GHANA LAW FINDER

                         

Self help guide to the Law

  Easy to use   Case and Subject matter index  and more tonykaddy@yahoo.co.uk
                

HOME

IN THE HIGH COURT OF JUSTICE ACCRA COMMERCIAL DIVISION,

HELD ON THURSDAY THE 22ND DAY OF FEBRUARY 2007

 

SUIT NO                      BDC / 8/ 06

    SMICE INTERNATIONAL LIMITED               

                                       VRS.

                            P & D LIMITED

 

 

 MARGARET INSAIDOO J (MS).

 

JUDGMENT

PRELIMINARY REMARKS

This court unfortunately was not assisted with "all" the evidence as it were. The reason being that although the defendant filed a defence and a counterclaim, and despite the fact that it was represented in court a few times, and also the fact that there is evidence on record that it had been served with copies of the proceedings to enable it cross- examine the plaintiff, the defendant failed and or refused to attend court. The court was thus constrained to proceed without the defendant's input. The court inferred from the conduct of the defendant that it had waived its right to give evidence. From June 2006, to 22nd January 2007, several notices, faxes, telephone and email messages were sent to the defendant and or defendant's solicitor, but no response was received. There is on record an affidavit of non-service dated 2nd February 2007 that indicates that the defendant company had been closed down. The court thus feels justified in delivering this judgment.

THE BRIEF FACTS

In August 2004, the defendant had an agreement for the hire or lease of the Plaintiff's caterpillar bulldozer (D9R Dozer) to work on the Defendant's project site at Newmont Mining Company at Ahafo-Kenyase in the Brong Ahafo region of the Republic of Ghana. It was agreed that the rate for the lease would be one hundred and twenty dollars ($120) per hour. The hourly meter reading of the machine at the start of the lease was 14060 hours.

Due to the urgent nature of the work to be done, it was agreed that the machine would be released to the defendant on 9th August 2004 before the formal execution of the contract by the parties on 1ih August 2004.

It was agreed that the plaintiff would have an operator on site to supervise the operation of the said machine while being used by the defendant.

Contrary to the agreement, the defendant started operating the machine even before the plaintiff's operator arrived on site. As a result of this it found that the hydraulic pump of the machine had failed after 42 hours of use and was repaired by the defendant at a cost of ¢35 million cedis.

On 16th November 2004, the plaintiff decided to withdraw the machine from the defendant's project site because the defendant persistently failed to pay the accumulated charges for the use of the machine. At the time the plaintiff withdrew the machine from the site, the meter reading was 14,356 hours. This

meant that the defendant had used the machine for two hundred and ninety six (296) hours. This translates into an amount of $35,520.00.

The plaintiff's claim against the defendant is for an amount of $35,520.00 or its cedi equivalent and interest on the said sum at the current bank rate with effect from 18th November 2004 to date of final payment.

The Defendant basically agreed with the facts as stated by the Plaintiff, it however claimed that soon after delivery of the machine it broke down and all attempts to contact a responsible officer of the Plaintiff Company to address the issue failed with the ostensible reason that the Managing Director had then travelled to the United States.

The Defendant in it statement of Defence said that it was forced to undertake major repairs on the machine before it could start using it. Additionally, the operator that the Plaintiff was supposed to provide came to the site only at the time the machine was being repaired. He never returned thereafter forcing the Defendant to employ an operator at extra cost.

The Plaintiff faxed an invoice to the Defendant on 12/11/04 and on 18/11/04 the Plaintiff withdrew the machine after it had authorized Naachiaa Plant Pool Limited to take possession of it by letter dated 16/11/04.

As a result of the Plaintiff's precipitate withdrawal of the machine the Defendant averred that it was forced to hire a replacement machine at the same rate. According to the defendant, the cost of repairing and maintaining the Plaintiff's machine came to US$32,lOO.00.

The defendant denied that it had utilized the machine up to the number of hours that the plaintiff was claiming that the time-clock shows the number of hours the machine is switched on including stand by and stand-down time, time spent greasing and fuelling the machine, testing of hydraulics and transmission in situ and performance testing totaling up to ten per centum of the number of hours shown on the meter.

The defendant claimed that it had incurred losses as a result of the plaintiff's precipitate withdrawal of the machine. It therefore asked for a set off in the sum of $32,100 being cost incurred by it in repairing the machine. It also counterclaimed for general damages for breach of contract.

ISSUES FOR TRIAL

I)                                Whether or not the Plaintiff was to maintain and keep the machine in a good state of repair and condition to ensure optimum availability to carry out the contract and the plaintiff as a result was to provide an operator for the machine.

II. Whether or not the hire rate was inclusive of VAT, NHIL and withholding tax to be paid 30 days following receipt of a VAT invoice.

                  III.   Whether or not the machine broke down soon after delivery and

whether or not a responsible officer of the plaintiff company was got to address the problem.

                  IV. Whether or not the defendant company employed an operator at an

extra cost.

                  V. Whether or not there was a breach of contract by the plaintiff.

VI.             Whether or not the defendant is entitled to a set off of $32,100,000.

VII.            Whether or not the Defendant is entitled to its counterclaim.

VIII.            Whether or not the Defendant operated the machine for 296 hours.

IX.             Whether or not the Defendant was entitled to repair the machine

without the express approval of the plaintiff.

X.              Whether or not the cost of the repair to the machine was $32,100.00.

XI.             Whether or not the defendant owes the plaintiff $35,520.00 being the

cost of the use of the machine for 296 hours.

EVIDENCE ADDUCED AT THE TRIAL

Has the plaintiff adduced sufficient evidence in accordance with the Evidence Decree,1975 (NRCD323)? Is the evidence sufficient to the extent that a reasonable mind could hold that the existence of a fact in issue was more probable than its non-existence?

The Plaintiff's case was presented by its director of operations, Nick K. Baffour. The witness testified that the plaintiff normally has an agreement signed before the machine is rented, but, the defendant stated that its contract was under threat if the machine was not sent to his site immediately and so the plaintiff sent the machine to the site on a Sunday. He was supposed to sign within the

week but the defendant never did for all the three months duration that the machine was with the defendant.

He stated that the machine was run for forty two (42) hours and then it broke down where the hydraulic pump failed.

The terms of the agreement included the fact that the machine would be on lease for $120 per hour of operation. The plaintiff would maintain the machine and the defendant was to provide fuel.

At the time that the machine was retrieved from the defendant's project site, the meter reading was 14,356 hours.

In addition, one of the terms of engagement was that if the defendant kept the machine idle without operating for a certain number of hours, the defendant was supposed to pay at least half rate; but he did not agree to that. According to the witness, that was the reason why the defendant failed and or refused to sign the agreement.

Exhibit "A" dated 21-10-04 was a pro-forma invoice from Tractor and Equipment addressed to the plaintiff. "A1" was the receipt from the Tractor and Equipment in the sum of ¢48,769,535.00 cedis. The defendant informed the plaintiff that it could obtain a cheaper pump from Italy for three thousand dollars ($3,000.00). The plaintiff asked the defendant to provide a pro-forma invoice so that they would approve the purchase. The defendant never got back to the plaintiff on this issue. Consequently, the plaintiff recalled it operator from the site in order that no one would have access to the machine.

The plaintiff then bought the parts from Tractor and Equipment and had the pump repaired to the tune of ¢48,769,535.00. On returning the repaired pump to the site, the plaintiff realized that the machine had been run for 296 hours after it had broken down. The plaintiff realized that the defendant had "quietly gone and repaired the machine without our operator's presence and knowledge".

Exhibit "C" was tendered in evidence. These were the letters written to the defendant by the plaintiff demanding payment for the hours that the machine had been run. However, the defendant refused to settle the amount demanded by the plaintiff. The plaintiff decided to withdraw the machine from the site.

The plaintiff was therefore claiming:

      i)          $35,520.00 less $3000 being the cost of repair by the Defendant and

      ii)         interest

 

ISSUES

1)                Whether or not the Plaintiff was to maintain and keep the machine in a good state of repair and condition to ensure optimum availability to carry out the contract and the plaintiff as a result was to provide an operator for the machine.

The plaintiff was to provide an operator for the machine but the defendant should report any repairs so that the plaintiff's would see to the repairs himself.

2)                 Whether or not the hire rate was inclusive of VAT, NHIL and withholding tax to be paid 30 days following receipt of a VAT invoice.

The plaintiff's response was that the defendant would pay the plaintiff "every two weeks in advance from the 1st day of the machine leaving the premises of Smice".

Whether or not the machine broke down soon after delivery and whether or not a responsible officer of the plaintiff company was got to address the problem.

The evidence that was adduced was that, the machine was sent to the site on 8th August 2004 and the pump was faulty after 42 hours of use by the defendant. The operator of the plaintiff company was on site and tried to address the problem, but he realized that the repairs to the machine were not going to be immediate. He thus came back to the Plaintiff Company in order to effect repairs on the pump. However, no evidence was adduced as to whether or not the defendant company employed an operator at an extra cost.

The defendant in essence agreed that the machine had been used but indicated that the time clock of the machine included times when the machine was switched on including stand by and stand-down time and time spent in greasing and fuelling the machine. The plaintiff countered this by saying that the time clock only runs when the machine is actually being used.

FINAL ORDERS

I find the claim of the following as proved. The Plaintiff is not in breach on the agreement, it is rather the Defendant that has not complied with the terms of the agreement. The case of British Crane Hire Corp Ltd v. Ipswich Plant Hire, Ltd [1974J 1 All ER 1059, CA cited in support. The Judgment is therefore given in favour of the plaintiff in the sum of $35,520 dollars being the cost of the number of hours that the machine was run by the defendant.

However, the plaintiff informed the court that it repaired the pump at a cost of

48 million cedis. The plaintiff however claims that the defendant said that it

could repair the pump in Italy for $3000, the evidence before me is that the defendants repaired the pump for 35 million cedis. I therefore accept that figure of 35 million cedis and reject the figure of $32,100 being demanded by the defendants. This judgment therefore is for $35,520 less ¢35 million cedis.

COUNTERCLAIM

I dismiss the defendant counterclaim as unsubstantiated and the Defendant is therefore not entitled to his counterclaim. His claim for set off has been taken care off as above.

I award interest on the resultant sum with effect from 18th November 2004 in accordance with C1. 52 to date of final payment.

Costs of fifty million cedis (¢50,OOO,OOO.00) awarded to the plaintiffs.

 

 

(SGD.) MARGARET INSAIDOO J (MS)

 

 

 

 

Legal Library Services        Copyright - 2003 All Rights Reserved.