GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

 

IN THE SUPERIOR COURT OF JUDICATURE

IN THE HIGH COURT

ACCRA

CORAM; MRS. JUSTICE GERTRUDE TORKORNOO

 

SUIT NO. SUIT NO. RPC 246/09

03 August 2010

 

DE SIMONE LIMITED

 

PLAINTIFF

VRS

 

 

INTERCITY HOTELS LIMITED

 

DEFENDANT

 

 

The plaintiff was employed as a main contractor to construct the Accra Mall by the Defendant by appointment letter dated 14th December 2005. The construction contract was governed by the Fourth Edition (1987) of the Conditions of Contract for Works of Civil Engineering Construction produced by the International Federation of Consulting Engineers, or Federation International Des Ingeneurs-Conseils popularly called the FIDIC 4 contract or The Red Book because of the color of its cover. A partial version of the General Conditions Of Contract Was tendered by plaintiff as exhibit B and the full version by defendant as exhibit 8. The Conditions of Particular Application to this contract were tendered as exhibit 9. It is the case of the plaintiff that after sectional handing over of parts of the mall from July 2007 to February 2008, the parties reached substantial completion of the project in November 2007 and every portion of it was handed over by February 2008. On 28th October 2008, the Engineer produced what was described as the Final Account Statement on the project on which representatives of the parties and the engineer signed that the final agreed full and final value of all works executed by the Contractor stood at 23,544,152.12$. On 17th December 2008, the Engineer issued Payment Certificate Number 24 in the sum of $254,478.63. On Certificate 24, tendered as exhibit 1 and which was described as the Final Payment Certificate, the Engineer certified that the current 'Contract value stood at 24,668,783.00$ and that the Contractor was due payment of 254,478.63$. The disparity in figures between the Final Account Statement agreed on 28th october and this certificate dated 16th December 2008 showed that in the space of those weeks, for whatever reason, the value of the contract works had been identified as being more than one million dollars over and above what the final Account Statement agreed. Before the Contractor could issue its invoice for payment of the certified sum on Certificate Number 24, the Employer issued an email the very next day through its Fatima Wadiwalla stating that 'all the payments made to DeSimone and related sub-contractors totaled $23,943,378 which exceeds the final account by 329,066.35$. Without making any comment On the directions issued by the Engineer for Contractor to prepare invoice for payment on Certificate 24, she suggested the way forward as the need for all the parties to confirm the payments and cross check her spread sheet setting out the payments and advise her of any reconciled differences. It is the plaintiff's case that following this communication and the position that payments to the contractor had exceeded the values on the final account, the Contractor was unable to prepare an invoice pursuant to Certificate 24 for payment, but was compelled to abide the outcome of this reconciliation exercise. The defendant's Witness, Phillip Cobbina testified that by the end of this reconciliation exercise in March 2009, the parties had agreed that the overpayment amounted to 73,296.5$ dollars and not 329,066.35$. The plaintiff remains unpaid the amount certified on Certificate Number 24 and has instituted this action claiming the sum identified on the Final Account Statement as the difference between the value of the contract works and payments made to the contractor as at 28th October 2008. This sum is set out on the last page of exhibit C as 516,061.65$. The defendant has resisted the claim on several grounds. Firstly, they argue that their records show payment to the Contractor in excess of 73,296.52$ and this sum is agreed by the Contractor and therefore the Contractor is not entitled to any further payments. Their second argument is that exhibit C which was described as the Final Account Statement is the Final Statement that ought to be submitted to the Engineer for consideration under clause 60.6 of the General Conditions of Contract. And that this clause provides that following the issue of this Final Statement, if there is a dispute as to the sum Owed to the Contractor, the Engineer was required to issue an Interim Payment Certificate for those parts of the draft final statement which are not in dispute. Consequently, Certificate Number 24 is an interim final certificate (IPC) issued pursuant to clause 60.6. It is defendant's case that the next step after the issue of this IPC is a written discharge from the Contractor confirming that the Final Statement represents full and final settlement of all monies due to the Contractor and that without the written discharge, a final certificate for payment is not due for payment. Thus the plaintiff's action is premature, not having waited out the contractual processes set out in the Red Book for arriving at a final certified sum for payment. The third argument of the defendant, which is in tandem with the just set out argument is that the figure identified on the Final Account Statement - exhibit C - is only the value of the contract works and does not signify a certified sum for payment and therefore it cannot form the basis for a claim in court. They urge the court to dismiss the claim of the plaintiff and direct the parties to return to the processes of the contract set out in Clause 60.6. A collateral argument which was not developed to any conclusion was that a Taking- Over Certificate for the whole of the works had not been issued by the Engineer and the Defects Liability Certificate for the works had consequently not been issued and so the project had not gone through the Defects Liability period. This argument is denied by plaintiff. The issue for determination by this court is whether the plaintiff is entitled to payment of the sum stated on the Final Account Statement as claimed or it has failed to prove any entitlement in this court and the parties should be directed back to conclude the final contractual processes as prayed by the defendant. On a study of the pleadings, evidence and exhibits before me, it is clear that there is considerable confusion in the arguments of both parties regarding: what the parties and the Engineer sought to do between October and December2008 and the implications of those processes and that this confusion has been fueled largely by the failure of the Engineer to decisively do the impartial work expected of the Engineer in the dying phases of the Contract. The FIDIC 4 contract is extremely popular because of the regime it creates for the Engineer, although paid by the Employer, to act as a neutral arbiter of the work program and payments. He achieves this position by the decisions and processes he issues to declare his decisions. In clause 2.6, captioned 'Engineer to Act impartially', the contract provides that 2.6 Wherever, under the Contract, the Engineer is required to exercise his discretion by: a. giving his decision ,opinion or consent, b. expressing his satisfaction or approval c. determining, value, Or d otherwise taking action which may affect the rights and obligations of the Employer or the Contractor he shall exercise such discretion impartially within the terms of the contract and having regard to all the circumstances Any such decision, opinion, consent, expression of satisfaction, or approval, determination of value or action may be opened up, reviewed or revised as provided in clause 67. It is clear to this court that the befuddled position of the Engineer on this case, leading to its officer appearing as the first witness of the employer in this court has contributed greatly to this dispute. It is the case of the plaintiff that the whole of the works reached substantial completion in February 2008 following sectional taking over of various parts of the mall from July 2007 to February 2008. Exhibit 3 shows that the last part of the Mall taken over was the Media Center and this was on 2nd February 2008. This is not denied by the defendant. Thus, in addition to the Sectional Taking Over Certificates issued pursuant to clause 48.1 such as exhibit J dated November 2007, by which date only 4 zones were outstanding, the contractor ought to have requested for and the Engineer ought to have issued a Taking Over Certificate for the substantial part of the works completed and taken over by the employer after pursuant to clause 48.2(b) and (c). This was not done and although no evidence was placed before the court to establish that pursuant to clause 48.1, the contractor Was notified of any defects affecting substantial completion between November 2007 to February 2008, to date there is no final Taking Over Certificate on this project. Be that as it may, the parties testified that following the handing over of the project, a snagging list for defects was given to the Contractor who claimed to have rectified all defects, though the defendant denies this alleged rectification. But within the evidence before the court, I can find that by operation of clause 49.1, the Defects Liability Periods for the parts covered by the Taking Over Certificates issued pursuant to clause 48.1 such as exhibit H commenced from the date certified on those certificates and by necessary application of the terms of the contract in clauses 48 and 49, to the extent that by November 1st , more than 90% of the works had been taken over and a Taking Over Certificate issued, the Defects Liability Period for the substantial part of the works would run for 90 days from 1st November 2007 to 31st January 2008. The defendant took over the remaining insignificant number of shops — precisely 2 — on 2nd February 2008. What is the import of this for the accounts that triggered the controversy? Clause 60 of the General Conditions of Contract deals with certificates and payments. The regime set out is that payments would be triggered by the contractor submitting to the Engineer monthly statements showing the amounts it considers itself entitled to. 28 days after receipt of such statements, the Engineer would issue an interim payment certificate stating the amount of payment the Engineer considers as due to the Contractor pursuant to the monthly statement. In every IPC, the Engineer is allowed to modify and correct any previous one. Through the issue of these statements,. their verification and the eventual issue of IPC's, the Engineer is able to keep track of the value of works executed, payments made to the Contractor, and the due administration of all aspects of the project, including payments made to or due and owed from sub contractors. Under clause 60.5, 84 days following the issue of the Taking Over Certificate in respect of the whole of the works, the contractor shall submit to the engineer six copies of what is now called a 'Statement at Completion' with supporting documents showing the final values of the works and sums which the Contractor considers to be due to him under the contract. The certificate to be issued pursuant to this statement at completion is still an Interim Payment Certificate in the nature of the Clause 60.2 certificates. 56 days after the issue of the Defects Liability Certificate, the contractor commences the final account statement by submitting a draft to the engineer. This is where I see that the problems began. Although it placed no evidence before this court to prove that particular defects were seen by February 2008 which plaintiff failed to rectify, the Engineer testified that he failed to properly bring this contract to an end by issuing a Defects Liability Certificate as required by Section 62.1 because there were defects in the project. Thus, while abdicating his duties to properly manage the rectification of defects through notices and follow up on the contractor, the Engineer took the position not to issue the Defects Liability Certificate. Under clause 61.1, only: the Defects Liability Certificate shall be deemed to constitute approval of the Works. And clause 62.1 provides for the issue of this certificate under three alternate circumstances 'The Defects Liability Certificate shall be given by the Engineer 28 days after the expiration of the Defects Liability period, or, if different Defects Liability periods shall become applicable to different Sections or parts of the Permanent Works, the expiration of the latest of such period, or as soon thereafter as any works instructed, pursuant to clauses 49 and 50, have • been completed to the satisfaction of the Engineer.' The literal understanding of these alternate scenarios for issuing the Defects Liability Certificate is that in the absence of identifiable defects which the Engineer instructs the Contractor to remedy under clauses 49 and 50, the Engineer 'shall'; and this is mandatory, give the Contractor the Defects Liability Certificate 28 days after the expiration of the Defects Liability Period, which in this case would be by 31st January 2008 - being 90 days after substantial completion on 1st November 2007, or at the worst, 30th April, which is 90 days after the last two zones were handed over to the Employer. From the evidence, although the Engineer did not identify that any instructions of his for rectification of defects were outstanding in that crucial 90days period, it failed to issue this certificate and left the matter in limbo. It now seeks to rely on the part of clause 62.1 which provides that .the' Contract shall not be considered as completed until a Defects Liability. Certificate shall have been signed by the Engineer and delivered to the Employer, with a copy to the Contractor, stating the date on which the Contractor shall have completed his obligations to execute and complete the works and remedy any defects to the Engineer’s satisfaction'. Its representative, Mr. Bovell who testified as the defendant's witness argued before this court that there are still defects in the project and the Defects Liability Certificate has not been issued as a result of this. I find the arguments at best disingenuous and at worse evidencing lack of candor. None of the copious exhibits tendered by the defendant showed that between November 2007 when it issued a Taking Over Certificate for substantially the entire mall, and April 2008, when the Defects Liability Period for the last two zones handed over in February 2008 should be deemed to have ended, the Engineer sought any rectification of any defects. The language of Clause 62.1 is clear that in the absence of instructing any works pursuant to clauses 49 and 50, the Engineer is compelled by reason of the contract to issue the Defects Liability Certificate. Although this Certificate was not issued, by reason of the mandatory stance of the contract, I find my way clear to finding that the Defects Liability Period for the entire mall came to a satisfactory final end on April 30th 2008 and there being no outstanding un-remedied defects that have been shown to this court, the Contractor was discharged from an obligation to remedy defects that Were not latent defects. The failure of the Engineer to issue the Defects Liability Certificate is a process that is outstanding for fulfillment but it cannot serve to hold the entire contract hostage It is not too late for the Engineer to fulfill his obligations under the contract since he failed to tender evidence to prove that during the Defects Liability Period he raised instructions for remedying defects what were not complied with. Of course, this would not preclude the defendant from seeking rectification of latent defects in any part of the works, but such a demand would be pursuant to its rights under the general law of contract, neither would it preclude liability on the part of either party for the fulfillment of any obligation incurred under the Contract prior to the cessation of the Defects Liability Period as provided for Under clause 62.2. However, even without the official declaration of the contract coming to an end through the clause 48.1 taking over certificate and the issue of the Defects Liability Certificate, the records show that the parties entered into the preparation of the Final Statement pursuant to clause 60.6. There are two comments I must make here. Although Mr. Bovell originally denied that the plaintiff as contractor ever submitted a statement of completion as required by clause 60.5 to be issued by the contractor before the preparation of the Final Statement, he later conceded to this. Plaintiff's witness Mr. Amankwaah also claims that the contractor sent its statements at completion and draft final statement be email and this is what led to the preparation of the Final Account Statement tendered as exhibit C. Secondly, although the Final Statement issued pursuant to clause 60.6 is supposed to be a document emanating from the Contractor, the tenor of exhibit C shows that this was a document prepared by the Engineer and not the Contractor as anticipated by the contract. But be that as it may, whether or not the contractor initiated the issue of the Final Statement by presenting a Statement at Completion, and produced drafts for the preparation of the Final Statement, Clause 60.6 makes it clear that unlike the monthly statements issued by the contractor and interim payment certificates issued by the engineer, the Final Statement is a document concluded through agreement of the Contractor and the Engineer. And indeed, exhibit C, the Final Account Statement is an agreed document signed not only by the Contractor and Engineer but also by the. Employer. By the terms of clauses 60.5 and 60.6 of the contract, it is anticipated that this document will be completed not less than 140 days or almost five months after the taking over of the whole of the works. In this case this document was agreed 9 months after the taking over of the whole of the works in February 2008. Thus although exhibit C does not say explicitly that it is issued pursuant to clause 60.6, its preparation and structure was in compliance with that provision - as testified by representatives of both parties. I totally agree with defendant counsel's arguments on addresses that by the terms of Section 60.6, the declaration of a figure as the sum agreed to be due to the Contractor on the Final statement does not create a legal or contractual liability for its payment. What I do not agree with him is that the certificate issued following the final statement is by operation of the contract an interim payment certificate. The answer lies in the last paragraph of clause 60.6 which reads 'If following discussions between the Engineer and the Contractor and any changes made to the draft final statement which may be agreed between them, it becomes evident that a dispute exists, the Engineer shall deliver to the Employer an Interim Payment Certificate for those parts of the draft final statement, if any, which are not in dispute. The dispute may then be settled in accordance with clause 67' Clearly, the issue of an interim payment certificate after a clause 60.6 statement is done only arises where there is a dispute regarding the values on the final statement. At that point in time, the contract regime provides for the Engineer to -certify by an interim certificate the undisputed sums, and subject the outstanding balance to his own decision, an amicable settlement of the parties or arbitration pursuant to clause 67. But in the current case, there was no dispute as to the values on the final account statement. It was so agreed that even the employer signed it. In such a situation, the next process is not an interim certificate but a written discharge by the Contractor under clause 60.7 and a final payment certificate under clause 60.8. Clearly, the Contractor served no separate written .discharge on the Employer. But notwithstanding this, the Engineer went ahead and certified a final payment certificate in Certificate number 24. And I do not find that the non-issue of the written discharge is fatal to the validity of the final certificate. Indeed the words of the final statement invite the finding that it also constitutes a. written discharge. Under clause 60.7, the written discharge confirms that 'the total of the final statement represents full and final settlement of all monies due to tile contractor arising out of or in respect of the contract.' The opening paragraphs of the final Account in Exhibit C has these words ‘I/we hereby agree that the above amount represents the full and final value of all work executed by us under the above contract and all claims that we have against the employer in connection with the above contract. 'It will take a stretch of imagination to deny that these words do not satisfy the discharge anticipated under clause 60.7. And it would seem that the Engineer recognized this hence it went ahead to issue certificate 24 as a final certificate. It has been argued by defendant that certificate 24 is an interim certificate and not a final certificate. I must respectfully disagree. At the top of the certificate, two boxes are provided to indicate whether the certificate number is interim or final. The engineer clearly filled that box with the information '24 Final Account'. And following on the heels of the Final Account, it is clear that this certificate was issued as the final payment certificate required under clause 60.8. Contrary to the arguments of plaintiff, there is no contractual obligation for the Engineer to certify payment in total tandem with the final statement as if nothing else may occur after the issue of the final statement. It must be remembered that as a necessary part of this contract, additional works, variations and extra Works may be ordered by the client and the contractor has a duty to execute them, subject to claims for payment. In the same way, the cost of the project may be reduced by reason of omission of works or even the remedying of defect. Thus, it is no surprise that certificate 24 has a value different from that acknowledged on the final statement. An examination of the Certificate shows that since the final statement was completed in October 2008, the contract value changed from 23,544,152.12 $ to $24,668,783.00. Indeed Fatima Wadiwalla's email of 17th December 2008 which alleged the overpayment being contested identified that 'the subtotal of 23,943,378 excludes any payments that were made for the fire damage works and the new retaining wall.' Please see exhibit F. This clarifies that between October and December, there could easily have been reason for the contract works value to change. Clause 60.8 thus gives the Engineer the room to certify what is in his opinion finally due under the contract in the final payment certificate. Thus I do not find that it is open at all to this court admit the contention that plaintiff should be entitled to the values on the final account statement but not the value on the final certificate which is certificate 24. That contention by the plaintiff is dismissed. But having certified the final certificate sum, is it open to the employer to dispute this sum and refuse to pay same on the ground that it has over paid the contractor, such that the contractor is bound to enter into reconciliation exercises directly with the employer's team as Ms Wadiwalla directs in her email? I am afraid not. And this is where I find that the Engineer terribly let down the parties in what was his contractual function. There is no contractual provision that allows the contest of this final certified payment in the manner that interim payment certificates are open to review and corrections by further interim certificates.Clause 60.10 provides that with the exception of situations where the contractor is liable to pay liquidated ascertained damages for late delivery under clause 47, the employer 'shall' pay the amount certified under clause 60.8 within 56 days -after such final payment certificate has been delivered to the employer or pay interest for late payment. This obligation is not negotiable. To my mind, the danger in this stance is validated by the alleged reduction of the alleged overpayment from approximately 325,000$ to 73,000$ during this reconciliation exercise that seemed that seemed to have been done through the presentations of spread sheets etc and outside the purview of the Engineer's administration and creating what could easily be an arbitrary result. Evidence has been tendered before this court to prove this alleged overpayment. But without a doubt, this evidence only leads to what Mr. Kobbina referred to as 'mathematical figure'. An interesting point was made in cross examination of Mr. Kobbina. He was asked 'so the overpayment is just an arithmetic figure?' A. Yes Q. And so when you said that when the project manager put a figure of 516,000$ as the amount due the contractor and you considered that a mathematical figure, what does that mean, it means the same as yours isn’t it? A No because I have been able to prove that and I have given you a listing.1n exhibit 2 which shows reconciliations of what happened and it gives a reconciled overpayment amount Clearly, Mr. Kobbina was of the opinion that as long as he could prove payments, it was legitimate to set off the payments against the value of the works, whether or not this conflicted with the certification of the Engineer in Certificate 24. One of his final statements was extremely telling of the mindset accompanying the exercise that the defendant is inviting this court to endorse. He said 'We took out those that we were comfortable with and that it should be taken out'. When questioned by the court as to the extent to which he averted his mind to the Conditions of Contract in pursuing the alleged reconciliation, he said 'My Lord, I did not use the book at all'. I must whole heartedly disagree with his presentations based on these positions - if for none other. The duty of a court in contract adjudication is simply to enforce the terms of the contract. The contract is clear that the only person with the function of determining the sums due the contractor is the Engineer and he has no business abdicating that role to a team comprising whichever persons come from the offices of the parties. Whether the defendant has paid the sums stated on the final statement, or on the final certificate, and whether the payments constitute overpayment to the Contractor, the import of what payments have been made is a matter of contract administration and that is the preserve of the Engineer under the FIDIC 4 contract that the parties have chosen to bind themselves to and not the function of the parties. It must be premised on what is allowed to either party by reason of the contract, and arrived at in proper form - not through an office, email and phone call reconciliation exercise dominated by the employer, when the contract has not officially been brought to an end. This court finds that as at date, by operation of Certificate 24, the contractor has been found to be owed $254,478.63. Mr. Bovell's purported endorsement of the review done by the employer as testified in court has not been set down as a part of the contractual records of this project. The engineer has not given a decision on the protests of Fatima Wadiwalla dated 17th December and unless and until he does so, in proper contractual form those communications cannot be recognized by this court. This is not the forum for protesting a Certificate and as such, the Defendant is ordered to pay the Plaintiff the sum of $254,478.63 being the sum certified on the Final Payment Certificate with interest from December 2009. Unfortunately I do not have the expertise to determine the exact figure due the contractor following examination of the certified payments and the alleged claims of the employer. Costs awarded at $15,000 being 5% of the Contract sum and provision for court expenses. COUNSEL: MR. ADDO WITH MR. AGYEMAN AND MR. OSEI ASARE FOR PLAINTIFF MR. ARHIN WITH MS.MARTINSON FOR DEFENDANT

 

Legal Library Services        Copyright - 2003 All Rights Reserved.