GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use

  Case and Subject matter index

 and more

tonykaddy@yahoo.co.uk

 

              

HOME

 

 

IN THE HIGH COURT OF JUSTICE (COMMERCIAL DIVISION) HELD IN ACCRA ON  15TH FEBRUARY 2011 BEFORE HER LADYSHIP BARBARA ACKAH-YENSU (J)

 

SUIT NO. BDC/53/09

 

        REVIX LIMITED                                                            ===     PLAINTIFF

 

                                                                        VRS.

 

1.    FORESTRY COMMISSION

 

2.    W.M. AWAREGYA                                                   ===  DEFENDANTS

 

 

 

=======================================================

 

JUDGMENT:

 

The Plaintiff is claiming against the Defendants, the following reliefs:

 

“ a.    General Damages for breach of contract

 

  b.       Loss of profit on export of the teak

 

  c.       The amount Plaintiff has over paid Defendants for the

   overestimation of the total teak volume on the said

   concession.

 

  d.       GH¢42,000 in demurrage charges from transporters

occasioned by Defendants’ unlawful delays in processing conveyance of work

 

  e.       GH¢57,500 for the 23 days of work stoppage from March

   25, 2009

 

  f.        GH¢2,500 per each day from May 8, 2009 until the day

   Defendants lift the ban or until judgment, whichever is   

  earlier in time

 

  g.       Any further and other damage(s) as the Court shall deem

   fit or as the circumstances of the case shall demand

 

  h.       Costs, including attorney fees.”

 

The Plaintiff’s case is that it won by competitive bidding and 1st Defendant granted Plaintiff the right to fell teak timber from the Kaboso West Taungya Series in the Kabo River Forest Reserve (“the concession”).  Having won the competitive bidding for the said concession, Plaintiff and 1st Defendant entered into a Plantation Utilization Contract for the period 14th April 2008 to 13th April 2009.  1st Defendant initially indicated by the contract that the concession contained a total teak volume of 12,671Cubic Meter (m3).  However, upon re-assessment, it was confirmed that the actual teak volume of the concession was much lower than what was stated in the contract.  On the 31st March, 2009, 1st Defendant revised the assessed total teak volume from 12,671m3 to 6,773m3.

 

 As a further condition for the grant, which Plaintiff performed relying on the understanding that Defendants would not derogate from the grant, Plaintiff secured a performance guarantee from its bank at a substantial cost of GH¢22,000.  According to Plaintiff, it paid GH¢1,662,729.77 for the grant at GH¢245.50 per cubic meter based on a total teak volume of 6773m3.  Upon further due diligence however the Plaintiff believes the actual teak volume in the concession is 4,700m3 and despite protestations, Defendants have refused to revise the teak volume and refund the excess payment by the Plaintiff back to it.  It is Plaintiff’s estimation that it has overpaid Plaintiff by GH¢508,921.50.  Plaintiff’s further case is that it had to take a bank facility and committed the facility to the wrong total volume of 12,671m3 provided by 1st Defendant for the concession. 

 

Plaintiff also entered into a Social Responsibility Agreement (SRA).   The Social Responsibility Agreement required Plaintiff to provide assistance to the community at GH¢1.18 per cubic meter on the total volume of timber to be removed from the concession.  Even at the total volume of 6,773m3, Plaintiff was to pay a total Social Responsibility obligation of GH¢7,992.14.  Plaintiff had paid a total of GH¢5,500, i.e. 68.8% of the total required amount although Plaintiff had removed a total of 2,490m3 of teak timber representing 36.7% of the total teak volume of 6773m3.

 

Plaintiff claims further that in the course of Plaintiff’s operations in the felling and export of the teak, 2nd Defendant put a lot of improper, unlawful impediments in Plaintiff’s way and unnecessarily stopping Plaintiff from its rightful operations.  That Defendants on a number of occasions unlawfully stopped Plaintiff from its operations in the concession.  Defendants conduct, Plaintiff states, is in breach of the contract, is improper, unlawful and derogates from the grant.  As a result of the said conduct, Plaintiff has suffered and continues to suffer damages.  Plaintiff particularized the special damages as follows:

 

a.               GH¢42,000 in demurrage charges from transporters occasioned by Defendants’ previous unlawful stoppage of work.

 

b.               GH¢57,500 for the 23 days of work stoppage from March 2, to March 25, 2009.

 

c.               GH¢2,500 per each day from May 8, 2009 until the day Defendants would lift the ban or until judgment, whichever is earlier in time.

 

d.               Loss of profits on export of the teak.

 

e.               The amount of GH¢508,921.50 being over payment to Defendants for Defendants’ over estimation of total volume of teak trees by 2073m3.

 

The Defendants admit that 1st Defendant entered into a contract with Plaintiff but deny that Plaintiff satisfied all conditions prior to the issuance of entry permit.  Defendants’ contention is that 1st Defendant indicated that the concession had estimated total volume of 12,671m3, nonetheless Plaintiff had ample opportunity to employ due diligence in assessing the volumes involved before accepting the offer made by the Defendants.  Defendants also state that the re-assessment carried out revealed that some of the teak trees enumerated in the initial assessment had been damaged by fire to the extent that they could not be felled for use as timber; hence such trees were not enumerated during the re-assessment.  Another significant observation was that holes were detected in lower sections of some of the teak trees that might have been caused by wildfires and senescence of the teak trees at the site.  It was also detected that Plaintiff’s harvesting operation was ineffective as indicated by a high level of waste that characterised Plaintiff’s operations.  For instance, just one or two billets were produced from an entire log, and the remaining lengths were abandoned on many occasions.

 

Defendants state further that Plaintiff paid 50% i.e. GH¢1,662,729.77 as the initial deposit in respect of the GH¢3,110,730.50 for the 12,671m3 initially estimated.  Plaintiff paid the said amount as a requirement before it commenced operations in the area allocated.  Defendants also state that they took into consideration payment of the 50% initial deposit before demanding payment of GH¢107,379.77 from Plaintiff by 3rd April 2009 to ensure full payment for the re-assessed volume of 6,772.83m3 at GH¢245.50 per cubic meter.  It is therefore Defendants’ contention that Plaintiff never fully paid for the 12,671m3 initially estimated but only 50% of the value thereof (GH¢1,662,729.77).  The Plaintiff accepted the re-assessed total volume of 6,772.83m3 being GH¢107,379.77 since March 31, 2009 but has failed and/or refused to pay the said amount.      

 

The issues set down for the trial were as follows:

 

a.      Whether or not Plaintiff was granted the right to harvest teak trees from the Kaboso West Taungya Series in the Kabo River Forest Reserve (the Concession)

 

b.     Whether or not the teak volume in the said concession was overestimated by Defendant.

 

c.    Whether or not as a result of the overestimation, Plaintiff overpaid Defendants by GH¢508,921.50

 

d.    Whether or not Defendants unlawfully stopped Plaintiff from its operations in the concession from March 2nd to March 25th, 2009 and indefinitely from May 8th, 2009.

 

e.      Whether or not Plaintiff overpaid Social Responsibility to the Community.

 

f.      Whether or not Defendants caused unlawful delays in processing conveyance permits.

 

g.    Whether or not Defendants breached the contract with Plaintiff and/or derogated from its grant of the concession to Plaintiff

 

h.    Whether or not Plaintiff is entitled to its claim.

 

In my opinion, the fact that Plaintiff was granted the right to harvest teak trees from the Kaboso West Taungya Series in the Kabo River Forest Reserve is not in dispute.  As stated above, the gravamen of Plaintiff’s case is that the concession allocated to Plaintiff was over estimated by Defendants as a result of which Plaintiff overpaid Defendants.  Also Plaintiff overpaid the Social Responsibility obligation to the community.  Furthermore, Defendants unlawfully stopped Plaintiff from its operations. Defendants have therefore breached the contract, and/or derogated from its grant of the concession to Plaintiff. Plaintiff has consequently suffered injury and loss.

 

The evidence adduced on behalf of Plaintiff by Dilesh Patel, P.W.1, who said he was a Director/Shareholder of Plaintiff Company, was that pursuant to the execution of Plantation Timber Utilization Contract (Exhibit “C”), Plaintiff was granted permission per exhibit “D”, to harvest the allocated teak trees within the allotted concession.  P.W.1’s further evidence was that Plaintiff engaged one Mr. Bright of Ingot Company to complete the operations under exhibit “C” on behalf of the Plaintiff. According to P.W.1, the prospectus stated that there were 20,885 standing trees with the volume being 12,671 m3.  The Plaintiff signed a contract with the contractor and the operator to do the complete operation for Plaintiff. 

 

Mr. Patel ran the Court through what the operations entailed.  His evidence was that Plaintiff having paid the price, the role of the 1st Defendant was to measure the log which is the volume of the tree.  After the measurement had been taken, then the Plaintiff was permitted to load the log unto their container.  After the total volume of the log loaded into a container was determined, the final document was sent to the Plantation Manager to sign off the conveyance.  The Conveyance is the document which allowed the transporter to take the logs from the site to the Tema Port for shipping.

 

The further evidence of Mr. Patel was that the logs were not measured in time at the beginning; Defendants would not sign the conveyance on time; and the transporter refused to send the containers to Plaintiff because the conveyance had not been signed.  This cost Plaintiff demurrage charges.  Furthermore, 1st defendant stopped Plaintiff from working on four (4) different occasions.  In spite of all the difficulties, Plaintiff managed to export 2,490 cubic meters from the overall 12,671 trees allotted to the Plaintiff.  Mr. Patel tendered in evidence a letter from 2nd Defendant dated 2nd March 2009 (Exhibit “E”) in which letter, Plaintiff was stopped from working without giving any reason for the stoppage.  Pursuant to an appeal to the Minister for Lands, Forestry and Mines (Exhibit “F”) the “suspension” of logging and harvesting operations was lifted per letter dated 25th March 2009 (Exhibit “G”).

 

So, what evidence did the Defendants’ lead to rebut this?  The 2nd Defendant and Hugh-Clement Addoquaye Brown, Operations Manager of the 1st Defendant Company gave evidence for the Defendants.  According to Mr. Addoquaye Brown, prior to the grant of a Timber Utilization Contract, an inventory of the area in question was taken and trees to be harvested were clearly marked.  Any tree that fell outside of those marked for felling or any other species felled outside those allocated constituted an offence under the law. 

 

Mr. Addoquaye Brown’s evidence was that about eight (8) months after the grant of a permit was made to Plaintiff, the Company wrote to 1st Defendant indicating that after working for sometime they had contracted the services of some forestry expert who had combed through the concession and in their estimation, the 12,671m3 which they had bid for would not be realized at the end of the operation.  Plaintiff therefore requested for re-assessment of the standing trees (Exhibit “4”).  With the consent of the CEO of 1st Defendant, a request was made to Plaintiff to pay the re-assessment fee to enable the exercise to be undertaken (Exhibits “5” and “6”). And even though, according to Mr. Addoquaye Brown, they found the request rather strange coming in the middle of Plaintiff’s operations.  1st Defendant acceded to the request. 

 

A team was constituted, after the fee was paid, and the exercise commenced in February 2009; the exercise ended in March 2009.  The Report that was generated at the end of the exercise was tendered in evidence as Exhibit “7”.  He said the Plaintiff’s operations were stopped to allow the exercise to be conducted.  After the re-assessment, the Plaintiff was informed about the new volume, which was much lower than what had been advertised during the competitive bidding.  The value that was realised was more than the 50% deposit that Plaintiff had paid and so Plaintiff was asked to pay the difference owed to the 1st Defendant per letter dated   31st March 2009 (Exhibit “H”).  The balance to be paid was stated as GH¢107,379.77, and Plaintiff was to make the said payment by 3rd April 2009. 

 

It was also Mr. Addoquaye Brown’s evidence that while the re-assessment was going on, the 1st Defendant received directives from the Ministry to stop the operations of all timber companies in the Volta Region to enable some investigations to be undertaken.  The two incidents, according to him, occurred simultaneously.  He denied any knowledge of Plaintiff’s allegation that 1st Defendant had again suspended their operations since 8th May 2009, and stated that Plaintiff’s permit expired on 28th May 2009; He said the earlier suspension at the instance of the Ministry was lifted around the said period.         

 

So, did the Defendants over estimate the teak tree volume in the allotted concession as is being alleged by Plaintiff?  Even though the evidence of D.W.1 was that the Plaintiff voluntarily bid for the concession based on independent assessment carried out by Plaintiff itself; and also that Plaintiff operated in the area for eight (8) months before it requested for re-assessment of the teak volume; the fact of the matter is that the total teak volume of 12, 671m3 stated in the Plantation Timber Utilization Contract (exhibit “C”) was reduced to 6,772.83 m3 after the re-assessment exercise. 

 

The Report and or findings of the team which carried out the re-assessment stated the reasons which accounted for the shortfall in volume. The first reason attributed fire out break as the cause of the shortfall and it is presumed that the fire outbreak took place after the initial assessment.  Another significant observation was the issue of holes in lower sections of teak trees that might have been caused by wildfires in the area.  Some of the teak trees were observed felled but rendered useless by the large holes.  Thus some lying logs with holes were excluded from the measurement of the log length during the re-assessment.  The report also conceded that 10% of the sampling intensity employed in the estimation of the standing tree volume during the initial assessment might have been biased, and this might have over estimated the mean volume.  Lastly, the level of waste associated with Plaintiff’s harvesting operations during the early stages was relatively high.

 

These pieces of evidence were not debunked by the Plaintiff.    Plaintiff did not lead an iota of evidence to establish the basis for their belief that the correct volume ought to be 4,700 m3.  I will therefore find that even though the teak tree volume was reduced as a result of the re-assessment, Plaintiff has not been established that 1st Defendant over estimated the volume in its initial assessment.

 

The evidence placed before the Court was that as a result of the re-assessment, the total outstanding amount owed by Plaintiff on the contract was GH¢107,379.77 which was to have been paid by the Plaintiff by 3rd April, 2009.  Plaintiff led no evidence to establish its claim that it had over paid Defendants by GH¢508,921.50 as a result of the said over estimation of the teak volume.  As a matter of fact, Plaintiff has not established that it has overpaid Defendant by any amount whatsoever; and I will so find.

 

The evidence adduced on behalf of the Defendants was that when Plaintiff failed to pay up the outstanding balance of GH¢107,379.77 by the deadline of 3rd April 2009, 1st Defendant wrote to the Plaintiff’s bankers, Intercontinental Bank, to demand payment under a Guarantee issued by the Bank.  The Bank complied and paid.  The Bank subsequently informed 1st Defendant that Plaintiff had defaulted in some payments to the Bank, and therefore requested the 1st Defendant to hand over the rights of harvest in the concession to the Bank (Exhibit “8”).  1st Defendant wrote to Plaintiff informing them of the Bank’s demand and requested for their consent (Exhibit “9”).  Plaintiff wrote back to 1st Defendant to ask for time to consult their majority shareholder (Exhibit “10”).  Subsequently, Plaintiff wrote to 1st Defendant on December 2, 2009 giving their consent for the transfer (Exhibit “11”).  1st Defendant consequently wrote to the Bank to fulfil certain conditions and when those were fulfilled, the area was transferred to the Bank. So the concession has been allocated to Intercontinental Bank.

 

Plaintiff did not lead evidence to debunk any of the above stated pieces of evidence. However, the Plaintiff’s case is that during the existence of the contract between them and 1st Defendant, 1st Defendant stopped Plaintiff’s operations in the concession on three (3) separate occasions.; (1) for an alleged illegal felling; (2), without stating any reason; (3) for allegedly failing to pay on a Social Responsibility Agreement (SRA) and compensation to some farmers who complained about their crops having been destroyed. And (4),  Defendants refused to issue Plaintiff with conveyance certificate (LMCC) to enable Plaintiff transport its teak lumber to the Port for shipment.  It is Plaintiff’s claim that the said stoppages were in breach of the contract, were improper, unlawful and derogated from the grant of the concession by Defendants.  As a result of Defendants’ conduct, Plaintiff contends that it suffered and continues to suffer damages as endorsed on the writ of summons.

 

It is trite learning that if a contract has been breached, or if a breach is threatened or imminent, there must be a remedy. And, damages are the normal remedy for a contracting party who suffers as a result of a breach of contract by the other. In a claim for damages, the court considers two matters; remoteness of damages (i.e. the proximate cause of the breach) and the measure of damages (i.e. quantum or the amount of money that must be awarded). Remoteness of damages means that the damage i.e. the loss suffered and therefore claimed must be proximate to the breach. The case of Hadeley v Baxendale [1854] 9 Ex. 341 is the locus classicus. This case supplies two tests for determining which damages are proximate and recoverable, and which are too remote and therefore unrecoverable. The tests are:

 

1.    Do the damages arise naturally from the breach? Or

 

2.    Were the damages reasonably contemplated by both parties when they made the contract as being a probable result of the breach.

 

The first damage suffered by Plaintiff, according to P.W.1 was with regard to transportation of logs to the Tema Port. The Plaintiff’s case is that the 2nd Defendant unnecessarily and/or wilfully delayed/withheld the processing of conveyance permit to enable Plaintiff’s teak which it had prepared and loaded into trucks to be conveyed to the Port. P.W.2, Bhavish Patel, who said he represented the international investors and assisted in the day to day operations of Plaintiff Company also testified on behalf of Plaintiff. P.W.2 however did not corroborate the evidence of P.W.1 that the alleged conduct of the Defendants to the effect that 2nd Defendant unlawfully delayed in processing Plaintiff’s conveyance permits. Both P.W.1 and P.W.2 testified that Plaintiff engaged the services of one Bright to carry out its operations, but the said Bright was not called to testify.  In my opinion, Mr. Bright is a material witness and should have been called to testify.

 

2nd Defendant denied the allegation that he delayed/withheld the processing of conveyance permits and testified that the Plaintiff exhibited some level of incompetence and unprofessionalism in their operations. When they started their operations they used some local boys within the community who were inexperienced in loading the trucks and thus it took them longer than usual to load the containers.  His further testimony was that Plaintiff only used the allegation that 1st Defendant was the cause of the delay as an excuse to the truck owners.  2nd Defendant also said that Plaintiff was incompetent in processing or computing the volumes of the material contained in their packing list, resulting in delays. And even though, 2nd Defendant conceded that he refused to sign LMCC’s when there were complaints against Plaintiff with regard to the Plaintiff’s obligations under the SRA, in my opinion Plaintiff did not lead sufficient evidence to establish that this was the cause of the alleged damage suffered by Plaintiff.

 

The position of the law as stated in the oft-cited case of Majolagbe v Larbi [1959] GLR 190 at 192 is that:

 

“Proof in law is the establishment of facts by proper legal means. Where a party makes an averment capable of proof in some positive way e.g., producing documents, descriptions of things, reference to other facts, instances or circumstances and his averment is denied, he does not prove it by merely going into the witness box and repeating that averment by oath, or having repeated by his witness. He proves it by producing other evidence of facts and circumstances from which the court can be satisfied that what he avers is true”.

 

Plaintiff also alleged that Defendants unlawfully stopped their operations a number of times. The first occasion was when 1st Defendant accused Plaintiff of illegally felling three (3) trees which were not the approved teak but of different species; namely mahogany and emire. Plaintiff’s case is that it agreed to pay the fine/fee although it was not guilty of the offence. But more importantly, it is Plaintiff’s case that the contract did not give Defendants the right to stop the Plaintiff from operating.  2nd Defendant’s evidence was that Plaintiff’s permit only allowed them to fell teak trees and within their operational area.  However, during the course of its operations it was found that Plaintiff had felled some mahogany and emire trees.  Plaintiffs were accordingly fined with a deadline of August 28th 2008 to pay the fine.  Plaintiff failed to pay the fine even after three (3) months. 

 

2nd Defendant’s further evidence was that they were forced to stop Plaintiff from operating to put pressure on them to pay the fine.  Plaintiff was allowed to resume its operations after it made part-payment of the fine.  2nd Defendant conceded under cross-examination that per the contract, he was to report any act of non-compliance to the Chief Executive Officer (CEO) of 1st Defendant.  I will therefore find that the contract did not permit 2nd Defendant to stop Plaintiff’s operations.  The fact however remains that Plaintiff did not establish that it was not liable for not complying with the terms of the permit.

 

Plaintiff’s further case is that Defendants again unlawfully stopped it from operating from 2nd to 25th March, 2009. Exhibit “E” captioned “ORDER TO STOP WORK” was tendered in evidence. In the said letter, 2nd Defendant stated that he had been directed by the Executive Director to stop the operations of all contractors granted permit to harvest plantation timber within the Jasikan Plantation Area. The letter was addressed to eleven (11) companies including Plaintiff. Defendants contended that as provided in the Contract, the 1st Defendant gave the reason for the stoppage; the reason being that they had been instructed to suspend operations.  

 

Ordinarily, I would not accept that this satisfies the requirement of stating a reason, but in my opinion there are unanswered questions with regard to this issue. For a start, the provision that Plaintiff is coming under is captioned “Timber Operations Inspection Officers”.  It is therefore not clear that it applies to the situation in question.  Also, it was the evidence of D.W.1, that the period in question coincided with the period when the re-assessment was done, and therefore during that period, Plaintiff could not have continued with its operations.  His further evidence was that the stoppage did not go beyond the period of the re-assessment exercise.  The evidence before the Court is that Plaintiff was asked to resume their operations after the re-assessment. In my opinion there is not sufficient evidence placed before the Court to convince it that Defendants had breached the terms of the Contract.

 

Plaintiff is also claiming that it has overpaid its Social Responsibility obligation to the community. The evidence before the Court is that the Plaintiff was to pay GHc1.18 per cubic meter for the 12,671 m3.  Hence Plaintiff was expected to pay an amount of GH¢14, 951.78 for the 12,671m3. The evidence of both D.W.1and 2nd Defendant was that at the time Defendants stopped Plaintiff for alleged non-payment of SRS, Plaintiff had paid GH¢5,500. Plaintiff’s unchallenged evidence was that at the time of the final stoppage, Plaintiff had removed a total of 2,490 m3.  By simple arithmetic, therefore, Plaintiff was to pay GH¢2, 938.2.  I will find therefore, that Plaintiff had indeed overpaid its Social Responsibility obligation to the community.   However, there is no specific claim for the overpayment, although the issue was set down for trial.  This is a specific payment made by Plaintiff and therefore cannot form part of the damages being claimed by Plaintiff.  Since Plaintiff has made no specific claim for any amount, the Court cannot give to the plaintiff what it has not asked for.  

 

The other matter to be considered is the measure of damages. The position of the law is that damages are the arithmetical computation of how much money must be paid by the party in breach to the party suffering from the breach of the contract.  The purpose of damages is to put the party who has suffered as a result of the breach in nearly the same position that he would have been had the other party not broken the contract.  In Royal Dutch Airlines (KLM) & Another v. Farmex Limited [1989-90] 2 GLR 623 the Supreme Court held that on the measure of damages in breach of contract, the principle adopted by the courts was resitutio in integrum, i.e. if the Plaintiff has suffered damages – not too remote – he must, as far as money could do it, be restored to the position he would have been in had that particular damage not occurred.

 

It is trite learning that damages may be general or special.  And in the instant suit, Plaintiff is claiming both general and special damages.  In Delmas Agency Ghana Ltd. v. Food Distributors International Limited [2007-08] SCGLR 748, the Supreme Court held that general damages is such as the law will presume to be the natural or probable consequence of the Defendant’s act.  It arises by inference of the law and therefore need not be proved by evidence.  The law implies general damage in every infringement of an absolute right.  The catch is that only nominal damages are awarded.  Where the Plaintiff has suffered a properly quantifiable loss, he must plead specifically his loss and prove it strictly. If he does not, he is entitled to anything unless general damages are also appropriate.

 

In the instant suit, the claim for loss of profit; GH¢42,000 in demurrage charges; GH¢57,500 for the 23 days of work stoppage from March 2 to March 25, 2009; and GH¢2,500 per each day from May 8, 2009 until the day Defendants lift the ban or until Judgment; are claims for special damages and have to be proved strictly.

 

Admittedly the authorities have not held that to establish a claim receipts should be provided by all means.  They have nonetheless held that the party who alleges should lead cogent evidence to establish the claim.  The nature of the evidence required was stated in the case of Kubi v. Dali [1984-86] 2 GLR 501, His Lordship Justice Abban stated as follows:

 

“I do not think in the circumstances of this particular case, the production of receipts at the trial could be the only legitimate means of proving special damages and she led cogent evidence to that effect.  She led evidence to show that she incurred hospital expenses, paid for the cost of the police report and spent on transportation to and from the hospital.  In the course of the evidence, the Plaintiff clearly indicated that she had no receipts for some the items but had receipts of others but had lost them and they could not be traced and the court was therefore entitled to accept secondary evidence as given by the Plaintiff.  In respect of those she was not given receipts for it was again a question of fact as to whether or not the expenses were incurred.”        

 

In the opinion of the Court, the issue to be determined is whether or not the Plaintiff, in the circumstances of this case, is entitled to damages at all? And why do I raise this issue? The unchallenged evidence before the Court, as I have already indicated, is that Plaintiff, upon default, consented to the transfer of its interest in the concession to Intercontinental Bank, Plaintiff’s Guarantor. Now, I can understand that Plaintiff took the facility from Intercontinental Bank based on the initial volume assessment of 12,671m3, and therefore Plaintiff may have suffered some loss. Plaintiff may even have suffered some injury as a result of the unlawful stoppage of its operations.   Nonetheless, this does not necessarily give Plaintiff a cause of action.

 

 Why do I say so? The evidence placed before the Court is that when Plaintiff failed to meet the deadline for payment of the outstanding balance of the contract fee, 1st Defendant decided to fall on the Guarantee provided by Plaintiff’s bankers, Intercontinental Bank. P.W.1 raised an issue that Mr. Rexford Agyeman who signed Exhibits “10” and “11” as Managing Director of Plaintiff Company, did not inform P.W.1 as a Director, but it is apparent from Exhibit “10” that P.W.1 was copied.     There is no evidence before me to show that the letters dated 2/10/2009 and December 2, 2009 respectively indeed were not authorised by Plaintiff.   As a matter of fact, these were not the only documents signed by the said Mr. Agyeman that were tendered in evidence.  There is nothing to show that Plaintiff challenged 1st Defendant’s right to fall on the Guarantee at the time that 1st Defendant proceeded to do so.  Neither is there any evidence that Plaintiff made any of the complaints herein at the time of the transfer of their interest. Indeed, the evidence is that Plaintiff consented to the transfer of its interest to Intercontinental Bank without any complaint.  In my opinion therefore, Plaintiff is estopped by its own conduct from now complaining of any act of commission or omission on the part of the Defendants that may have caused any  injury to the Plaintiff during the existence of the contract between them; and I will so find.

 

In conclusion, I will find that Plaintiff is not entitled to general damages nor is it entitled to any of its claims. I shall accordingly dismiss all of Plaintiff’s claims.

 

Costs assessed at GH¢3,000.00 in favour of Defendants.

 

 

 

                                                                                                (SGD)

BARBARA ACKAH-YENSU (J)

JUSTICE OF THE HIGH COURT

 

 

COUNSEL

KWADWO OWUSU AGYEMANG                        -           PLAINTIFF

DENNIS OSEI HWERE                              -           DEFENDANT           

 

Legal Library Services        Copyright - 2003 All Rights Reserved.