GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

COMMERCIAL  COURT CASES

 

IN THE HIGH COURT OF JUSTICE (COMMERCIAL DIVISION) HELD IN ACCRA ON 11TH  JUNE  2010 BEFORE HER LADYSHIP BARBARA ACKAH-YENSU (J)

 

SUIT NO. BFS/302/08

 

 SG-SSB BANK LIMITED                                 === PLAINTIFF

 

                                                          VRS.

 

CHARLES BARTELS                                                === DEFENDANT

 

=======================================================

 

 

 

I

 

JUDGMENT:

 

Per its Writ of Summons, Plaintiff is seeking against Defendant, the following reliefs:

 

“     1.  Recovery of the sum of Two Hundred and Twenty-Five Thousand Five Hundred and Ninety United States Dollars Eighty Cents (US$225,590.80) being the outstanding balance on a facility of US$400,000.00 granted by the Plaintiff, at the request of the Defendant which said amount was due and owing as at the 31st day of March, 2008 to the Plaintiff and which amount Defendant has failed and/or refused to pay to Plaintiff in spite of several and repeated demands made therefor

 

2.     Interest on the said amount at an agreed interest rate of 9.9.% per anum plus an additional of 6% per anum payable on the outstanding arrears from the 31st day of March, 2008 till date of final payments.    

 

3.   Costs.”

 

It is the case of the Plaintiff that it advanced a personal loan of US$400,000.00 to the Defendant for a period of Sixty (60) months payable on monthly basis with interest accruing thereon.  The loan transaction between the parties was governed and covered by a loan agreement which had specified terms and conditions covering same.  Plaintiff called in and terminated the facility according to the terms and conditions stipulated in the agreement.  Plaintiff says it called in the facility as a result of a default on the part of the Defendant.   Defendant was given time to settle or retire his indebtedness but, he did not comply, as a result of which the Plaintiff had no choice than to offset his indebtedness by using the available cash security.  There was still an outstanding amount and the Plaintiff thus instituted the instant action to recover same.

 

The Defendant has denied Plaintiff’s claim.  It is his case that the loan facility was called in under unjustifiable circumstances as a result of which the Plaintiff was therefore in breach of the loan agreement.

Defendant also contends that due to the negligence of Plaintiff some monies amounting to GH¢4,000 were withdrawn from the Defendant’s account.  The monies withdrawn constitutes a breach of trust unbecoming of a bank of Plaintiff’s stature.  The Defendant contends further that he contracted the loan to build a hotel but has since been unable to complete it due to the Plaintiff’s unjustifiable call-in of the loan facility.  Thus it has become very difficult to secure another loan to complete the project.  This has caused a lot of financial loss and income to the Defendant.  Defendant has thus counterclaimed for the following:

 

a.   General damages for the breach of the loan agreement

b.   General damages for negligence and for breach of trust.

c.   Special damages

i.              Monies illegally withdrawn from the Defendant accounts without his consent amounting to GH¢4,000

ii.            Interest on the said GH¢4,000 at the prevailing bank rate

iii.           Estimated loss of Profits of GH¢5,400 per day had the Hotel been completed on schedule.

 

From the pleadings and evidence led, there are some undisputed facts. They are that:

 

1.     Plaintiff was granted a loan facility of US$400,000 by Defendant on 30th April 2006 to be repaid within a period of five (5) years and with a repayment schedule of sixty (60) equal monthly instalments.

 

2.   The facility was a personal loan to be used to complete Defendant’ hotel project in Elmina

 

3.   The loan was secured by

 

a.    A lien on Flexi plus of US$50,000 held in Defendant’s account;

 

b.   Lien over US$60,000 also held in Defendant’s account ,

 

c.   Mortgage over property described as No. 159 Shippi Link, Cantonments owned by Defendant; and

 

d.   Mortgage over Bart Plaza Hotel Building  in Elmina .

 

4.   There was an agreement that there would be an automatic deduction from Defendant’s account every month.

 

5.   Monthly payments were stalled because there was not sufficient money in Defendant’s account.

 

6.   Plaintiff agreed to deduct  instalment payment from Defendant’s account over which Plaintiff had a lien for the month of July 2007.

 

7.    Plaintiff subsequently refused Defendant’s request for the instalment payments for September and October 2007 to be deducted from his account.

 

8.   The facility was called-in by Plaintiff as per a letter dated 12th November 2007 (Exhibit “D”) in which letter Plaintiff was given notice of termination to enable him settle or retire his indebtedness.

 

 

The main issue in contention in my opinion, is whether or not within the terms of the loan agreement the Defendant was in breach that entitled the Plaintiff to call in the facility.  Plaintiff is claiming that Defendant was in breach of the loan agreement for failure to pay some monthly instalments, and thus by virtue of Clause II.0 (a) of the said agreement, it was entitled to call-in the loan.  Defendant on the other hand, denies that there was any default.  His reason being that there was sufficient money in his accounts which Defendant had taken lien over.  Moreover Plaintiff had agreed to deduct the monthly instalment for July, 2007 and there was no reason why Plaintiff refused Defendant’s request to make further deductions for the subsequent months.  More importantly the said clause II.0 (a) did not give the Plaintiff the right to terminate the agreement in the manner it did.  In his evidence, Defendant stated that in his opinion the reason why Plaintiff took the decision to terminate the agreement was because of a letter he wrote to the bank which in his opinion, was a fair critique of the operation of the bank, but which the Plaintiff did not take kindly to.

 

The relationship of banker to customer is one of contract; see Foley v. Hill [1848] HL Cas.28.  It consists of a general contract, which is basic to all transactions, together with special contracts which arise only as they are brought into being in relation to specific transactions or banking services. 

 

So, to the specific contract in question; Exhibit “B”.  The crucial clause in Exhibit “B” is clause II, and it reads:

          “11.0 Termination/Suspension

The Bank has the right to terminate suspend and/or call up the

facility if the terms and conditions stipulated in this agreement

are not met by the Borrower including:

 

a.    Failure to pay any sum when due.

 

b.   False or untrue representations and warranties made prior to and during the tenure.

 

 

c.   Whether the Bank has reason to believe that the Borrower may not be able to abide by the terms and conditions of the facility.

 

d.   Failure to abide by any other covenant term or conditions detailed in this agreement.

 

e.   If the borrower shall take or permit to be taken, any actions or proceedings whereby any of his properties shall or may be liable to be assigned or in any manner transferred or delivered to other person whether appointed by the borrower or otherwise whereby such property shall or may be distributed among creditors of the Borrower.

 

In the event of suspension the right of Borrower to draw upon the facility shall continue to be suspended until the event which gave rise to such suspension shall have ceased to exist to the satisfaction of the Bank or until the Bank shall have notified the Borrower that the right to draw upon the facility has been restored.  Notwithstanding any suspension or termination pursuant to the above, all the provisions of this agreement shall continue in full force and effect to the benefit and protection of the Bank’s interest. 

 

The evidence led by Plaintiff’s representative, Nana Kofi Bame (P.W.1) was that the loan agreement was breached because of the failure of Plaintiff to pay two (2) instalments for September and October 2007.  He said that by virtue of the agreement, Plaintiff had the right to call-in the facility.  The Defendant in his evidence denied that there was any default to talk about.

 

The position of that law is that monies lent to a customer are

repayable either on demand or at a specified future date.  Term loans usually list events of default on the occurrence of which repayment can be demanded before the date on which the bank reserves the right to make prior demand; the agreement however may present difficulties of construction as is being contended by Counsel for Defendant. 

 

This occurred in the English case of Titford Property Co. Ltd. v. Cannon Street Acceptances Ltd. [22nd May 1975, unreported]

Where the Defendant merchant bank had granted the claimant companies fixed term overdrafts to finance their property development business.  There was a separate account and overdraft facility for each project.  Each facility letter contained the following clause:

 

“9’  All monies due by you, whether by way of capital or interest, shall be payable on demand, and you shall have the right to re-pay all monies due without notice.”

 

The lenders demanded repayment before the fixed expiry date of certain of the facilities and appointed receivers on default in repayment.  The claimants applied for injunctive relief.  Goff J viewed the construction of the facility letters as an issue which did not depend on disputed facts and which he was therefore bound to decide.  He held (i) that ‘due’ in the first of Clause 9 meant ‘due, whether presently payable or not,’ this being clear from the second part of the clause; but (ii) that Clause 9 so construed was ‘completely repugnant to the whole facility’ and accordingly, it had to be modified, by reading it as subject to the provision as to the duration of the facility, or ignored altogether.

 

The Titford case may be compared with Williams and Glyn’s Bank v. Barnes [1981] COM LR, 205, where a bank granted an overdraft facility which it knew was to be used to finance a particular transaction.  However, the overdraft was expressly repayable on demand and was not granted for a fixed period.  Peter Gibson J held that the bank was entitled to demand repayment at any time.

 

In Lloyds Bank PLC v. Lampert [1999] 1 All ER (Comm) 161, CA, a facility letter provided that the loan would be ‘repayable in full on demand’ but that the bank intended to make the facility available until

 

a specific date.  After citing the Titford Property case and the Williams and Glyn’s Bank case, Kennedy LJ said (at 167-168):

 

“I am wholly un-persuaded that the words ‘repayable on demand’ used in the facility letter do not mean what they say.  It is in no way inconsistent for a bank or any other lender to grant a facility which it and the borrower both envisage will last for some time, but with the caveat that the lender retains the right to call for repayment at any time on demand”

 

This decision was followed in Bank of Ireland v. AMCD (Property Holdings)Ltd’s [2001] 2 All ER (Comm) 894 in which the Defendants had arranged funding of £1.4m from the claimant bank for a property development venture.  The facility letter provided for a term of 12 months from the first use of the facility, and for repayment on demand or, ‘in the expected ordinary course of events’, from the sale of the development within 12 months.  The letter also provided that in the event of the non-payment of any money due which had not been rectified to the satisfaction of the bank, the bank would be entitled to make demand for immediate repayment.  The court held that it was not seriously arguable that the provisions of a facility letter which envisaged (i) that the facility would be available for a period of 12 months; and (ii) that the bank was entitled demand immediate repayment in the event of non-payment, were repugnant to or overrode in any way a clear statement that repayment was to be made ‘on demand’. 

 

Further, it was trite law that parties to a contract were free to determine for themselves what primary obligations they would accept, and in the instant case there was no warrant for treating the repayment provision otherwise than in accordance with the terms.  No business person could have understood that provision in any sense other than that for which the bank contended, namely that the amounts advanced were repayable on demand, but that, if all went well, the bank would expect to receive repayment from the sale of the development.        

                                       

In his written address, Counsel for Defendant submitted that a cursory reading of Clause 11 .0 (a) of Exhibit “B” would suggest that failure by Defendant to pay any instalment resulted in an automatic breach of clause 11.0 (a) of Exhibit “B”.  The question however is whether it can be fairly contended that where, as in this instant case, out of a total of over 60 instalments, Defendant makes default in the payment of two, the intention of the parties was that the agreement should automatically terminate.

 

In this regard, Counsel relied on the case of Biney v. Biney [1974] 1 GLR 318 CA, in which case it was opined that interpretation/construction of deeds and documents should take into account “the mind and intention of the author”. Hence, whether it can fairly be contended that where, as in the instant case, out of a total of 60 instalments, if Defendant defaults in payment of 2, the intention of the parties was that the agreement should automatically terminate.  Defendant’s position is that Plaintiff’s decision to terminate Exhibit “B” is unjustifiable.

 

It is the case that in the last resort, when parties have differing views about what their contract means or what its effect on their legal rights and obligations is, their difference must be settled by the court, or by arbitration.  In arriving at its conclusion the court applies relatively well established principles of construction.  It is commonly, though inaccurately, thought that the purpose of interpreting a contract is to discover the actual intentions of the contracting parties.  In Pioneer Shipping Ltd v. B.T. P. Tioxide Ltd [1982] A.C. 724, Lord Diplock said:

 

“The object sought to be achieved in constructing any contract is to ascertain what the mutual intentions of the parties were as to the legal obligations each assumed by the contractual words in which they sought to express them.”

 

The position of the law is that the intention of the parties must be ascertained from the language they have used, considered in the light of the surrounding circumstances and the object of the contract, in so far as that has been agreed or proved.  Thus in Leader v. Duffey [1888] 13 App. Cas. 294, Lord Halsbury L.C. said:

 

“...I agreed that you must look at the whole instrument, and inasmuch as there may be in accuracy and inconsistency, you must, if you can, ascertain what is the meaning of the instrument taken as a whole in order to give effect, if it be possible to do so, to the intention of the framer of it”.

 

This rule of interpretation which requires that in interpreting a deed or instrument it must be read as a whole was also stated in the case of Boateng v. Volta Aluminium Co. Ltd [1984-86] 1 GLR 734, CA

 

Defendant’s contention is that under and by virtue of Exhibit “B”, upon default by Defendant in the payment of any instalment, the natural consequence and/or remedy as per Exhibit “B” was not the calling-in of the loan facility and for that matter terminating same.  This is because there is also the option provided under clause 13 of Exhibit “B” which provides as follows:

 

“In the event of default in repayment terms and other conditions, the Bank shall be at liberty to sett off and apply any and all deposits (general or special, time or demand, provisional or final) at any time held or other indebtedness at any time owing by the Bank to or for the credit of the Borrower against any and all of the obligations of the borrower which may now or hereinafter exist under this Agreement or any other Agreement and whether such  deposit, indebtedness or obligations may be un-matured or contingent.  The Bank’s rights hereunder are in addition and without prejudice to other rights and remedies including without limitation, other rights of set off which it may have.” 

 

Defendant’s view there is that having regard to clause 13.0 of Exhibit “B” even if Defendant had breached clause 11.0 (a) the remedy was to apply clause 13.00 by using some of his funds standing to his credit with Plaintiff to pay off any instalment due and owing to Plaintiff.

 

There is a second reason why Defendant contends that there was no breach by Defendant of Exhibit “B” that justified Plaintiff’s decision to terminate the agreement.  The reason being that the parties had themselves recognised the fact that the failure by Defendant to pay one instalment did not warrant the calling in of the facility.  Defendant’s evidence was that when there was not sufficient money in Defendant’s account to meet the instalment payment for the month of July 2007, P.W.1 advised Defendant to apply for the use of his cash security for payment of his instalments. According to Defendant,

this arrangement was consistent with clause 13.0 of Exhibit “B”. 

 

In my opinion the Defendant is asking the court to do equity.  However, it is common knowledge that equity follows the law and where the law is clear the court cannot do equity.  I am saying this because the parties herein entered into a contract, Exhibit “B”. 

 

Contracts freely entered into by parties with capacity are treated in law as scared. The law is concerned with the free will of the parties and not with the fairness of the terms of a valid contract.  Courts uphold the sanctity of contracts for a number of related reasons.  Firstly, there is a judicial deference to the contracting parties.  The argument here is this; if the parties have freely come to terms, the courts must defer to the parties and respect those terms.  Secondly, courts find themselves incompetent, and are therefore reluctant, to

substitute terms freely entered into by parties themselves.  Anin J.A. put it succinctly in his dissenting judgment in Addision v. A/S Norway Cement Export Ltd [1973] 2 GLR 151 at 162, as follows:

 

The parties must make their own contract; and the courts will not make a contract for them..”  

 

It is my opinion that the language used in clause 11 is very simple and therefore there is no need for the court to attempt to ascertain the presumed intention of the parties. The parties herein agreed that Plaintiff had the right to terminate, suspend and/or call up the facility if Defendant failed to pay any sum when due (emphasis mine).  There is no ambiguity with regard to this term of the contract.  It is one of the rules of construction that where words of a contract are clear, the Court must give effect to them even if they have no discernible commercial purpose.

 

So in Safeway Food Stores Ltd v. Banderway Limited [1983] 267 E.G. 850 Goulding J rejected  an invitation to depart from the literal meaning of the words.  He said.

 

“It may not be what one would think most probable, but there is nothing absurd about it, nothing insensible about it.  For all that I am entitled to know in a construction case, the matter may have been so arranged as the result of bargaining on various points between the original landlord and the original tenant.  If I assume that they had a common intention different from what the words express, I think I am merely guessing and accordingly on this point the defendant succeeds.”  

 

And in Charter Reinsurance Co. Ltd v. Fagan [1966] 3 All ER 46 HL, Lord Mushill said:

 

“There comes a point at which the court should remind itself that the task is to discover what the parties meant from what they have said, and that to force upon the words a meaning which they cannot fairly bear is to substitute for the bargain actually made one which the court believes could better have been made.  This is an illegitimate role for the court.  Particularly in the field of commerce, where the parties need to know what they must do and what they can insist on not doing, it is essential for them to be confident that they can rely on the court to enforce their contract according to its terms.”

 

Plaintiff also had the right to terminate, suspend and/or call up the facility “where the Bank has reason to believe that the Borrower may not be able to abide by the terms and conditions of the facility”.  The evidence placed before the Court was that Defendant never used monies or proceeds from his personal earnings as stated in Exhibit “J” of which Defendant was a signatory.  Rather, Defendant made the monthly instalment payments from the loan itself and when the money got finished he, albeit on the advise of his relationship manager, P.W.1, requested for the bank to deduct the July 2007 instalment from his account with the Bank.  In my opinion Plaintiff had good reason to believe that Defendant may not be able to abide by the terms and conditions of the facility.  Moreover, Plaintiff had applied for additional funding from Defendant but his request had been rejected. 

 

I will therefore find that Defendant was in breach of the Contract Exhibit “B” and therefore Plaintiff was entitled to call in the facility.

 

So, Defendant called in the loan facility on the 12th of November, 2007 and Plaintiff was given up till the 3rd of December, 2007 to clear his indebtedness.  Failure to do so necessitated a set off as provided for in clause 13 of Exhibit “B”.  By virtue of clause 7.0 of the loan agreement, Plaintiff took a four-leg security from Defendant. Clause 13.0 provided that in the event of default of the repayment terms, the bank shall be at liberty to set off and apply any and all deposits held by the Bank for Defendant against any obligations of the Defendant.

 

Per Exhibit “J” which is a Deed of Assignment, Defendant assigned two (2) foreign currency accounts to Plaintiff as part of the security for the loan facility.  And by virtue of the said Exhibit “J” and clause 13.) of Exhibit “B”, Plaintiff exercised its right of set-off.

 

A banker’s set off is a right, not an obligation.  Accordingly, a customer who maintains two current accounts has, in the absence of agreement, no right to draw a cheque on one on which the balance is insufficient to meet it and expect the cheque to be paid if the combined balance is sufficient.  See Direct Acceptance Corporation Ltd. v. Bank of New South Wales [1968] 88 WN NSW 498 per Macfarian J.

 

Thus upon termination of the contract, Plaintiff applied the monies in the assigned accounts to off-set the balance outstanding on the loan facility.  Defendant’s claim is that there is yet an outstanding balance of US$225,590.80 as at 31st day of March 2008.  P.W.1 tendered in evidence Exhibit “C”, a loan report that was generated to track the repayment instalment and/or any other commitments that are due. 

 

From the above, I will find that Plaintiff has established its case and is therefore entitled to its claim.           

 

Defendant, as earlier stated, has counterclaimed.  As I have already stated, there is no doubt that even though the loan granted to Defendant was described as a personal loan, it was understood between both parties that it was for the purpose of completing Defendant’s hotel project in Elmina.  However, I have not made any finding that Plaintiff breached the contract and therefore no award of damages arises.  

 

It is trite learning that the purpose of damages is to put the party who has suffered as a result of a breach of contract in nearly the same position that he would have been had the other party not broken the contract.  In Delmas Agency Ghana Ltd. v. Food Distributors International Ltd [2007-2008] SCGLR 748, it was held that general damages or as such as the law will presume to be the natural or probable consequence of the defendant’s act.  It arises by inference of the law and therefore need not be proved by evidence.  Where the Plaintiff has suffered a properly quantifiable loss, he must plead specifically his loss and prove it strictly.

 

I will find that in the circumstances of this case, Defendant is not entitled to general damages.  Neither is he entitled to special damages for the estimated loss of profits of GH¢5,400 per day had the hotel been completed on schedule.  As I have state there has been no finding that there has been a breach by the Plaintiff.   

 

Defendant is also claiming general damages for negligence and/or breach of trust but did not lead sufficient evidence to assist the court make a determination on this.   I will therefore find that Defendant is not entitled to this claim.

 

With regard to the claim for special damages for monies illegally withdrawn from the Defendant’s accounts without his consent amounting to GH¢4,000.00, the issue has become moot since there is evidence that the Defendant was invited to go for a refund of the said money.  The letter from Plaintiff was tendered in evidence by Defendant’s first counsel as Exhibit “2”.  In the circumstances, I will find that Defendant is not entitled to this claim nor the claim for interest on the said amount.

 

In conclusion, I will find that Plaintiff is entitled to its claim and hold that Plaintiff recovers from Defendant the sum of US$225,590.80 together with interest at the agreed interest rate of 9.9.% per anum plus an additional of 6% per anum payable on the outstanding arrears from the 31st day of March, 2008 till date of final payment.

I will dismiss all of Defendant‘s Counterclaim.

 

Costs assessed at GH¢2,500.00 against Defendant.

 

 

 

                                                                             (SGD)

 BARBARA ACKAH-YENSU (J)

JUSTICE OF THE HIGH COURT

COUNSEL

GEORGE  HEWARD MILLS                   -        PLAINTIFF

THADDEUS SORY                        -        DEFENDANT

 
 

Legal Library Services        Copyright - 2003 All Rights Reserved.