ARRANGEMENT OF REGULATIONS
Regulation
Purpose and application
1. Purpose
2. Application
Application for new service
3. Breach of application
processing procedures
Reliability of electricity
supply
4. Interruption of supply
5. Restoration of supply
6. Breach of requirement for
notice of interruption
7. Reporting standards
System voltage 8.
System voltage complaint
The meter
9. Requirement for a meter
10. Separate meter
11. Prepayment meters
12. Meter repositioning
13. Revision of meter
14. Meter complaint
Miscellaneous provisions
15. Payments
16. Dispute resolution
17. Notification of rights of
customers
18. Provision of information
19. Exemptions from compensation
payment
20. Penalty
21. Transitional provisions
22. Interpretation
SCHEDULE
ELECTRICITY SUPPLY AND
DISTRIBUTION (STANDARDS OF
PERFORMANCE) REGULATIONS, 2008
IN exercise of the power
conferred on the Board of the
Energy Commission acting in
consultation with the Public
Utilities Regulatory Commission
by section 27 of the Energy
Commission Act, 1997, (Act 541)
these Regulations are made this
4th day of June, 2008,
Purpose and application
Purpose
1. The purpose of these
Regulations is to provide for
performance benchmarks for
electricity supply and
distribution in conformity with
the provisions of Electricity
Supply and Distribution
(Technical and Operational)
Rules, 2005 (LI 1816).
Application
2. (1) These Regulations
apply to electricity supply and
distribution utilities licensed
by the Commission.
(2) For the purpose of this
regulation, "electricity supply
and distribution utility" means
a person licensed under the Act
to distribute and sell
electricity without
discrimination to consumers in
an area or zone designated by
the Commission.
Application for new service
Breach of application processing
procedures
3. (1) A supplier of
electricity shall process a
customer's application for
connection to electricity
services in accordance with the
requirements specified in rule 2
of Electricity Supply and
Distribution (Technical and
Operational) Rules, 2005
L.I.1816.
(2) A supplier shall, subject to
these Regulations, pay the
customer the sum prescribed in
the Schedule where
(a) that supplier fails to
provide the applicant with an
estimate and charges for the
connection service within
(i) five working days, if the
connection is to be made from an
existing supply line; or
(ii) two weeks, if the
connection requires a line
extension,
(b) that supplier fails to
provide the connection service
to a customer after that
customer has paid the required
charges for the connection
service within
(i) five working days if the
connection is to be made from an
existing supply line; or
(ii) one month if the connection
requires a line extension.
Reliability of electricity
supply
Interruption of supply
4. (1) A supplier of
electricity shall ensure that
the cumulative electricity
interruption for each customer
within an operational year does
not exceed·
(a) forty-eight hours, in a
metropolitan or municipal area,
or industrial estate;
(b) seventy-two hours, in a
district capital; and
(c) one hundred and forty-four
hours, in a rural area.
(2) Despite subregulation (1)
the supplier shall ensure that
the electricity interruption to
a customer's premises within an
operational year does not exceed
six periods.
(3) Despite subregulations (1)
and (2) the duration of each
outage shall not exceed
(a) eight hours, in a
metropolitan or municipal area
or industrial estate;
(b) twelve hours, in a district
capital; and (c) twenty four
hours, in rural areas.
(4) For the purposes of
subregulations (1), (2) and (3)
the period of an interruption
shall be consistent and commence
from the time the supplier is
initially informed by
(a) a customer that the supply
to the customer's premises has
been interrupted; or
(b) a person other than the
customer or is otherwise made
aware by the operation of any
automatic system operated by the
supplier in circumstances in
which the supply to the
customer's premises has been
interrupted or may reasonnably
be expected to have been
interrupted.
(5) Despite subregulations (1),
(2), (3) and (4), an
interruption of supply to a
customer shall not be treated as
wrongful where
(a) the interruption was as a
result of a major fault or
damage to an indispensable
equipment in the electricity
supplier's distribution system
subject to subregulation (6);
(b) the interruption was as a
result of a failure of, fault in
or damage to either the
transmission system to which the
electricity supplier's
distribution system was
connected or a generating
station connected to that
transmission system; or
(c) the interruption was as a
result of a failure of, fault in
or damage to a generating
station connected to the
supplier's distribution system;
(d) the interruption was one for
(i) planned maintenance,
(ii) emergency,
(iii) supply disconnection, (iv)
load shedding, or
(v) safety of supply
as permitted under the
Electricity Supply and
Distribution (Technical and
Operational Rules, 2005 (L.I.
1816); and
(e) the customer informed the
supplier that the customer did
not wish the supplier to take
any action.
(6) Where a major outage was due
to the negligence of the
supplier, paragraph (a) of
subregulation (5) shall not
apply.
(7) A supplier shall, subject to
these Regulations, pay into the
Energy Fund the sum prescribed
in the Schedule where that
supplier is in breach of the
supply interruption limits
specified in sub regulations
(1), (2) and (3).
(8) Subject to regulation 19,
the sum prescribed in the
Schedule shall not be paid by
the supplier where
(a) the supplier has not
received a claim for
compensation from the customer
within a period of three months
after the expiry of the relevant
year;
(b) the interruptions were not
in respect of supply to the same
premises; or
(c) the customer or where more
than one person is the customer,
at least one such person was not
the customer of the premises to
which the supply was interrupted
on the occasion of each of the
interruptions as a result of
which this regulation applies.
Restoration of supply
5.
(1) Where a supplier is informed
of an interruption in the
customer's supply due to a fault
in or damage to the supplier's
distribution system either by
the customer or a person other
than the customer, the supplier
shall, unless the fault was
caused by a natural disaster,
restore supply to the customer's
premises
(a) in the case of a minor
fault, within
(i) eight hours, in the case of
a metropolitan or municipal area
or industrial estate,
(ii) twelve hours, in the case
of a district capital, and (iii)
twenty four hours, in the case
of a rural area; or
(b) in the case of a major fault
that would require capital
intensive equipment replacement,
within
(i) eighty hours, in the case of
a metropolitan or municipal area
or industrial estate,
(ii) one hundred and twenty
hours, in the case of a district
capital, and
(iii) two hundred and forty
hours, in the case of a rural
area.
(2) A supplier shall restore
electricity supply to a customer
who has been disconnected for
non-payment of electricity bill
or undisputed arrears within
(a) six hours, in the case of a
metropolitan or municipal area
or industrial estate,
(b) twelve hours, in the case of
a district capital, and
(c) eighteen hours, in the case
of a rural area,
after settlement of all
outstanding financial
obligations.
(3) Where the electricity supply
to a customer's premises is
interrupted by natural disaster
supply shall be restored by the
supplier within the period
specified in subregulations (1)
and (2) after the situation
returns to normalcy.
(4) A supplier shall pay the
customer the sum prescribed in
the Schedule, subject to
regulation 19,
(a) where the supplier fails to
restore supply to the customer's
premises in accordance with the
time specified in subregulations
(1) and (2); and
(b) in respect of each
consecutive twelve-hour period
after the expiry of the period
specified for the restoration of
supply.
(5) Subject to regulation 19,
the sum prescribed shall not be
paid by the supplier where
(a) it was not practicable for
the supplier to be aware that
the supply had not been
restored; or
(b) the premises or the vicinity
within which the premises is
situate9- is supplied through an
electric feeder situated on a
river or sea bed;' or
(c) the premises is situated on
an island and no alternative
means of supply to the island
exists.
Breach of requirement for notice
of interruption
6.
Where a supplier
(a) fails to give notice of a
planned interruption of supply
through .
(i) public notice,
(ii) direct contact by
telephone, electronic mail,
satellite phone broadcast or any
other appropriate communication
system; or
(b) gives notice but interrupts
the supply at a time or on a day
other than the time or day
stated in the notice;
the supplier shall, pay into the
Energy Fund the sum prescribed
in the Schedule but subject to
regulation 19.
Reporting standards
7.
(1) A supplier shall prepare and
submit to the Commission and the
Public Utilities Regulatory
Commission separate technical
and financial reports quarterly
and annually which shall contain
proper records of the
performance of the supplier over
the relevant period.
(2) A supplier shall submit to
the Commission and Public
Utilities Regulatory Commission
(a) quarterly technical reports
within one month after the end
of each quarter, and
(b) quarterly financial reports
within two months after the end
of each quarter.
(3) A supplier shall, within
three months after the end of
each operational year in the
case of a technical report and
within four months after the end
of the operational year in the
case of a financial report,
submit to the Commission and the
Public Utilities Regulatory
Commission, a report on the
levels of performance achieved
in respect of the standards of
performance for that year.
(4) The supplier shall ensure
that the contents of the report
submitted
under subregulation (1) include
(a) the system average
interruption frequency index,
(b) the system average
interruption duration index,
(c) the customer average
interruption duration index, and
(d) Financial Statements.
(5) Where a supplier fails to
submit the quarterly reports and
annual reports in the manner
specified in this regulation,
the supplier shall, pay to the
Commission and Public Utilities
Regulatory Commission the sum
prescribed in the Schedule.
System Voltage
System voltage complaint
8.
(1) Subject to regulation 21 (1)
, a supplier shall ensure that
the voltage at the point of
supply to a customer's premises
or electrical installation is
within plus or minus ten percent
of the following voltage levels:
(a) 230 Volts,
(b) 400 Volts,
(c) 11 Kilovolts,
(d) 33 Kilovolts, or
(e) 34.5 Kilovolts.
(2) A supplier shall visit a
customer's premises within
twenty four hours on receiving a
supply voltage complaint to
investigate and where possible,
rectify any problem where the
supplier
(a) has been notified that the
electricity supply to a
customer's premises is or has
been at a voltage outside the
limits of the permitted
variations prescribed in
subregulation (1), or
(b) may have reason to expect
that an event which has occurred
within the distribution system
or in the power system external
to the distribution system may
have been the cause of the
supply voltage being outside the
limits of the permitted
variations.
(3) Despite sub regulation (2),
the supplier shall within seven
days after receiving notice of
the supply voltage problem send
to the customer an explanation
of the cause of the problem.
(4) Where the supplier fails to
visit the customer's premises,
investigate and rectify a supply
voltage problem contrary to sub
regulation (2) or to communicate
to the customer an explanation
of the problem contrary to
subregulation (3), the supplier
shall, subject to these
Regulations, pay the customer
the prescribed sum in the
Schedule.
p.8///////////////////////////
L.I. 1935
8
ELECTRICITY
SUPPLY AND DISTRIBUTION
(STANDARDS OF PERFORMANCE)
REGULATIONS, 2008
The meter
Requirement for a meter
9.
(1) A supplier shall provide,
install and maintain a meter
which will measure and record
the amount of electricity
supplied to the customer within
the accuracy limits of that
meter class.
(2) The supplier shall in
complying with subregulation (1)
give priority to
(a) a customer whose estimated
consumption of electricity per
month is above 300 kilowathours;
and
(b) a customer for whom the
Public Utilities Regulatory
Commmission has ordered the
installation of a meter in
respect of the customer's
premises in the course of the
settlement of a complaint.
(3) Where the supplier breaches
the requirement to provide a
meter within six months, the
supplier shall pay the customer
the sum prescribed in the
Schedule.
Separate meter
10.
(1) A supplier shall install a
separate meter at the customer's
premises where
(a) the customer requesting the
separate meter is a distinct
household and shares a meter
with another household;
(b) the total consumption of
electricity by the households
which share a meter exceeds 400
kilowatt hours per month or as
may be determined from time to
time by the Public Utilities
Regulatory Commission;
(c) facilities exist on the
premises for the supplier to
install the separate meter at
the customer's own cost;
(d) the customer who requested
the separate meter is willing to
make the necessary modifications
to the wiring system to
accommodate the separate meter;
and
(e) by installation of the
separate meter, the supplier is
not required to install any new
connection line except for a
line to connect the meter where
the distance between the meter
connection points and the
supplier's service fuse or
cut-out does not exceed one
meter.
(2) On receipt of the customer's
request, the supplier shall
visit the premises, assess the
situation and provide the
customer with estimates for
installing the meter within five
working days.
(3) Where the customer pays the
required charge for a separate
meter, the supplier shall
provide and connect the separate
meter to the electricity
distribution system within five
working days of the payment.
(4) A supplier who fails to
provide the estimates for the
separate meter or does not
install the meter upon payment
of the required charge within
the periods specified in
subregulations (2) and (3) shall
pay to the customer the
prescribed amount in the
Schedule.
Prepayment meter
11.
(1) The supplier shall ensure
that a facility for the purchase
of credit for a prepayment meter
is
(a) established within a ten
kilometer distance of the
premises where the prepayment
meter is installed, and
(b) open for a minimum of eight
hours each day of the week.
(2) Where a supplier fails to
(a) provide a facility for the
purchase of credit in respect of
a prepayment meter contrary to
subregulation (1)(a), or
(b) keep the facility for the
purchase of credit in respect of
a prepayment meter open for the
specified duration contrary to
subregulation (1)(b),
the supplier shall pay into the
Energy Fund the sum prescribed
in the Schedule.
(3) Despite subregulation (2), a
supplier shall pay into the
Energy Fund the sum specified in
the Schedule for each succeeding
six months that the supplier
fails to provide the credit
paying facility centre contrary
to subregulation (1 ) (a).
Meter repositioning
12.
(1) A customer may apply to the
supplier for a change in the
position of the electric meter
at the customer's premises by
stating the reasons for the
change in position and
indicating the preferred
location of the meter.
(2) On receipt of the customer's
request, the supplier shall
provide the estimate and charge
for repositioning the meter
within five working days where
the request is reasonable.
(3) Where the supplier rejects
the request the supplier shall
provide the customer with the
reasons for the rejection.
(4) Where the customer pays the
required charge, the supplier
shall reposition the meter
within fourteen days.
(5) Where the supplier fails to
provide the estimates and
charges contrary to
subregulation (2) or fails to
reposition the meter contrary to
subregu1ation (4), the supplier
shall, subject to these
regulations pay the customer the
sum prescribed in the Schedule.
Revision of meter
13.
(1) A supplier shall each year
undertake an audit of meters
that have been in operation for
twenty years or more and replace
at least 75% of the meters each
year.
(2) Despite sub regulation (1),
the supplier shall, within six
months after commencement of
these Regulations, submit to the
Commission
(a) an audit report of the
meters in operation for twenty
years or more, and
(b) a programme for replacement
of the meters within the
subsequent twelve months.
(3) A supplier who does not
comply with these requirements
under these Regulations shall be
considered to be in breach of a
mandatory technical performance
indicator requirement for Public
Utilities Regulatory
Commission's electricity tariff
review:
Meter complaint
14.
(1) The supplier shall visit a
customer's premises within
twenty-four hours after receipt
of a meter complaint from that
customer in respect of the
following matters
(a) that the electric meter on
the customer's premises is or
may have been operating outside
the permitted margins of error;
or
(b) that an event has occurred
or circumstances exist which the
supplier may reasonably expect
to have been the cause of a
meter operating beyond its
margins of error;
and for that reason the supplier
shall investigate the complaint.
(2) A supplier shall after
establishing a defect in the
operation of a customer's meter
replace the customer's defective
meter within forty-eight hours.
(3) The supplier shall use an
estimated consumption for
billing the customer for up to
six months, where the supplier
has no meter in stock for
replacing a defective meter in
accordance with subregulation
(2).
(4) A supplier who contravenes
subregulations (1) to (3) shall
pay to the customer the sum
prescribed in the Schedule.
Miscellaneous provisions
Payments
15.
(1) Where a supplier is to pay
compensation to a customer, the
supplier shall, subject to these
Regulations pay the sum
specified to the customer within
one month after demand.
(2) A claim for the payment of
compensation prescribed in these
Regulations shall be made in
writing within thirty days after
the breach in respect of which
the claim is made.
Dispute resolution
16.
(1) A customer who is not
satisfied with electricity
supplied, may complain orally or
in writing to the supplier.
(2) The supplier shall deal with
the customer's complaint in
accordance with its complaint
procedures.
(3) Where the supplier fails to
address a customer's complaint
to the customer's satisfaction,
the customer may lodge. a
complaint with Public Utilities
Regulatory Commission in
accordance with the Public
Utilities (Complaints Procedure)
Regulations, 1999 (LI 1665).
Notification of rights of
customers
17.
A supplier shall prepare and
make available to its customers,
a customer charter summarizing
the rights and responsibilities
of customers as well as the
level of service customers are
to expect.
Provision of information
18.
A supplier shall, on request
provide a customer with
information about the services
provided to the customer's
premises including the following
(a) load profiles and power
factors, where applicable,
(b) meter readings for
electricity supply to the
customer's premises,
(c) the customer's account, and
(d) the efficient uses of
electricity and electric energy
conservation practices.
Exemptions from compensation
payment
19.
Subject to these Regulations, a
supplier is exempted from
payment of compensation to a
customer where the breach of
duty in respect of which
compensation is payable occurred
as a result of or in the
following circumstances
(a) severe weather conditions;
(b) the inability to gain access
to the customer's premises';
(c) industrial action by
employees of the supplier,
subject to the Labour Act, 2003
(Act 651);
(d) a frivolous or vexatious
complaint;
(e) the breach of an enactment
was likely to occur if the
supplier took the action; or
(f) failure of the customer to
pay any charge required to be
paid before an action is taken.
Penalty
20.
The penalty units for the
contravention of these
Regulations are specified in the
Schedule.
Transitional provisions
21.
(1) A supplier shall achieve the
voltage levels specified in
regulation 8 (1) within the
period specified in the
Electricity Supply (Technical
and Operational) Rules, 2005 (LI
1816).
(2) The payment of the sums
prescribed in the Schedule shall
be due two years after the
commencement of these
Regulations.
Interpretation
·22.
In these Regulations unless the
context otherwise requires:
"Act" means the Energy
Commission Act, 1997 (Act 541);
"capital equipment" means major
electrical equipment that
attaches to the electricity
network including among others
power and distribution
transformers, wire and cable,
transmission and distribution
switch gear;
"Commission" means the Energy
Commission established under
Section 1 of the Act;
"connection service" means the
installation and activation of
connection assets in order to
distribute electricity;
"customer" means a person that
contracts to purchase
electricity from a supplier, or
an owner or occupier of a
premises who is supplied with
electricity;
"customer average interruption
duration index" means a measure
of the average duration of
interruptions for customers
interrupted during a year;
"distribution system" means a
system consisting of a network
of electric feeders,
transformers, service lines
meters, and other distribution
switchgear;
"electric feeder" means an
overhead conductor or
underground cable used for bulk
electricity supply;
"industrial estate" means an
area or land demarcated and set
aside for factories and
warehouses;
"major fault" means a fault that
requires capital equipment to
fix or remedy such as substation
blasts, cable blasts, damaged
transformer, damaged switchgear
etc;
"minor fault" means a fault that
requires minimal capital
equipment such as blown
substation LV fuse, jumper cut,
blown aerial fuse etc.;
"operational year" is the same
as a calendar year;
"supplier" means an entity that
has been licensed by the Energy
Commission under the Act as an
electricity distributor and
retailer;
"system average interruption
duration index" means a measure
of the average duration of
interruptions recorded for the
distribution system during a
year;
"system average interruption
frequency index" means a measure
of the average number of
interruptions recorded for the
distribution system during a
year;
"residential" means electricity
used by a customer for domestic
purposes;
"non-residential" means
electricity used by a customer
for a purpose other than
domestic activity; and
"rural area" means an
operational district with a
customer population under five
thousand and a demand below
fifteen megawatts. |