GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

COMMERCIAL  COURT CASES

 

IN THE HIGH COURT OF JUSTICE (COMMERCIAL DIVISION) HELD IN ACCRA ON THE 8TH SEPTEMBER 2011 BEFORE HER LADYSHIP BARBARA ACKAH-YENSU (J)

 

SUIT NO. BDC/67/09

 SHARP PHARMACEUTICALS LTD               =======    PLAINTIFF

 

                                                  VRS.

 

                                                VANGUARD ASSURANCE CO LTD              =======    DEFENDANT

 

=======================================================

 

 

 

JUDGMENT:

 

Vanguard Assurance Company Limited (the Defendant herein), an insurance company, guaranteed the successful execution and completion of a contract between the Plaintiff herein, Sharp Pharmaceuticals Ltd on one hand, and Decision Resource (the Contractor) on the other by issuing Advance Payment Bond and Performance Bond.  Sharp Pharmaceuticals says that the Contractor has refused, failed or neglected to enforce the Contract “as agreed per the said bonds.” And even though they have informed the Defendant of the breach and demanded the immediate settlement as per the Bonds, the Defendant has failed or refused to honour same. The Plaintiff has therefore sued the Defendant seeking the following reliefs:

 

“   (i) An order for the enforcement of the Performance and

Advance Payment Bonds  

 

(ii).     Costs .”

 

The Plaintiff’s case as per its pleadings and evidence of its Managing Director, Kwabena Abankwa-Yeboah is that in August 2008 it entered into an agreement with the Contractor for the supply, fabrication and installation of glazed aluminium windows, doors, curtain walls and internal partitioning of its offices at Adabraka, Accra (the Contract); Exhibit “A”. It paid 85% of the total Contract Sum to the Contractor for the installation of glazed aluminium windows, doors, curtain walls and internal partitioning of office. The Defendant, as a condition for the award of the contract, provided an Advance Payment Bond and Performance Bond as guarantee for the successful completion by the Contractor of the said works.

 

Mr Abankwa - Yeboah testified further that the Performance Bond and the Advance Payment Bond issued in the first instance were valid for the period between the 13th August 2008 and 12th November 2008.  However by 12th of November 2008, the Contractor had failed to deliver on the Contract and the Plaintiff called on Defendants to pay up on the guarantee.  This caused Defendant to invite the Contractor and after their discussions decided to extend the Advance Payment Bond and the Performance Bond to June 2009.  The Plaintiff agreed to these terms to allow the Contractor more time to deliver on the Contract.  But in spite of the above extension, as at June 2009 the Contractor had failed to install the glazed windows and doors except for installing some erroneous curtain wall. 

 

The Defendant admits issuing the Advance Payment Bond and Performance Bond to guarantee the performance of the Contract by the Contractor.  The Defendant, however, contends that the readiness of the site for the contracted works was a condition for the Contractor’s performance of the Contract and further that, at all material times, the site had not been ready.  To the extent that the site was ready the Contract had been fully performed by the Contractor.  The Contractor has not been able to complete the contracted works because of the Plaintiff’s own default.  The Defendant is also contending that the Plaintiff is not vested with an accrued or present cause of action against the Defendant.

 

The Defendant further contends that Plaintiff had only paid 37% of the total contract sum to the Contractor and not 85% as pleaded by the Plaintiffs.  Defendant also contends that Plaintiffs action against the Defendant was time barred and that the action had to be brought within three (3) months of the expiry of the bonds and that consequently the instant action is out of time.

 

The issue as to whether or not the Plaintiff’s claim should be submitted to arbitration in accordance with provisions of the contract between the Plaintiff and the contractor is moribund in my opinion. It is trite learning that an arbitration agreement need not be separate from the main contract; it may be a clause in the contract.  Apart from the fact that there was no evidence of an arbitration agreement placed before the Court, the position of the law is that the mere presence of an arbitration clause in an agreement does not oust the jurisdiction of the Court. The Court’s duty if an application is made is to consider it and in appropriate cases make an order to stay proceedings; as stated in the case In Re. Ghana Private Road Transport Union (GPRTU); Tetteh v. Essilfe [2001-2202] SCGLR 786.  In the instant case no application has even been made for stay of proceedings.

 

In my opinion therefore the main issues to be determined by the Court are:

 

1.   Whether or not the Plaintiff has a present or accrued cause of action against the Defendant.

 

2.   Whether or not the Plaintiff is out of time in bringing the instant action.

 

3.   Whether or not the Plaintiff is entitled to its claim.

 

Whether or not the Plaintiff has a present or accrued cause of action against the Defendant.

 

According to Kpegah JSC in the case of NPP v NDC and Others (2000 civil motion no.36 2000), the term “Cause of Action” can be defined as an occurrence which gives right to an enforceable claim or relief in law or equity. Thus in the instant suit, the moment that the Contractor’s alleged default/breach occurred, based on the Defendant’s guarantee, the Plaintiff had a cause of action. The Defendant has not denied Plaintiff’s assertion that it immediately notified Defendant of the Contractor’s breach. It is also trite learning that the mere issuance of the writ by the Plaintiff constituted notice to the Defendant by the Plaintiff of the alleged breach of the Contractor.

 

I will therefore find that the Plaintiff has a cause of action.

 

Whether or not the Plaintiff is out of time in bringing the instant action.

 

According to the terms of the Advance Payment Bond and the Performance Bond any action or suit brought in respect of the said Bonds was to be brought within three (3) months of the expiration of the Bonds. The evidence before the Court is that the original Bonds issued on 12th August 2008 (Exhibits “B” and “B1”), and which were to expire on 12th November 2008, were re-issued by the Defendant (Exhibit “C” and “C1”). The renewed period was from 12th November 2008 to 30th June 2009. The instant action was filed on 24th August 2009, within two months of the expiration of the Bonds. It is therefore very clear that the Plaintiff is not out of time in instituting the instant action, and I will so find.

 

Whether or not the Plaintiff is entitled to its claim.

 

The Plaintiff’s action is founded upon the Defendant’s Advance Payment Bond and Performance Bond.  The Plaintiff entered into the Contract with the Contractor for the works described above.  To protect itself from loss in case of default by the Contractor in the performance of the Contract the Plaintiff requested for guarantee in the form of Advance Payment Bond and Performance Bond; Exhibits “B” and “B1” which were subsequently extended (Exhibits “C” & “C1”).  The guarantee was provided by the Defendant on behalf of the Contractor.

 

In the construction industry cash-flow problems are common.  The employer therefore runs the risk of a project worth millions being abandoned at a critical stage because the contractor has suddenly become insolvent.  Traditionally in the construction industry, these problems were met by the practice of requiring the contractor to provide guarantee from a bank or, more often, an insurance company, to secure the performance of his obligations.  These guarantees would normally take the form of a conditional bond or “surety bond”. 

 

Such bonds will contain an undertaking that the contractor will perform a particular obligation such as repay a deposit or simply to do the work which he has contracted to carry out. In the absence of a specific provision to the contrary effect, he would normally have to prove the contractor’s default and how much it has cost him, before he can recover under the bond; see Nene Housing Society v National Westminster Bank [1980] 16 B.R.L. 22; Guyana and Trinidad Mutual Fire Insurance Co Ltd v Plummer and Associates Ltd [1992] 8 Const. L.J. 171; Perar v General Surety and Guarantee Co Ltd [1994] 66 B.L.R 72.

 

The Advance Payment Bond is a guarantee supplied by a party receiving an advance payment to the party advancing. It provides that the advanced sum will be returned if the agreement under which the advance was made cannot be fulfilled. It is given by the contractor that he will repay or settle the advanced cash paid by the owner related to contract. This bond ensures that the principal will perform his obligation as mentioned in the contract. If he fails to perform his obligation, then this bond makes the obligator to repay the advance as per contract.  

 

The Advanced Payment bond is used by building contractors to fulfil his contract within the contract period. If any loss incurred to the purchaser, then the loss will be covered by the insurance company.  Surety Company will cover the loss only when the builder cannot be able to use the down payment given by the customer or the builder cannot be able to refund the amount given by the customer. This ensures that the contractor will complete his contract as per the agreement.

 

The type of suretyship most frequently encountered in the construction context is the Performance Bond (or Performance Guarantee). A Performance Bond is a surety by an insurance company or a bank to guarantee satisfactory completion of a project by a contractor. For example, a contractor may cause a performance bond to be issued in favour of a client for whom the contractor is constructing a building. If the contractor fails to construct the building according to the specifications laid out by the contract, the client is guaranteed compensation for any monetary loss up to the amount of the Performance Bond.

 

Performance Bonds may be considered as falling into two categories. Conditional performance bonds exist where the guarantor only becomes liable to the party entitled to claim the bonded sum (the beneficiary), on proof of breach of the terms of the underlying building contract, or on proof of both breach and loss as a result of the breach. Unconditional or (more usually) “on demand” bonds exist where, on a true construction of the words used in the bond, the guarantor is liable to pay the beneficiary the bonded sum when demand is made in the manner provided for in the bond, without the need for the beneficiary to prove the breach of the underlying building contract or damage (or both). It is a question of construction in each case whether a bond taken as a whole, is conditional or “on demand” and, in the former case, the nature of the conditions attaching to the bond, will also be a matter of the construction of the language used.

 

The Performance Bond in the instant suit, Exhibit “C1” reads inter alia as follows:

 

“NOW THEREFORE, the Condition(s) of this Obligation is such that, if the Contractor shall promptly and faithfully perform the said contract (including any amendments thereto) then this obligation shall be null and void; otherwise it shall remain in full force and effect.  Whenever the Contractor shall be, and declared by the Employer to be in default under the Contract, the Employer having performed the Employer’s obligations there under, the Surety may promptly remedy the default, or shall promptly.

 

(1) Complete the contract in accordance with its terms and conditions; or

 

(2) Obtain a Tender or Tenders from qualified bidders for submission to the employer for completing the Contract in accordance with its terms and conditions, and upon determination by the Employer and the Surety of the lowest response bidder, arrange for a Contract between such bidder and Employer and make available as work progresses (even though there should be a default or a succession of defaults under the Contract or Contracts of completion arranged under this Paragraph) sufficient funds to pay the cost of completion less the Balance of the Contract Price:  but not exceeding, including other cost(s) and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof.  The term “Balance of the Contract price” as used in this paragraph shall mean the total amount payable by the Employer to the Contractor under the Contract, less the amount properly paid by the Employer to Contractor; or

 

(3) Pay the Employer the amount required by the Employer to complete the Contract in accordance with the terms and conditions up to a total not exceeding the amount of this Bond...............................

 

The surety shall not be liable for a greater sum than the specified penalty of this Bond.”

 

Under the said Performance Bond therefore, whenever the Employer declares the Contractor to be in default under the Contract “the surety may promptly remedy the default or shall promptly;” (1) complete the contract; (2) obtain a Tender or Tenders from qualified bidders for submission to the employer for completing the contract in accordance with its terms and conditions; (3) pay the employer the amount required by the Employer to complete the Contract.

 

As indicated above, the liability of the surety or guarantor is determined by the wording of the guarantee.  He is bound only in accordance with the proper meaning and effect of the written agreement he has entered into.  Lord Chancellor Lord Westbury said in Blast v. Brown (1962) 45 ER 1225 at 1229 as follows:

    

“It must be recollected in what manner a Surety is bound.  You bind him to the letter of his agreement.  Beyond the proper interpretation of that engagement you have no hold on him.”

 

In my opinion from the wording of the Performance Bond, Exhibit “C1”, it is a conditional performance bond and therefore the Plaintiff had to prove that the Contractor had breached the terms of the agreement between them.  Conditional bonds are based upon breach of the underlying contract by the contractor, and because they are based on a failure by the principal to perform, conditional bonds are in the nature of contracts of guarantee.

 

The position of the law and this is common knowledge, is that for every case there is a burden of proof to be discharged and the party who bears the burden will be determined by the nature and circumstances of the case. Our Evidence Decree 1976 (NRCD 323) as interpreted in Ababio v Akwasi 111 [1994-95] Ghana Bar Report, Part 11, 74 in which case it was held that a party whose pleadings raise an issue essential to the success of the case assumes the burden of proving such issue. In Takoradi Flour Mills v Samir Faris [2005-06] SCGLR 882 Ansah JSC exhaustively dealt with the burden of proof as follows:

 

“ a great deal of the submission made on the behalf of second defendant in support of the grounds of appeal, centered on the burden of proof, or the onus probandi, by which it is the duty of the party who asserts the affirmative to prove the point in issue. This was expressed in classical terms ei incumbit probation qui dicit, non qui negat. As it was the Plaintiff who made the claim and asserted the positive, he had to adduce evidence sufficient to establish a prima facie case, as required by section 14 of the Evidence Decree, 1975 because in law where a fact is essential to a claim, the party who asserts the claim has the burden to persuade the Court of existence of that fact. The standard of proof is by a preponderance of the probabilities: see section 12(1) of the Decree section 17(1) states that the burden of producing any particular fact is on the party against whom a finding on that issue would be required in the absence of further proof ”.

 

As stated by Justice Mensa-Boison JA, in the case of Acquaye v Awotwi [1982-83] 2 GLR 110, the testimony of a plaintiff is presumptive evidence which is rebuttable. The well-known rule of evidence is that although proof in a civil case rested on the plaintiff, that burden was discharged once the plaintiff had introduced sufficient evidence of the probability of his case. It would then rest on the defendant to rebut the plaintiff’s evidence. Thus in Re Ashalley Botwe Lands: Adjetey Agbosu & Ors v Kotey & Ors [2003-04] SCGLR 420, it was held as follows:

 

“….the burden of producing evidence in any given case was not fixed, but shifted from party to party at various stages of the trial depending on the issue(s) asserted and/or denied.”

 

 

So did the Plaintiff prove the breach?  The evidence of Mr. Abankwa-Yeboah was that the Contractor had earlier on breached the Contract consequent to which the Plaintiff, upon terms specified by the Contractor and the Defendant accepted an extension of the guarantee.  Plaintiff’s evidence on this issue was not controverted in any way by the Defendant.

 

Mr. Abankwa- Yeboah tendered in evidence as Exhibit “A” the Contract in question.  The Contract indicated how much was involved and how much the Contractor had received in respect of the Contract.  Mr. Abankwa-Yeboah led evidence to show that at least 85% of the Contract Sum had been paid to the Contractor who had provided the Performance Bond and Advance Payment Bond from the Defendant as guarantee for the successful completion of the Contract from August 2008 to November 2008.  But for the period of twelve (12) weeks covered by the said guarantees, the Contractor failed to perform except that the Contractor only began installing some aspects of the curtain wall with wrong materials.

 

Mr.  Abankwa - Yeboah’s further testimony was that when the Contractor failed to perform he made attempts to call in the guarantee provided by the Defendant who advised that the Contractor extend the guarantee.  This extension was duly done by the Defendant from November 2008 to June 2009.  In spite of this extension the Contractor failed to perform the works on the site and has since failed to carry on any works on the site.  Mr. Abankwa-Yeboah’s led evidence to show that the site’s readiness was upon the instruction of the Contractor and the site was made ready and it was based on the readiness that the Contractor was able to install the curtain walling.

 

However, the Manager of the Contractor, Christopher Kobla Darkey (D.W.1) testified that the non-readiness of the site contributed to his breach.  I find it rather difficult to believe that the Plaintiff who needs his premises for the conduct of its business and had paid 85% of the contract sum to the Contractor, as admitted by D.W.1 during cross-examination, would not make the premises ready for instalment. This is what D.W.1 said under cross-examination:

 

Q:      As per the Agreement, 60% advance payment was to be made to you to begin the contract,  a further 25% and the 15% when u are done with the job; As we speak, have you received the first 60% and second 25% of final payments?

 

          A:      Yes my Lord.

 

I will make a finding at this point that the Contractor was paid 85% of the Contract Sum and not 37% as pleaded.

 

Mr Abankwa –Yeboah’s evidence was that the site was ready for the Contractor to do the works; the site had been ready since August 2008. That, it was because the site was ready that the Contractor even started with the glazing windows in the first place. He said that he rented scaffoldings and sent them to the site but had to send them back as a result of the default of the Contractor. Plaintiff tendered pictures of the site through D.W.1 (Exhibit “D”, “D1” – “D6”) to show the readiness of the site. His further evidence was that the Contractor did not set foot on the site after the extension of the guarantee by the Defendant. This piece of evidence was not challenged by the Defendant.

 

I must say here that I believe Mr Abankwa – Yeboah, and will accept his evidence as against that of Mr Darkey, D.W.1 who I did not find to be a credible witness. I shall expatiate on my reasons later in the judgment.

 

D.W.1 testified that aluminium profiles he had procured were at Korle- Bu, and the glass in his warehouse at Labone Junction.  While it had been agreed that 60% advance payment and a further 25% payment was to be made upon delivery of materials unto the site prior to installation, D.W.1 had collected the monies without delivering the materials.  It was further suggested to him that the position that hacking ought to have been done before manufacturing of the glazed doors and windows was not a true professional position.  This is so because D.W.1 admitted that he ought to manufacture the window or door and when it was done, he would the hack the windows and fit it in what he had manufactured.  This was contrary to his earlier position that the windows and doors had to be hacked before manufacturing the glazed windows and doors.

 

Mr Abankwa – Yeboah, in his evidence, denied the Defendant’s assertion that there were no final levels for the installation of windows and doors, and that the the walls had not been tiled. Mr. Abankwa-Yeboah also led evidence to show that filing was to be done after the installation of doors and windows.  D.W.1 however sought to deny this but his answers were with inconsistencies.  This is what transpired:

 

Q:      Let us consider this scenario, is it not the case that           if we lay    tiles considering these two windows it is possible that you will have the tiles tilting from this angle up until we get it the other angle, is it not the case?

A:      It is not the case

Q:      So it is not possible to have tiled tilting from that end to other end?

A:      I am saying that is possible but that will be very bad construction.

Q:      So you agree that that is the case?

A:      I do not agree

Q:      I am asking is it not the case that if we do have such bad construction then by the time we get to that level, if we pick window levels from this angle to that angle, the windows would have tilted and not been on the same level?

A:      That it possible but in as much as the levels will more or less determine the window production, the other essential factors that we have been overlooking all this while is that we could not have installed sub frames.  The sub frames could not have been installed because the openings of the windows have not been hacked off.  So the level alone should not determine the production and installation of the windows, there are other factors and then for me, I think you are more or less ignoring them.

 

These answers is an admission on the part of D.W.1 that his position that window levels had to be taken from the tiles was not the truthful position and that he was to manufacture windows and doors regardless of whether or not the tiles had been laid.

 

D.W.1’s evidence was that the site was to be ready for the Contractor to install what he had manufactured, yet he claimed that he had not manufactured any of the windows, doors and partitioning to date and that the materials were at his warehouse.  

 

The case of Kayiofi v Wono (1967) GLR 463 at 466 provides the relevance of the question of credibility of a witness as follows:

 

“The question of impressiveness on convincingness are products of credibility and veracity.  A court becomes convinced, impressed or unimpressed with oral evidence according to the opinion it forms of the veracity of the witnesses.”

 

D.W.1 the sole witness of the Defendant contradicted himself throughout his testimony and this comes out clearly as whatever he said contradicts the Defendant’s defence as well as his own evidence.

 

The dictum of Edward Wiredu J.A. (as he was then) in Atadi v Ladzekpo (1981) GLR 218 at 224 states that it is not open for a trial court to gloss over conflicts when adducing evidence, and make a finding in favour of the party whose case contains the conflicting evidence.

 

Also, in Obeng v Bempoma (1992 – 93) Ghana Bar Law Reports, 1029, Lamptey J remarked that:

 

“Inconsistencies, though colourless may cumulatively discredit the claim of the proponent of the evidence.”

 

In my opinion the Plaintiff has satisfied the requirement of the law with regard to proof and has presented the court with sufficient and cogent evidence of the breach of the agreement by the Contractor and is entitled to its claim against the Defendant.


 

In conclusion, I will order the enforcement of the Performance Bond and Advance Payment Bond by the Defendant.

 

Costs assessed at GH¢3,000 in favour of the Plaintiff.

 

 

                    

                                                              (SGD)                                                                                  BARBARA ACKAH-YENSU (J)

JUSTICE OF THE HIGH COURT

 

 

COUNSEL                             YAW SARPONG BOATENG - PLAINTIFF

 

                                                OFORI ADUENI   -  DEFENDANT

 

 
 

Legal Library Services        Copyright - 2003 All Rights Reserved.