Appeal Court, 19th April, 1939.
Appeal from judgment of Division
Court.
Breach
of Contract--Illegal contracts
unenforceable-Accra Building
Regulation, 1930.
The plaintiff agreed with the
defendant to construct a new
building on the defendant's land
for £1,675. The specifications
given in the contract differed
materially from those fixed by
the Building Permit held by the
defendant. The learned trial
Judge held that the plaintiff
was entitled to recover damages
for breach of contract and
rejected the contention that the
contract was illegal on the
ground of public policy and
therefore unenforceable. He held
that, since the specifications
given in the contract were at
variance with the terms of the
Building Permit, the plaintiff
would have been compelled to
erect a building in accordance
with the terms of that Permit
and that the extra expense would
have fallen on him ..
Held: That a contract to erect a
building contravening the
provisions of a legal enactment
was illegal and could not be
enforced.
Held Further: That as the action
was framed for damages for
breach of contract the plaintiff
could not recover for work and
labour on the demolition of the
old building on the site and
that the writ could not be
amended at that stage .
. Appeal allowed; judgment of
Court below set aside and
judgment entered for defendant
with costs.
Case cited.
Stevens v. Gourley
(141 English Reports 752).
J Henley Coussey for
Appellant.
R. E. Phipps
for Respondent.
The' following joint judgment
was delivered:-
PETRIDES, C.].. GOLD COAST,
BUTLER LLOYD, ACTING C.J.,
NIGERIA AND STROTHER-STEWART, J.
Plaintiff by his writ claimed
£500 damages for loss sustained
by him through defendant's
breach of a contract to erect a
building at Accra, made between
the parties and dated 5th
August, 1937. Of this amount
£122 5s. was claimed as special
damages according to
particulars attached to the
writ.
There were no pleadings
and the defendant's Counsel in
his opening said :-
There was litigation over the
site and parties could not get
on the site, till after West
African Court of Appeal
Judgment-June, 1938. Prior to
this, defendant intimated to
plaintiff he could not pay owing
to cocoa hold-up ..
. By the Specification,
plaintiff contracted to
construct the foundation and
walls which were not in accord
with the building
regulations-Contract £1,675.
Claim inconsistent-(l) Claim for
entire breach, (2) Claim for
special damages. Pleads no
damage has arisen from the
breach-admits- breach ".
The trial Judge gave judgment
for the plaintiff for £205 5s.,
of which £55 5s. was for general
and the balance £150 for special
damages. He rejected the
contention of defendant's
Counsel that the contract was
illegal on the ground of public
policy and therefore
unenforceable. His reasons for
doing so are contained in
the following passage in his
judgment
The
description of the materials,
etc. to be used in the work are
set out in the building permit
and had the work been proceeded
with it is obvious the building
Inspector would have compelled
the work to be done in
accordance with that permit; and
as the contract provides for a
lower standard than permitted by
the Building Regulations, all
that would happen would be that
the owner would get a more
substantial building than that
provided for in the contract and
the extra expense would fall on
the contractor, and I hold that
although it may be an argument
in mitigation of damages
possibly, yet it cannot be said
to render the contract illegal.
"
The contract relied upon by the
plaintiff, hereinafter referred
to as the contract, is contained
in Articles of Agreement made
the 5th August, 1937, 1:etween
the defendant (Owner) and the
plaintiff (Contractor). By the
contract the defendant agreed to
demolish an old building on a
site at Rowe Road, Tudu, Accra,
and erect a new building thereon
for £1 ,675. These articles
recited that :-
WHEREAS the Owner is desirous of
constructing a Building at Rowe
Road Accra aforesaid- and has
caused Drawings describing the
work to be done to be made and
has obtained a Building Permit
AND WHEREAS the said Drawings
have been signed by the
Contractor AND WHEREAS the
Contractor has agreed to execute
upon and subject to the
Conditions set forth hereunder
the work shewn upon the said
Drawings and described in the
Specification hereto annexed."
Among the conditions was the
following :-
The work shall be executed in a
thoroughly substantial manner
with materials of the best
quality to the entire
satisfaction of the Owner and
strictly in accordance with the
Specification and Drawing
If the
specifications in the contract
are compared with the
particulars in the Building
Permit granted by the Accra Town
Council It will be seen that the
proportion of cement to stone
and sand that the plaintiff by
his contract agreed to supply
was very substantially less than
that required by the Building
Permit. it cannot be doubted
that !he additional proportion
of cement required by the
Building. Permit would have
considerably increased the cost
of the Building. The trial Judge
realised this but said that all
that! would happen would be that
the owner would get a more
substantial building than that
provided for in the contract and
the extra expense would fall on
the contractor."
We cannot agree with this view.
It is true that the contract
recite that the plaintiff had
obtained a Building Permit cut
nowhere does It provide that the
building shall be erected in
accordance with that permit.
On the contrary it is clear
from-
(a)
the recital and the condition
set forth above, and
(b)
the provisions in the body of
the contract,
that the plaintiff was to do the
work shewn upon the Drawings and
descended in the Specification
annexed to the contract. In
other words he was bound to
comply with the Specification to
the
Contract
and not to that of the Permit.
If he had been required to
comply with the Permit it would
have been open to him to tell
the defendant that he had not
contracted to do so and that if
he wanted a more substantial
building to conform to the
Permit he must pay extra.
By the Accra Building
Regulations, 1930, which were
made by the Accra Town Council
with the approval of the
Governor in-Council under
Sections 11 and 18 of the Towns
Ordinance and Section 4 of the
Town Councils Ordinance no
person shall erect any building
or execute any work except under
and in accordance with the terms
of a permit.
The Contract relied upon in this
case was therefore one to do a
thing which was prohibited by
those regulations. In the case
of
Stevens v. Gourley,
141 English Reports 752, it was
held that a contract to erect a
wooden structure contravening
the provisions of 18 and 19
Viet. C. 122 was illegal and the
builder could not enforce it. In
Leake on Contracts, 6th Edition
at page 564 it is stated :-
. The effect of illegality in
the matter or purpose of an
agreement is to render it wholly
void of legal effect; no claim
or defence can be maintained,
which requires to be supported
by allegation or proof of an
illegal agreement. Either party
may repudiate the agreement.
with or without alleging a
reason, and may afterwards
justify on the ground of the
illegality. The objection that a
contract is immoral or illegal,
as between plaintiff and'
defendant, sounds at all times
very ill in the mouth of the
defendant. It is not for his
sake, however, that the
objection is ever allowed; but
it is founded on general
principles of policy , which the
defendant has the advantage of
contrary to the real justice as
between him and the plaintiff.
If, from the plaintiff's own
stating or otherwise, the cause
of action appears to arise
ex t1trpi causa,
or the transgression of a
positive law, then the Court
says he has no right to be
assisted ".
It is clear from the authorities
that a contract to erect a
building contravening the
provisions of a legal enactment
is illegal and the builder
cannot enforce it.
The contract in this case, in so
far as it relates to the
erection of the building in
violation of the Accra Building
Regulations, 1930, is therefore
unenforceable by the plaintiff.
It has been contended on behalf
of the respondent that even if
that part of the contract which
relates to the erection of the
building is unenforceable the
plaintiff is entitled to
judgment for £55 5s. which the
trial Judge found was the cost
of demolition of the old
building and in respect of which
he awarded the plaintiff special
damages. To this defendant's
Counsel has replied that the
action was framed to recover
damages for breach of contract
and that as the plaintiff cannot
maintain an action for breach of
contract he cannot recover
anything under the writ as
framed. We consider this
argument unanswerable. It is
obvious that we cannot hold that
the plaintiff is entitled to
this amount for breach of
contract for it is clear that
there has been no breach of the
enforceable contract. Had the
claim in respect of this £55 5s.
been one for work and labour it
may well be that the plaintiff
could have recovered it under
this head. There was no such
claim before the Court below and
this Court is not prepared to
allow the writ to be amended at
this stage.
The appeal is allowed and
judgment of the Court below is
set aside and in lieu thereof
judgment is entered for the
defendant with costs. The
respondent to pay the
appellant's taxed costs in the
Court below and the costs of
this appeal which are assessed
at
£34 135 6d.
The Court below to carry out.