GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

COMMERCIAL  COURT CASES

 

IN THE HIGH COURT OF JUSTICE (COMMERCIAL DIVISION) HELD IN ACCRA ON  21ST JULY 2011 BEFORE HER LADYSHIP BARBARA ACKAH-YENSU (J)

 

                                                  SUIT NO.OCC/45/09 

CONTINENTAL TERMINALS LIMITED                   ===   PLAINTIFF

 

                                                          VRS.

 

1.   GHANA PORTS & HARBOURS AUTH

2.   JAMES BEN GAISIE

3.   RICHARD DEIH                                        ===  DEFENDANTS

 

=======================================================

 

 

JUDGMENT:

 

The Plaintiff, Continental Terminals Limited, has sued the Defendants, jointly and severally. The 1st Defendant is Ghana Ports & Harbours Authority; the 2nd Defendant is James Ben Gaisie, Estate & Environmental Manager of 1st Defendant Company; and the 3rd Defendant is Richard Deih, General Manager, Estate of 1st Defendant Company.  The reliefs being claimed by the Plaintiff are as follows:

 

1.    Declaration that the Defendants’ refusal to accept payment of rent arrears by the Plaintiff is in breach of section 29 of the Conveyance Act, 1973 (NRCD176).

 

2.   Relief against forfeiture upon such terms as may be just and equitable.

 

3.   An injunction restraining the Defendants from re-entering or re-possessing the demised premises; and

 

4.   Such other relief or reliefs as the justice of the case requires.

 

The Plaintiff’s case as per its amended Statement of Claim is that by a Lease Agreement (“the Lease”) dated 7th September, 2007, the 1st Defendant demised to it a parcel of land at the Tema Port for the construction of a port warehouse and container terminal complex.  By the terms of the Lease, Plaintiff was required to commence development of the demised parcel of land within one year and to complete same within three (3) years. According to the Plaintiff, 1st Defendant approved its structural drawings and Plaintiff proceeded to develop the demised land by clearing it of bush, grading and partly filling the site, and erecting concrete posts along the boundary line of the land.

 

It is however the Plaintiff’s claim that development slowed down considerably due to delay in the disbursement of a term loan facility from the Agricultural Development Bank (ADB) which delay also led to it falling into arrears of rent.  Plaintiff contends that its financial challenges was compounded by the inability of its sister company, Cargo Systems Limited, to fund its project.  Plaintiff further claims that by a letter dated 28th August, 2009 it presented to the 1st Defendant the full payment of its rent arrears as demanded by the 1st Defendant by letter dated 18th August, 2009 but same was declined upon instruction by the 2nd and 3rd Defendants.  Plaintiff also claims that the 2nd and 3rd Defendants are using the 1st Defendant as a cover to deprive the Plaintiff of the lease and to allocate the demised land to their favourites, contrary to Article 284 of the 1992 Constitution.

 

The Plaintiff contends further that the Defendants have threatened to re-enter the demised land and re-possess same and unless restrained by the Court, the Defendants’ conduct will result in consequent inconvenience, hardship and irreparable harm to the Plaintiff.  It is Plaintiff’s further case that it shall be lawful for the 1st Defendant to re-enter the demised land if any covenant on the Plaintiff’s part shall not be duly performed or observed.  However the 1st Defendant failed to exercise that option and on the contrary requested the Plaintiff, by a letter dated 18th August, 2009, to settle its rent arrears and rent advance.  Thus, according to the Plaintiff, the 1st Defendant therefore waived or is deemed to have waived the right to forfeit the lease.

 

The Plaintiff denied receiving the 1st Defendant’s letter dated 26th August 2009 in which the 1st Defendant is alleged to have communicated its decision to re-enter the said land to the Plaintiff.  The Plaintiff contends that if the said letter exists at all, it could only have been created by the Defendants purposely for litigation.  The Plaintiff contends further that the 2nd and 3rd Defendants instructed their subordinate not to receive payment of rent from the Plaintiff when same was presented in their bid to take over the demised land for re-allocation to their favourite nominee.  That, the 2nd and 3rd Defendants were under a duty under the Directive Principles of State Policy, the 1992 Constitution, not to use the cover of the 1st Defendant to act in a manner that was capricious.

 

In their defence, the Defendants contend that 1st Defendant allocated the demised land to the Plaintiff for development of a multi-user distribution centre subject to terms and conditions contained in the offer letter dated 9th February 2006, and which terms were accepted by the Plaintiff per its letter of 22nd February, 2006.  That, on 7th September 2007, the Plaintiff and 1st Defendant executed a Lease.  The Defendant contends that the Plaintiff has breached the terms and conditions of both the offer letter and the Lease Agreement in respect of failure of Plaintiff to develop the land and failure to pay rent during the three(3) year period in accordance with the said terms and conditions.  The Defendants deny, however Plaintiff’s assertion that the accrual of rent arrears and the delay in its development of the land was because of its sister company’s (i.e. Cargo Systems Limited) inability to feed the Plaintiff with funds.  1st Defendant contends further that Plaintiff’s assertion is untrue since the Plaintiff in a letter dated 9th July 2009 to the Minister of Transport admitted facing difficulty in raising the requisite funds to pay its annual rents and also to commence construction on the said land (which letter was forwarded to the 1st Defendant by the Ministry dated 3rd August, 2009).

 

According to the 1st Defendant, the Plaintiff has failed to pay its rent for three (3) years thereby compelling the 1st Defendant to write to the Plaintiff on several occasions demanding settlement of outstanding rent arrears due and owing to the 1st Defendant.  1st Defendant also denies that there has been any development on the said land by the Plaintiff.  According to the 1st Defendant, it approved the development of the land according to Plaintiff’s proposal submitted to the 1st Defendant, and that the Plaintiff never commenced any construction on the said land.  Accordingly, the 1st Defendant on 26th August, 2009 duly notified the Plaintiff of its decision to re-enter the land citing the breach by the Plaintiff of the terms and conditions in the offer letter and the Lease Agreement.

 

1st Defendant contends that the 2nd and 3rd Defendants are its employees who acted in the course of their employment and their being joined as parties to the suit is vexatious and an abuse of the process of court.  The 1st Defendant contends further that since the Plaintiff has failed to develop the said land, same has been re-entered by the 1st Defendant and any relief against forfeiture had been overtaken by the event of re-entry on 26th August 2009, as communicated to the Plaintiff by the said letter.  This information was subsequently communicated to the Plaintiff’s Managing Director, Mr. Osei Sarfo-Bonsu and two other officers of Plaintiff on 28th and 31st August, 2009 respectively when they came to make payment of plaintiff’s rent arrears.  1st Defendant denies that Plaintiff has suffered irreparable harm since no development has taken place on the said land in breach of the terms and conditions governing the Lease.  And that the Plaintiff is not entitled to its claim.  The Defendants thus counterclaimed against the Plaintiff as follows:

 

a.   Recovery of possession of all that piece or parcel of land as leased to the Plaintiff if the Plaintiff has indeed not received the letter of 26th August 2009;

b.   Damages for breach of contract, and

c.   Costs.

 

From the pleadings and the evidence adduced the issues identified by the Court for determination are as follows:

 

1.    Whether or not the Plaintiff’s non-payment of outstanding rent entitled the 1st Defendant to re-enter the land in question and forfeit the lease.            

 

2.   Whether or not the Plaintiff is in breach of the covenant to commence development of the land within one year from the date of right of entry and to complete the buildings within 3 years.

 

3.   Whether or not 1st Defendant has re-entered the land in question and whether the 1st Defendant is entitled to recover possession of the land.

 

4.   Whether or not the Plaintiff is entitled to relief against forfeiture.

 

5.   Whether or not the 2nd and 3rd Defendants used the 1st Defendant as a shield to pursue their private agenda of depriving the Plaintiff of the lease and allocating it to their favourite.

 

 

1.           Whether or not the Plaintiff’s non-payment of outstanding rent entitled the 1st Defendant to re-enter the land in question and forfeit the lease

 

The evidence before the Court is that, the Plaintiff, by a written application dated 2nd November 2005 (Exhibit “1”) applied to the 1st Defendant for lease of land for the development of a distribution centre.  The facilities to be developed were proposed in Exhibit “1” as follows:

 

-      Two warehouses measuring 4,200 square meters in area

-      Open storage areas for holding containers, iron and steel produced and vehicles.

-      Vehicle repair maintenance facility

-      Offices and customs facilities.

 

The 1st Defendant by an offer letter dated the 9th of February 2006 (Exhibit “2”) offered the Plaintiff the land upon the terms contained in that letter.  The Plaintiff accepted this offer by a letter dated 15th March 2006.  Subsequently, the Plaintiff and 1st Defendant executed a Lease Agreement dated 7th September 2007 (Exhibit “G”) for a term of 25 years at a yearly rent of US$34,000.00 or its equivalent in cedis payable half yearly in advance.

 

By clause 2 (a) of the Lease the Plaintiff made a covenant to pay rent in accordance with the terms of the Lease.  The Lease stated clearly in clause 1 that the rent was an annual rent of US$34,000.00 to be paid half yearly in advance by the Plaintiff.  It is not in dispute that over the years the Plaintiff had failed to pay rent in accordance with the terms of the Lease and was therefore in breach of clause 2(a) of the Lease.  The Plaintiff in his evidence in chief admitted that he had received demand letters; Exhibit “7” dated 19th May 2008; Exhibit 8 dated 5th March 2008; Exhibit “9” dated 3rd July, 2008; Exhibit 10 dated 18th February 2009; and Exhibit 11 dated 18th August 2009).  The schedule, Exhibit “13” tendered in evidence by the 2nd Defendant showed that the Plaintiff from the time it accepted the offer of the Lease had paid only US$9,940 out of a total of US$119,000 due to the 1st Defendant for the period July 2006 to December 2009.

 

Clause 5 (a) of the Lease provides as follows:

 

   “(a) If the yearly rent hereby reserved or any part thereof shall be in arrears for three (3) calendar months whether formally demanded or not if the Lessee shall enter into liquidation whether compulsory or voluntary (not being merely a voluntary liquidation for the purpose of amalgamation or reconstruction) or if any covenant of the Lessee’s part shall not be duly performed and observed it shall be lawful for the Authority to re-enter upon the said Demised Premises or any part thereof in the name of the whole and thereupon this Demise shall absolutely determine but without prejudice to the rights of action of the Authority in respect of any antecedent breach of any of the Lessee’s covenants herein contained.”

 

I will therefore find that per the Lease Agreement the Plaintiff’s breach of the covenant to pay rent entitles the 1st Defendant to re-enter the demised land.                                                            

 

2. Whether or not the Plaintiff is in breach of the covenant to commence development of the land within one year from the date of right of entry, and to complete the buildings within 3 years.

 

By clause 2 (d) of the Lease the Plaintiff made a covenant to commence development of the land within one year from the date of right of entry and to complete the building or buildings within 3 years from the same date.  No building was to be developed or altered without the previous approval of the 1st Defendant.  The evidence shows that the 1st Defendant gave the Plaintiff the right of entry onto the land by a letter dated 17th October, 2007 (Exhibit “5”).  The Plaintiff contends that it has not violated clause 2(d) because it had commenced development within the said year by grading and filling the land and putting concrete pillars along the borders of the land.  The Plaintiff, by the rules of evidence has the burden of producing sufficient evidence to persuade the Court that the alleged “development of the demised premises” did take place.

 

In proof of the alleged filling and grading the Plaintiff tendered in evidence through P.W.2 (Solomon Tseh Wuve)  Exhibit “1”, which is the Bill of Quantities dated 29th September 2009 for an amount of GH¢352,888.  According to PW2, this was evidence that the land had been graded and filled.  It is however trite learning that Bill of Quantities “itemises the work described in the drawings and specification” (Halsbury’s Laws of England 4th Edition Vol. 4 (3) Para 11 Footnote 6).  Exhibit “1” is therefore evidence of work yet to be done and not work already done.  The Plaintiff was unable to produce any receipt indicating that any of these items on the Bill had been purchased within one year of 17th October 2007.  Moreover, Exhibit “1” appears to have been prepared one whole month after the original writ was filed.  Indeed, Exhibit “1” was not referred to in the original writ.  After Exhibit “1” was prepared, the Plaintiff amended its writ and made reference to Exhibit “1” It is the view of the Court that Exhibit “1” was prepared purposely for the instant case and can therefore not be relied on.

 

In any case, even if the Plaintiff had established that it did grade and fill the land, and place precast concrete posts round the land, the question is; do these acts constitute “development of the demised premises” within the meaning of the Lease? I would say not.

 

For a better understanding of Clause 2 (1) I shall quote the entire clause as follows:

“To commence development of the demised premises within one year from the date of right of entry and to complete the buildings within 3 years from that same date.  The building or buildings shall be in accordance with the approved building code and regulations and in conformity in every respect with plans, elevations, sections and specifications previously approved in writing by the authority.  No building on the demised premises shall be developed or altered in any manner by the Lessee without obtaining the prior written approval of the Authority.”

 

Applying the basic principles of interpretation to the Lease the parties could only have intended “development of the demised premises” to mean development of the buildings that the 1st Defendant had by Exhibit “5” previously approved.  Any such development of the buildings would be visible for all to see as against the alleged filling or grading of the land, which would not be visible to the eye. 

 

I will thus find that the Plaintiff is in breach of the covenant to commence development of the land within one year from the date of right of entry and to complete the development within 3 years.

 

3. Whether or not 1st Defendant has re-entered the land in question and whether the 1st Defendant is entitled to recover possession of the land.

 

As stated above, Clause 5 (a) of the Lease grants the 1st Defendant the right of re-entry if the yearly rent or any part of it remained in arrears for 3  calendar months whether formally demand or not or if the Plaintiff failed to perform any covenant in the Lease.  It is therefore established that a right of re-entry or forfeiture exists in the Lease.

 

In determining this issue the Court will be guided by the provisions of the Conveyance Decree, 1973 (NRCD 175), Section 29 (1) and (2) of NRCD 175 which provides as follows:

 

“Section 29 – Restriction on Re-Entry and Forfeiture

(1)         A right of re-entry or forfeiture under a provision in a lease fro a breach of a covenant, condition or an agreement in the lease is not enforceable, by the action or otherwise, until

 

(a)         the lessor serves on the lessee a notice,

(i)           Specifying the particular breach complained of,

(ii)          Requiring the lessee to remedy the breach, if the breach is capable of remedy.

(iii)        Requiring the lessee to make reasonable compensation in money for the breach except where the breach consists of a non-payment of rent.

 

(b)  the lessee has knowledge of the fact that the notice has been

      served, and

 

(c) the lessee fails, within a reasonable time after the service of the  

      notice under paragraph (a); to remedy the breach, if it is capable   

      of remedy.

 

And except where the breach consists of a non-payment of rent, to make reasonable compensation in money, to the satisfaction of the lessor, for the breach.

 

(2)           Where the notice is sent by registered post addressed to a person at the last known postal address in the Republic of that person then, for the purposes of subsection (1), that person shall be deemed, unless the contrary is proved, to have had knowledge of the fact that the notice had been served as from the time at which the letter would have been delivered in the ordinary course of post.”  

 

Sections 29 and 30 of NRCD 175 were interpreted in the case of Western Hardwood Enterprises Ltd. & Another v. West African Enterprises Limited (1998) SCGLR 105 where the Supreme Court held as follows:

 

“(4) Section 29 of the Conveyance Decree, 1973 (NRCD 175), required that the lessee be served with notice of the breach of any covenant in the lease complained of, and must have knowledge of the fact that such notice had been served before the right of re-entry could be exercised.  Furthermore, the enforceability of the re-entry or forfeiture under the lease should have been by action or otherwise, and by section 30 (1) where the lessor proceeded by action or otherwise to enforce his right of re-entry or forfeiture under the provisions in a lease or for non-payment of rent, the lessee might either in the lessor’s action or in any action brought by such person for that purpose apply to the court for relief against forfeiture.”

 

So, did the 1st Defendant serve on the Plaintiff a notice of the breaches, and requiring the Plaintiff to remedy the breaches? And is the Plaintiff aware of the service of such notice?  It was the 1st Defendant who made a case for re-entry of the land and therefore bore the onus to prove that it had satisfied the legal requirements.  It is the Plaintiff’s contention that it was only after the receipt of the Writ of Summons and Statement of Claim that the Defendants filed a defence stating for the first time that on the basis of the Plaintiff’s breach of all material conditions in the Lease and in order to restore order, it had decided to invoke its powers to re-enter the land and consequently notified the Plaintiff of its decision to re-enter the land.  1st Defendant however contends that it served several rent demand notices (Exhibits “7”, “8”, “9”, “10” and “11”) on Plaintiff notifying the Plaintiff of its breach of the covenant to pay rent. As already stated the Plaintiff does not deny receiving these notices.  1st Defendant contends further that the Plaintiff continued its violation of the covenant to pay rent and paid only US$9,940 out of the total of US$119,000.00 due to the 1st Defendant for the period July 2006 to December 2009.  By the time the Plaintiff presented the outstanding balance of the rent the 1st Defendant had taken a decision to re-enter the land and refused to accept the balance.

 

The 1st Defendant also contends that it sent a letter to the Plaintiff dated 26th August, 2009 informing the Plaintiff that it had re-entered the land.  However the Plaintiff claims it never received the said letter (Exhibit “14”). I am wondering how come Plaintiff suddenly went to pay the outstanding balance on the rent on 28th August, 2009 and not before.  Exhibit “14”  is dated 26th August, 2009. The evidence is that Plaintiff had received all other communications sent by 1st Defendant to Plaintiff with the exception of Exhibit “14”.  I find that difficult to accept and will therefore find that it is more likely than not that Plaintiff did receive Exhibit “14”.         

 

Counsel for the Plaintiff has submitted in his written address that 1st Defendant’s claim that it has re-entered the land is founded on the misconception that by merely writing and delivering Exhibit “14” giving notice to the Plaintiff that the 1st Defendant’s “had decided to re-enter” the land, the 1st Defendant is deemed to have actually, either re-entered the land and/or effectively forfeited the Lease.  Counsel submitted further that in so far as the 1st Defendant sought by Exhibit “14” to re-enter the land and forfeit the Lease, it was mandatory that  the 1st Defendant  complied strictly with section 29 (1) of NRCD 175 in terms of the content of any such letter.  Among other things, the 1st Defendant was under obligation to specify a particular breach of the parties lease agreement that the tenant had committed.

 

According to Counsel, there must also be a request by the 1st Defendant on the tenant to remedy that alleged breach.  The landlord is also required to give the tenant a reasonable time within which the tenant was to remedy the breach.  Then finally, the landlord is required to demand compensation to be paid by the tenant in appropriate cases.  It is therefore Plaintiff’s position that neither Exhibit “H” nor Exhibit “14” complied with the requirements of law.

 

I beg to differ.  In my opinion what section 29 (1) (a) states is that the lessor should serve the lessee notice; (1) specifying the particular breach complained of.  1st Defendant stated in Exhibit “14” that Plaintiff had not commenced development as agreed in the lease and was in arrears for more than three (3) months, thus satisfying this requirement; (2) if the breach is capable of remedy, requiring the lessee to remedy the breach.  In my opinion, this provision is not mandatory; and (3) (except where the breach consists of a non-payment of rent) requiring the lessee to make reasonable compensation in money for the breach.  It is my opinion that this does not apply in the instant case.

 

In any case even if Plaintiff was not aware of Exhibit “14”, the 1st Defendant per its counterclaim has unequivocally made a claim for recovery of possession of the land has exercised its right of re-entry.

It is settled law that “A writ that unequivocally claims a right to recover possession (as distinct from one which includes alternative claims for injunction based on the lease and its covenants continuing to exist) operates as a re-entry in law and so brings about forfeiture as soon as it is served on the tenant.” (The Law of Real Property, Sir Megarry and H.W.R. Wade, Steven & Son’s Limited, 1984 Pg 672).  In Halsbury’s Laws of England, 4th Edition, 2006 Reissue, Vol.27 (1) para 609 headed; “What amounts to re-entry”. It states as follows:

 

“The terms of proviso for  force-entry that if the landlord elects to determine the lease for forfeiture, he must do so by re-entry which the Landlord may effect by either physically entering the premises with the intention of determining the tenancy or by the issue and service of proceedings for the recovery of possession of the premises... Actual entry is not necessary to take advantage of the forfeiture.  When the cause of forfeiture becomes complete, the landlord may being a claim to recover possession, and the bringing of a claim to recover possession in equivalent to actual re-entry.”

 

 I will therefore find that 1st Defendant, having demonstrated that it has satisfied the preconditions for the exercise of the right of re-entry under section 29 of NRCD 175 and having re-entered the land by counterclaiming unequivocally for recovery of possession, is entitled to recover possession of the land.

 

(4) Whether or not the Plaintiff is entitled to relief against forfeiture.

 

It is trite learning that a lessor may become entitled to forfeit the lease.  Forfeiture prematurely terminates the lease before the expiration of the period created.  A lessor does not automatically become entitled to forfeit a lease for breach of covenant or condition to be performed or observed on the lessee.  The right to forfeit for breach must be expressly contained in the lease otherwise the lessor cannot exercise it.  The right of forfeiture can be enforced by re-entry or by an action for possession.  A lessor entitled to forfeiture can enforce his right by peaceably re-entering the land.  The normal method for effecting a forfeiture however is by an action for possession.

 

In the instant case, I have made a finding that the 1st Defendant has a right to forfeit. The right of forfeiture is one vested in the lessor which he can either exercise or not exercise as he pleases. A lessor may therefore waive his right of forfeiture. Counsel for Plaintiff has submitted that the demand for rent as contained in Exhibits “7”, “8”, “9”, “10”, and “11” amounts to a waiver of the right to forfeit the lease for non-payment of rent.  In my opinion, the 1st Defendant herein would be deemed to have waived its right to forfeiture if it had accepted the rent presented to it on 28th August, 2009. The said exhibits only served as notice to the Plaintiff of the breach of covenant.

 

The issue is whether the Plaintiff is entitled to relief against forfeiture.  The position of the law is that after the lessor has given notice as required and taken steps to enforce forfeiture, the tenant may apply to court for relief against forfeiture. Section 30(1) and (2) of NRCD 175 provides as follows:

 

“Section 30 – Relief against Re-Entry and Forfeiture

“(1)  Where a lessor is proceeding by action or otherwise to enforce a right of re-entry or forfeiture under a provision in a lease, or for non-payment of rent, the lessee of the property and also a sublease of the property comprised in the lease or a part of the lease may, in the lessor’s action or in an action brought by that person for that purpose, apply to the court for relief.

 

(2)  Subject to subsection (1) of section 29, where a lessee applies to the Court for relief, the Court may grant or refuse the relief having regard to the proceedings and conduct of the parties and to the other circumstances.

 

(3)  A Relief granted under subsection (20 may be on the terms as to costs, expenses, damages, compensation, penalty or otherwise, including the granting of an injunction to restrain a similar breach in the future, that the Court in the circumstances of each case thinks fit.

 

(4) Where a sublease applies to the Court for relief, the Court may make an order vesting, for the whole term of the lease or a lesser term, the property comprised in the lease or a part of the lease in that sublease on the conditions as to execution of a deed or any other document, payment of rent, costs, expenses, damages, compensation, giving security or otherwise that the Court in the circumstances of each case may think fit, but the sublease is not entitled to require a lease to be granted to the sublease for a longer term than the sublease had under the original sublease.”

 

In granting the relief, the court takes into account the proceedings and conduct of the parties and all other circumstances.  The court, if it grants relief, may do so on such terms as to costs, expenses, damages, compensation or penalty as it thinks fit.  The court may also grant an injunction to restrain a similar breach in the future if it thinks it is a proper case to do so: section 30(2) of NRCD 175. In the instant suit the Plaintiff is claiming an injunction restraining the Defendants from re-entering or re-possessing the demised premises.

 

Despite the fact that the Plaintiff herein alleged in its pleadings and also tried to demonstrate that it had incurred expenses in a total sum of GH¢655,543.00, P.W.2 testified that over four (4) years, the only amount that the Plaintiff had been able to pay was GH¢5,000.00 allegedly owed to Debrah & Associates.  The cost of the alleged filling and grading of the land, and erection of precast concrete pillars in the sum of GH¢359,565.00 remain unpaid.  The Plaintiff, in my opinion, never demonstrated its ability to fulfil its obligations in the lease.  The Plaintiff did not demonstrate that it was capable of developing the project as stipulated in its proposal.  It would probably have helped the Plaintiff’s case if it had paid into Court the amount of GH¢109,060.00 rent arrears which it had attempted to pay to the 1st Defendant but which had been rejected; but the Plaintiff did not do this.  In my opinion, 1st Defendant was right on refusing to accept payment of the rent since an acceptance would have been deemed as a waiver of its right to forfeit the lease; see Interplast Limited v. Bonsu (1979) GLR 285.

 

The Plaintiff itself stated in its pleadings that the reason for its inability to perform with regard to the development works and payment of rent was due to the delay of the ADB to disburse in a timely manner a term loan facility which the Plaintiff had applied for to undertake the project, with the Plaintiff using the demised property to secure its repayment obligation with the consent and approval of the 1st Defendant given by a letter dated 31st October 2007.  Plaintiff stated further that its “precarious financial position” was compounded by the inability of its sister company, Cargo Systems, incorporated in 2008, to feed the Plaintiff with funds as projected, consequent upon the 1st Defendant’s refusal to allocate cargo to the said Cargo Systems Limited after being licensed as a stevedoring company.  In my view, there is nothing placed before the Court to show that it was a term or condition  of the Lease or the proposals submitted by the Plaintiff that development of the land would only commence when funds had been received from the bank or a sister company. 

 

Furthermore, the 1st Defendant provided whatever assistance it could to the Plaintiff when by a letter dated 31st October 2007 (Exhibit “L”) 1st Defendant gave its consent to the use of the land as security to repay the term loan being sought by the Plaintiff from ADB.  Exhibit “L” at paragraph 2 clearly stated that the grant of consent was “without prejudice to all the terms, conditions, stipulations and covenants” contained in the Lease.  It is also my opinion that by the time the license was issued to Cargo Systems, the Plaintiff was already in violation of clauses 2(a) and 2(d) of the Lease.  The incorporation of this company therefore could not have in any way contributed to the fortunes of the Plaintiff. 

 

In my opinion, Plaintiff did not take any steps which would make it inequitable not to grant this relief. I will therefore find that in the circumstances of the case, the Plaintiff is not entitled to relief against forfeiture.

 

5. Whether or not the 2nd and 3rd Defendants used the 1st Defendant as a shield to pursue their private agenda of depriving the Plaintiff of the lease and allocating it to their favourite. 

 

The Plaintiff’s case is that the 2nd and 3rd Defendants used the 1st Defendant as a shield to pursue their private agenda of depriving the Plaintiff of the lease and allocating it to their favourite.  It is trite learning that he who asserts must prove.  The Plaintiff therefore bore the burden of producing sufficient evidence to prove the allegation  made by him against the 2nd and 3rd Defendants.  In my opinion the Plaintiff did not adduce a scintilla of evidence to prove this allegation.  P.W.1, in his evidence in chief simply repeated the averments pleaded and stated as follows:

 

“We made them parties to the action, in the first place the original demand notice came from the 2nd Defendant office so when we tendered the rent arrears as well as the rent advance the secretary received it stamped as having received the cheques as well as the letter on the same day.  The system is that after you have received you have to send it to the cashier to process the payment.  But when we went to the cashier the cashier said that he has received instructions from the 2nd Defendant not to process it.  I tried to contact the 2nd Defendant on the phone the phone was off, the 3rd Defendant’s phone was off I chase them out the office and outside and later on I was able to get the 2nd Defendant  on the phone.  The 2nd Defendant told me on the phone that it was the 3rd Defendant who instructed him not to process our payment and we suspected that they were up to some tricks because it’s done there projects are taken away from..”.

 

 It has been held in the oft-cited case of Majologbe v. Larbi & Ors [1959] GLR 190, that”

“Proof in law is the establishment of facts by proper legal means. Where a party makes an averment capable of proof in some positive way, e.g. by producing documents, description of things, reference to other facts, instances, or circumstances, and his averment is denied, he does not prove it by merely going into the witness box and repeating that averment on oath, or having it repeated on oath by his witness.  He proves it by producing other evidence of facts and circumstances, from which the Court can satisfy that what he avers is true”.

 

In the circumstances I will find that Plaintiff has not proved its assertion that the 2nd and 3rd Defendants are using 1st Defendant as a shield to pursue their private agenda.

 

1st Defendant has counterclaimed for damages for breach of contract. Counsel for the Defendants, in her written address, submitted that since the Plaintiff failed to give up possession of the land upon determination of the Lease, the 1st Defendant is entitled to damages in the form of mesne profits. I have taken note of the fact that the Defendants’ claim is for damages for breach of contract simpliciter. There is no claim for mesne profits. In any case, in my opinion, Counsel’s submission is misconceived. Where a lessee wrongfully deprives a lessor of his land, the lessor will generally wish to recover the land itself and not the value of the land. Damages will thus generally be limited to loss arising from the period of wrongful occupation by the lessee. Such damages are recoverable in the action for mesne profits, in origin an action of trespass. In the case of Hasnem Enterprises Ltd v IBM World Trade Corporation [1993-94] 1 GLR 172 relied on by Counsel, Benin J quoted Goddard LJ in Bramwell v Bramwell [1942] 1All ER 137 at 138, CA as follows:

 

      “....a claim for mesne profits can be joined with an action for the recovery of land, and mesne profits is only another term for damages for trespass, damages which arise from the relationship of landlord and tenant.”

 

But more importantly, in my view, this suit does not call for a damage claim. This is a case in which the Defendants are resisting a claim for relief against forfeiture, and the Defendants have also claimed for recovery of possession of the land in question. Defendants have succeeded in both, and so what have they lost? It is trite learning that for the court to make an award for damages the Defendants have to establish the basis for damages. There is no evidence placed before the court as to the basis. I will therefore find that Defendants are not entitled to damages.

 

In conclusion I will dismiss Plaintiff’s entire claim.  I find that Article 284 of the 1992 Constitution mentioned in the Plaintiff’s pleadings is misplaced. As a result, there is nothing to be said on this point. I will on the other hand hold that 1st Defendant is entitled to recover possession of the land in question.  Defendants claim for Damages for breach of contract is dismissed.

 

Costs of GH¢5,000.00 awarded in favour of Defendants         

 

                                                                             (SGD)

BARBARA ACKAH-YENSU(J)

JUSTICE OF THE HIGH COURT

COUNSEL

KWAKU PAINTSIL                         -        PLAINTIFF

MARIETTA APPIAH OPPONG    -        DEFENDANTS           

 

Legal Library Services        Copyright - 2003 All Rights Reserved.