pay moneys due to him as well as the cost of materials.

Since the respondent referred to Clause 3.1 and Clause 3.2 as having been violated by the respondents I would reproduce them in full for a better appreciation of the nature of his claim. They area as follows:

“3.1 Contractor may, at its option, terminate Sub-Contract at any time in whole or in part by written notice hereof to Sub-Contractor whether or not Sub-Contractor is in default and whether or not Main Contract is subject to termination. Upon receipt of any such notice, Sub-Contractor shall, unless the notice directs otherwise, immediately discontinue works on the date and to the extent specified in the notice, place not further orders or Sub-Contracts for materials, equipment, services or facilities except as may be necessary for completion of such portion of the works as is not discontinued, promptly make every reasonable effort to proceed with cancellation upon terms satisfactory to Contractor of all orders. Sub-Contracts and rental agreements to the extent they relate to the performance of works discontinued and shall thereafter do only such work as may be necessary to preserve to protect works already in progress and to protect materials, plant and equipment at the project site or in transit thereto.

3.2 Upon such termination, Sub-Contractor shall be entitled to be paid the value, calculated on the basis of the payment provisions of the Sub-Contract, of all the works properly carried out on the site by Sub-Contractor together with reasonable costs occasioned by and directly resulting from such termination and not previously paid for, less such sums as Sub-Contractor has already received on account of the work performed. If, at the time of such termination, Sub-contractor has properly prepared or fabricated off the site any goods for subsequent incorporation at the site and if Sub-Contractor delivers such goods to the site or to such other place as Contractor shall reasonably direct, the Sub-Contractor shall be paid for such goods or materials.

Also, according to the respondent even though he was permitted to work on 42 towers which would cost ¢69,416,803.00 he ended up with only 40 and was therefore paid ¢13,360,762.28 less than the contract price. The other assignments carried out by him for which he was not paid by the appellants were excavation works for the foundations and construction of Tower Numbers DE4, DE42, SS104, SS107, SS110, and SS111 at a total cost of ¢10,530,000 as well as survey work in respect of Towers 43 to 164. Therefore in the court below the plaintiff/respondent's claim against the first defendant and second/defendants/appellants jointly and severally was for the following reliefs:

(a) Special and General damages for breach of contract entered into between the plaintiff and 2nd defendant on or about 15th day of June 1998 for the erection of Steel Tower of 34.5 KV Lines between Kumbungu and Daboya in the Northern Region of Ghana.

(b) Balance of payment for work done but which the defendants have not yet paid to the plaintiff.

(c) Cost of Survey from Tower 43 to Tower 164.

(d) ¢400,000.00 being the cost of 4 trips of River Sand.

All along the appellant's stand has been that the reduction in the number of the steel towers to be worked upon by the plaintiff was not a unilateral action by them but was in exercise of their right under exhibit A, which allowed them to incerase or decrease the number of steel pillars to be constructed. According to them the plaintiff indeed agreed to the decrease in the number of steel towers to be erected to avoid the payment of penalties to be incurred if the project is not executed on schedule. That was after they had written to the plaintiff complaining about the unsatisfactory manner in which he carried out the work and instructing him to complete the foundations of Towers Nos. 2 to 41 before 15th July 1998. Even then the plaintiff was unable to complete the work on schedule in spite of several letters written to him cautioning him about the delay. The defendants further contend that they did not terminate the agreement wrongfully and that on the plaintiff's own admission in an agreement on his letterhead dated 12th October 1998, signed by both parties, the agreement was lawfully terminated and both partied were discharged from all further obligations.

The defendants/appellants filed four grounds of appeal namely:

(a) That the judgment is against the weight of the evidence

(b) That the trial judge erred when he held that the defendants had breached the contract agreement executed between the parties;

(c) That the trial judge erred when he found as a fact that the defendants owed the plaintiff ¢13,360,762.28 and ¢10,530,000.00 for works done;

(d) That the trial judge erred in not giving proper consideration to exhibit 2 executed between the plaintiff and the defendant

The plaintiff cross-appealed and his grounds were:

(a) The quantum of damages awarded is too small in view of the fact that the contract entered into by the plaintiff and the defendants provides a penalty clause of 1 to 15 percent of the contract price per week.

(b) The learned judge applied wrong principle in his assessment of damages in this case that has led to a miscarriage of justice against plaintiff/appellant.

(c) The learned judge erroneously considered the principles of vicarious liability and this has led to the erroneous exclusion of the first defendant/respondent from liability in this case.

However it appears from the written submissions of plaintiff's counsel that no attention was paid to the grounds of the cross-appeal. So I take it that the plaintiff does not to pursue the cross-appeal any longer and so what we have to look at are only the grounds of the appeal.

I would first like to take grounds (a) and (b) of the defendants grounds of appeal together, namely: "(a) That the judgment is against the weight of the evidence and (b) That the trial judge erred when he held that the defendants had breached the contract agreement executed between the parties”. It is worthy of note that paragraphs 5-7 of the plaintiff's Statement of Claim specify the Clauses in the agreement, exhibit A in respect of which the defendants' breach of the agreement relates. They read as follows:

“5. By Clause 1.7 of the agreement ‘in the event of default, failure or delay on the part of Sub-Contractor, Contractor may nominate 8 days after prior notice to Sub-Contractor, a specified person, firm or company to carry out any part(s) of the Works where Contractor considers such action appropriate and on receiving contractor’s notice, Sub-Contractor shall leave the site.’

6. When plaintiff was engaged in the excavation of foundation for towers 1 to 42 and the erection of the towers the first defendant without giving the required notice to the plaintiffs stopped them from the excavation of some of the foundations for the towers. This action of the 1st Defendant was in breach of Clause 1.7 of the agreement between the plaintiff and the defendants.

7. The defendants verbally and wrongfully terminated the plaintiff’s Sub-contract contrary to Clauses 1.7, 2.1, 3.1 and 3.2 of the agreement.”

It would be convenient at this stage to look at Clause 1.7 of exhibit A. It reads:

"1.7 Without Prejudice to any other applicable provision herein contained and at the sole option of the Contractor in the event of default, failure or delay on the part of Sub-Contractor, Contractor may nominate 8 days after prior notice to Sub-Contractor, a specified person, firm or company to carry out any part(s) of the Works where Contractor considers such action appropriate and on receiving contractors notice, Sub-Contractor shall leave the site.

After quoting the contents of Clause 1.7 of exhibit A the learned trial judge in his judgment had his to say at pages 75 and 76 of the record of appeal respecting the meaning and effect of the sub-clause as follows:

"Counsel for the defendants submitted that the Contractor has very wide discretion under the contract including this Clause 1.7. Indeed this is true. However, the discretion under this Clause 1.7 is a conditional one. The conditions precedent to the invocation by the Contractor of the discretion under this clause are (1) There must be a default, failure or delay on the part of the Sub-contractor, and (2) There must be 8 days prior notice to the Sub-contractor. The onus is on the Contractor to establish that these pre-conditions existed at the time he purported to exercise his discretion. If both or any one of these preconditions did not exist the exercise by the Contractor of his discretion would be wrongful... At the time the 2nd defendant exercised its discretion to stop the plaintiff from the further works the first precondition did not exist and I so find... There was no evidence before me that any notice of default, failure or delay was given to the Sub-contractor. This is quite understandable. The notice was to be given if there was a default, delay or failure on the part of the Sub-contractor. I have already held that the Contractor had not shown the existence of any default, failure or delay on the part of the Sub-contractor. Hence no notice could properly have been given and I find that no notice had been given when the Contractor suspended all work in respect of the steel towards beyond T42.

In asking the plaintiff not to perform the works beyond T42 the 2nd defendant was unilaterally repudiation the contract, exhibit A, in respect of Towers T43 to T221, i.e. 179 towers in all. The request was in breach of the contract. It was then up to the plaintiff to treat the contract as at an end in respect of T43 to T221 and make a claim for breach of contract later while the contract continued to exist in respect of TI to T42.

Subsequently by exhibit 1 Towers 1 and 42 were also taken out of the contract. This constituted another breach of contract as here, too, the necessary preconditions did not exist for the termination of the contract even under clause 2 or 3.1. For the 2nd defendant to purport to terminate the whole of exhibit A on 12th October 1998 was an exercise in futility. By that date exhibit A had long ceased to exist because of prior breaches by the 2nd defendant.”

In his preoccupation with Clause 1.7 of exhibit A the learned trial judge did not take cognisance of the opening words of the Clause, that is, "Without prejudice to any other applicable provision herein contained". If he had it would have been obvious to him that the defendants' right to exercise his discretion is not limited to the instance depicted in Clause 1.7 of exhibit A. What the learned trial judge sought to do was to fit the conduct of the defendants as depicted by exhibit 1 into the straight jacket of Clause 1.7 which admittedly lists preconditions for the exercise of discretion by the defendants, as amplified by the portion of the judgment of the court quoted above. What the trial judge should have done was to have looked at the whole agreement as suggested by the opening words of Clause 1.7 quoted above. Looking at the contents of exhibit 1, what took place was that the defendants did not terminate the whole of the agreement. They merely reduced the number of steel pillars the plaintiff was to construct. The question to ask is, “Were the defendants by the agreement entitled to do that?” A look at Clause 2.1 of exhibit A provides a clear answer. It reads:

“2.1 In lieu of giving notice of termination, Contractor may notify its decision to take part only of Sub-Contract Works out of the hand of the Sub-Contractor and may by itself, its servants or agents execute, complete and maintain such part and in such event Contractor may recover the cost of so doing from Sub-Contractor, or deduct such costs from monies otherwise becoming due to Sub-Contractor.”

It cannot be denied that exhibit 1 for all intents and purposes did not constitute termination of the contract. It falls in line with what Clause 2.1 of the agreement, exhibit A, which permits the defendants to reduce the number of towers the plaintiff was to construct under the contract without assigning reasons for so doing. However in this case the defendants in exhibit 1 pointed out to the plaintiff, as sub-contractor, his delay in the execution of the contract, which might result in the payment of penalty by the defendants as contractors. From all indications the plaintiff did not challenge the defendants' exercise of their right under Clause 2.1 of the agreement. In fact he initialled the document containing the new arrangement and followed what exhibit 1 required him to do to the letter. The evidence is that he co-operated fully with the defendants and carried out what he was required to do under exhibit 1. It appears to me that the reason why the learned trial judge came to the conclusion that the defendants had breached the agreement was the fact that he restricted himself to the provision in the agreement which relates to termination, that is Clause 1.7 of exhibit A. It is ironical that Clause 1.7 itself by its opening phrase that is: "Without prejudice to any other applicable provision herein contained', puts one on notice that there are other options in the agreement open to the defendants apart from their right to terminate the agreement under specified circumstances stipulated in Clause 1.7 and highlighted in the judgment of the court below at pages 75 and 76 of the record of appeal as follows:

“Counsel for the defendants submitted that the contractor has very wide discretion under the contract including this Clause 1.7. Indeed this is true. However, the discretion under this Clause 1.7 is a conditional one. The condition precedent to the invocation by the Contractor of the discretion under this Clause are (1) There must be a default, failure or delay on the part of the sub-contractor, and (2) There must be 8 days prior notice to the sub-contractor. The onus is on the contractor to establish that these pre-conditions existed at the time he purported to exercise his discretion. If both or any one of these pre-conditions did not exist the exercise of the contractor of his discretion would be wrongful.

As can be seen the defendants in real terms did not purport to terminate the agreement under Clause 1.7 of exhibit A. They exercised their options as permitted by Clause 2.1 of exhibit A and therefore their conduct in reducing the number of towers to be constructed would not amount to wrongful termination of the contract. As shown in exhibit 1 the reduction of number of towers to be constructed by the plaintiff did signify a variation of the terms of exhibit A, which was permitted by Clause 2.1 of the agreement.

I would now have a brief look at grounds (c) and (d) of the grounds of the appeal, which I intend to take together. As a reminder they read as follows:—

"(c) That the trial judge erred when he found as a fact that the defendants owed the plaintiff ¢13,360,762.28 and ¢10,530,000.00 for works done;

(d) That the trial judge erred in not giving proper consideration to exhibit 2 executed between the plaintiff and the defendants. "

As contended by the defendants, when they made their final payment to the plaintiff on 12th October 1998 they entered into agreement not to pursue any more claims. The agreement, exhibit 2, appears at page 87 of the record of appeal on the plaintiff's own letterhead and signed by both parties. It reads:

“AGREEMENT BETWEEN NOROLEC GHANA AND BUSHIE ENTERPRISE

The two companies agreed to solve the issue between them, according to the terms of the Contract No. CB 97143.

NOROLEC paid all the amount according to the work done by Bushie Enterprise, from tower No. 1 to tower 42 excluding tower No. 4 and No. 42. The two companies agreed in principle not to come back for any moneys, and stop all future co-operation "

The defendants' project manager, Stephen Graff, who testified on the defendants' behalf gave the circumstances under which exhibit 2 was made at page 35 of the record of appeal as follows:

"When he was not doing the work we informed him formally in September 1998 that we were terminating the contract; and invited him to our office on 12/10/98 to do the final reconciliation together. He came to the office on 12/10/98. We discussed all the matters in terms of payment, work done and final agreement. Plaintiff issued his final invoice for payment… on 12/10/98 when we met we paid the plaintiff ¢10,300,000 which represents ¢4,800,000.00 as payment of the retention on the previous invoice submitted by plaintiff plus ¢5,500,000.00 to buy some materials from plaintiff. Money paid him included work done by plaintiff. After paying all these monies we signed final agreement specifying that nobody would come back to claim any money.”

The plaintiff has not denied appending his signature to exhibit 2 and did not lead any evidence to suggest that the contents of exhibit 2 should be understood to mean anything other than conveyed by its plain language, namely: The plaintiff was paid what he was entitled to and each party agreed not to pursue any further claim for money. I am therefore of the view that taking into account the contents of exhibit 2, the conclusion of the trial court that the defendants owed the plaintiff various sums of money was erroneous. For the reasons given in this judgment I would allow the appeal and set aside the judgment of the court below. The plaintiff's cross-appeal is dismissed.

B.T. ARYEETEY

JUSTICE OF APPEAL

I agree. I have nothing useful to add.

V. AKOTO-BAMFO (MRS)

JUSTICE OF APPEAL

I also agree.

A. ASARE-KORANG

JUSTICE OF APPEAL

COUNSEL

MISS BRENDA SEMEVOR FOR

EKOW AWOONOR FOR APPELLANT

MR. IBRAHIM MAHAMA FOR RESPONDENT

 

 
 

Legal Library Services        Copyright - 2003 All Rights Reserved.