Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME   UNREPORTED CASES OF THE SUPREME

COURT OF GHANA 2006

 

IN THE SUPERIOR COURT OF JUDICATURE

THE SUPREME COURT

ACCRA A.D. 2006

 

CORAM:        ATUGUBA, J.S.C. (PRESIDING)

                        MRS.  WOOD, J.S.C.

                        BROBBEY, J.S.C.

                        ANSAH,  J.S.C.

                        ANINAKWAH, J.S.C.

 

                                                                        CIVIL MOTION

                                                                        NO.J4/14/2006

                                                                     20TH DECEMBER  2006

 

DANIELLI CONSTRUCTION  LTD .       …                        APPELLANT

 

                                                                        VRS.

 

MABEY & JOHNSON  LTD.                                 ..                       RESPONDENT

 

 

                                           J  U  D  G   M  E  N  T

 

ANSAH, J.S.C.:  The plaintiff sued the defendant for the following remedies:

            “(1)  The return of its piling hammer and accompanying accessories;

(2)   Payment of accrued charges for hiring the said hammer;

(3)   Damages for breach of contract;

(4)   Damages for wrongful detention of the hammer;

(5)   Damages for failing to pay for using the hammer;

(6)   Damages for wrongfully to return the hammer (sic);

(7)   Massive profit and interest”;

The gist of the case for the plaintiff was that it agreed to give its piling hammer and an Audi saloon car in exchange of the defendant’s Toyota Hilux pick-up and crushing machine.  Whereas it honoured its obligation and delivered the equipment to the defendant, the latter failed to deliver the crushing machine to the plaintiff. The plaintiff thereafter wrote to levy charges for the use of the piling hammer.

            On the other hand, the defendant denied there was any agreement to hire the equipment and asserted it was only an agreement to swap them for each other. The defendant therefore denied liability and rejected invoices the plaintiff submitted for payment, for the reason that it made the piling hammer available for collection by the plaintiff, but it (plaintiff) refused or failed to go for it.

            The trial judge found in his judgment there was a contract of hiring equipment by the parties which, the defendant breached and proceeded to award damages for the plaintiff.  He also ordered the defendant to deliver the piling hammer to the plaintiff at its premises or pay for the cost of the plaintiff retrieving it itself, awarded $300.00 (or its equivalent) per day chargeable from 18th December 1993 to date of judgment as damages, which sum was to attract interest.

            Dissatisfied with this judgment, the defendant appealed against it to the Court of Appeal on as many as nine grounds.  The Court allowed the appeal in part and awarded damages for the cedi equivalent of $890,411 for the plaintiff.

            Once again, the defendant felt aggrieved by the judgment of the Court of Appeal and appealed to this court on the grounds that:

 

“(1)  The conclusion that the appellant breached the swap agreement is wrong and not supported by the evidence as the court failed to consider evidence on record of the delivery of the piling hammer to the respondent.

 

(2)   Damages awarded against the Appellant are speculative and excessive and cannot be supported by the evidence on record in that:

 

(a)    The court misdirected itself when it based its award of damages on the alleged hiring fees of the piling hammer although the court’s finding was that the alleged breach for which plaintiff is to be compensated was in connection with the crushing plant.

 

(b)    The court misdirected itself by awarding damages in favour of the respondent although the respondent had provided no factual basis for the award of the exact sum of $890,411.00 or at all.

 

(3)   The general damages awarded was unreasonable in that the Court assumed that the piling hammer would work non-stop day in day out from the swap to the date of judgment without days of maintenance and without ‘no work’ days or a life span.

 

(4)   The court misdirected itself by assuming that since an appeal is a re-hearing it could substitute or award damages, although there were no facts upon which such damages could be based.

 

(5)   Further grounds to be filed upon receipt of the record of proceedings.”

No such additional grounds have been filed thus far.

A summary of the submission in support of grounds of appeal revealed they resolved themselves into the following questions, namely,

                        (1)  Whether or not the piling hammer was delivered to the respondent?

(2) If there was non-delivery of the item, how much damages the         respondent was entitled thereto?

 

(3) Whether the damages awarded the respondent was justified?

An appeal to the Court was by way of a re-hearing and the court had the power to make its own findings of facts where the trial court failed to do so: see Tuakwa v Bosom [2001-2002] SCGLR 61 at 65 per Sophia Akuffo JSC.  The trial judge failed to make  any definite findings on the delivery or otherwise of the piling hammer by the defendant to the plaintiff.

            The Court of Appeal considered the evidence and made a finding of fact that there was an agreement by the parties to swap equipment; thus reversing the finding of the trial court that there was a contract of hiring of equipment by the parties. There could be no doubt that the evidence on record supported the Court of Appeal on this finding.  This court therefore has no good reason to reverse the finding by the Court of Appeal on this and would therefore affirm that decision.

            The Court of Appeal went further to find that the defendant breached the swap agreement by failing to deliver the piling hammer to the plaintiff.  Delivering the judgment of the court, the learned Akoto-Bamfo JA said:

 

“It is not in doubt that there was a swap agreement under which the plaintiff was to give the piling hammer to the defendant who was in turn to give the plaintiff the crushing plant; that the plaintiff performed under the contract but that the defendant did not give the crushing plant to the plaintiff and therefore committed a breach of the agreement is beyond question.”

            The appellant has sought to question the rightness of this holding.  In law, to deliver a thing is to formally transfer or yield possession thereof to another.  It may be done actually, by which the thing is handed over to another by changing hands; or, constructively, that is, put at another specified place or placed at the disposal of another person; or, by granting reasonable and unimpeded access to the property in question.  Whether or not the defendant delivered the piling hammer was a question of mixed law and fact.  It must be recognized that the parties were free to agree one way or the other on the mode and place to deliver the property.  In the absence of any express agreement, the mode of delivery could be inferred from circumstances surrounding a particular case.  In the instant case, the defendant asserted it did deliver the plant to the plaintiff and thereby assumed the burden of proving on the balance of probabilities that it did.

Even though there was no evidence of a written or oral agreement in this transaction, that was not fatal for the evidence must be read as a whole to assist in coming to a conclusion one way or the other. Thus the plaintiff tendered exhibit K, dated 24 February 1994, and which emanated from the plaintiff company to the general manager of the defendant company.  It bore some relevance on the issue as it said inter alia:

“We refer to the arrangement you had with our managing director for making available for your use an Audi Saloon car and a DE 30C Diesel Hammer and request for a Toyota Hilux Pick-up (4x4) and a mobile crushing plant from your company for use on our construction sites…  It was anticipated that on your taking delivery of the diesel pile hammer you would hand over a mobile crushing plant to us.  You have been in possession of this hammer for some time now and would be grateful if you could provide us the crushing plant to enable us start producing our own aggregate for our concrete works remaining for the Phase I as well as Phase II of the Fumbisi Valley Project.”

The P.W.1, was D.K. Ofori Atta. He said in his evidence that the plaintiff wrote to the defendant to request the crushing plant to be sent to it and under cross-examination admitted the defendant made the Toyota Hilux Pick-up available to the plaintiff and they also gave the Audi saloon car to the defendant.

            Exhibit 2 dated 2 June 1997 which was tendered in evidence by the defendant and accepted without objection, also stated inter alia, that:

“M & J offered the crushing plant to Danielli as part of the hammer/pick-up arrangement (see attached confirmation letter from Danielli)… Danielli were to collect the crusher from the Damango site just as we had to collect the hammer from the Danielli site in Accra…  Danielli never picked up the crusher even though we reminded him every time we saw him.  The crushing plant is in a fully working and serviceable condition ready for collection, ie as of now.”

            The defendant company led oral evidence through its General Manager, Mr Francis Ronald Cooper, that the defendant made the mobile piling hammer available since 1984 but it was yet to be collected whereas the defendant collected the Toyota Pick-up early 1984.

            The totality of the evidence showed that, by their conduct and practice, the parties had a common pool from which each would go and collect the equipment it needed.  Further, after the defendant had had  the piling hammer, it would hand over the crushing plant to the plaintiff.  In accordance with the practice between the parties, the plaintiff was expected to go for the piling hammer from the defendant’s site in Accra just as the defendant went for the crushing plant from the plaintiff’s site at Damango.  The plaintiff company did not cross-examine the witness of the defendant company in the witness box when he gave that evidence; the plaintiff company did not also tender any evidence to challenge the veracity of the evidence in exhibit 2 and the inference was that it admitted the import of the evidence: see Fori v Ayirebi [1966] GLR 627, SC; and Browne v Dunn (1894) 6 R 67.

            Thus, there was evidence that the defendant made the crushing plant available to the plaintiff but he did not collect it in accordance with the practice that existed between them under the swap arrangement.

            One could hardly say in the circumstances of this case, the defendant did not deliver the piling hammer to the plaintiff and thereby breached the swap agreement.  The defendant having made the piling hammer available for the plaintiff to collect, it discharged its obligation under the agreement vis-à-vis the piling hammer. If anything at all, the plaintiff was the sole architect of its misfortune; in fact it might as well be held to have been in breach of its own agreement with the defendant.

            In the result, this court agrees with the appellant that the Court of Appeal erred in concluding that the defendant breached the agreement by failing to deliver the piling hammer.  The defendant was in no breach whatsoever.  This disposes of ground one of the grounds of appeal __  the most decisive of the grounds, and the appeal as a whole.  This error by the Court of Appeal no doubt led it to award damages in favour of the plaintiff.

            This is a good case to reverse the judgment of the Court of Appeal entirely and we so reverse it, and allow the appeal.

 

  

 

                                                                                                      J. ANSAH

                                                                               JUSTICE OF THE SUPREME COURT

 

 

 

                                                                                                     W. A. ATUGU BA

                                                                               JUSTICE OF THE SUPREME COURT

 

 

 

                                                                                                     G.T.  WOOD

                                                                               JUSTICE OF THE SUPREME COURT

 

 

                                                                                                     S. A. BROBBEY

                                                                               JUSTICE OF THE SUPREME COURT

 

 

 

                                                                                                  R. T. ANINAKWAH

                                                                              JUSTICE OF THE SUPREME COURT.

 

COUNSEL:

 

Mr. D. k. Letsa for Appellant

Mr. T. N. Ward Brew for Respondent

 
 

   Copyright - 2003 All Rights Reserved.